Chibougamau Hub-and-Spoke Complex — 2022 Technical Report

Figure 17-1: Simplified process flowsheet of the mill facilities

This report details the proposed processing design for restarting the Copper Rand mill to treat blended mineralized material from three deposits, supported by historical operating data and testwork.

Report context

This June 2022 technical report (NI 43-101) presents a preliminary economic assessment (PEA) for the Chibougamau Hub-and-Spoke Complex, owned by Doré Copper Mining Corp. The report describes recovery methods for mineralized material from the Corner Bay, Delvin, and Joe Mann deposits, processed through the Copper Rand mill, which has been closed since 2008.

Processing route

Crushing and mineral sorting

The crushing circuit is proposed for installation at the Corner Bay mine site. It comprises a grizzly feeder feeding a primary jaw crusher sized at 30 in × 42 in (76.2 cm × 106.7 cm) for a daily throughput of 3,600 t/d. The jaw crusher is rated with a connected power of 125 hp (93 kW). The crusher selection is based upon a feed size of 362 mm and a product P80 of 90 mm.

The jaw crusher product and grizzly undersize report to a single double-deck vibrating screen with a nominal feed size F80 of 64 mm. The top deck opening is 38 mm and the bottom deck opening is 10 mm. Top deck oversize is directed to the secondary cone crusher rated at 300 hp (224 kW). Bottom deck oversize reports to an integrated X-ray transmission (XRT) mineral sorter circuit. Screen undersize passes directly to the crushed material stockpile at the Copper Rand mill site.

The mineral sorter rejects low-grade and dilution material from the Devlin and Corner Bay mines. High-grade material is trucked to the Copper Rand mill site and stored in a covered stockpile under a mega-dome with approximately 50 hours of storage capacity.

Design crushing plant availability is 65%, operating for 5,690 hours per year. At full production, the crushing plant processes an average of 831.9 Kt/y of run-of-mine (ROM) material.

Grinding and gravity concentration

The grinding circuit is proposed for installation at the Copper Rand mill site. It consists of a single ball mill in closed circuit with classifying hydrocyclones. The ball mill has an installed power of 1,500 kW, reducing feed from 80% passing 8,148 µm to 1,064 µm, with a design feed of 2,240 t/d. The mill accommodates a design throughput of 2,240 t/d and a design feed rate of 93 t/h assuming a grind size of 80% passing 100 µm.

The ball mill product is sent to primary cyclones. The cyclone overflow, with a P80 of 100 µm, discharges to the flotation circuit. The underflow discharges to a distributor box, splitting into two streams: approximately two thirds of the slurry returns to the ball mill and approximately one third reports to two vibrating screens feeding two Knelson gravity concentrators operating in parallel. Gravity concentrate from the Knelson concentrators is sent directly to the final copper concentrate. Gravity tails are returned to the hydrocyclone feed pump box.

Design mill availability is 95%, operating for 8,322 hours per year. At full production, the mill processes an average of 492.8 Kt/y of mineralized material.

Flotation circuit

The ground product from the grinding circuit reports to a conditioning tank where chemical reagents are added. The conditioned material is floated to yield a copper concentrate.

The conditioning tank discharge is directed to the first rougher cell bank, comprised of one 32 m³ Maxwell 12 flotation cell. Concentrate from this cell reports directly to the third stage of cleaner flotation. Tailings report to three 20 m³ Maxwell 10 flotation cells operated in series. Nominal flotation time is 16 minutes at 42% solids density. Concentrate from these second rougher cells reports to the first stage of cleaner flotation with a target grade of 10% Cu. Second rougher tailings report to the scavenger flotation cells.

Scavenger flotation consists of six 14 m³ Denver DR-500 flotation cells. Scavenger concentrate is sent to the first stage of cleaner flotation. Scavenger tailings are collected and pumped to the tailings filtration circuit.

The first cleaning stage comprises four Denver DR-300 flotation cells, each with a capacity of 8.5 m³. First cleaner concentrate reports to the second cleaning stage. First cleaner tailings are collected and pumped to the regrind ball mill, then returned to the second stage of rougher flotation.

The second stage cleaner circuit consists of four Denver DR-300 flotation cells, each with a capacity of 8.5 m³. Tailings from the second stage are recirculated to the first cleaner.

The third stage cleaner circuit consists of four Denver DR-200 flotation cells, each with a capacity of 5.1 m³. Tailings from the third bank are recycled to the second cleaner circuit. Concentrate grade is expected to be 23.7% Cu.

The flotation circuit includes a regrind ball mill and a regrind hydrocyclone.

Concentrate and tailings dewatering

The final concentrate, a combination of product from the gravity circuit and the third cleaner, is directed to an 8 m diameter concentrate dewatering thickener equipped with an agitator, then passes through a filter press that recovers concentrate with a moisture content of 8%. Copper concentrate is sent to a concentrate stockpile for transport.

Total final tailings from the scavenger circuit, at 30% solids density, are thickened and filtered to reach approximately 88% solids. The filtration plant is located in a new building next to the mill and comprises two filter presses, both operating with no standby, each with 50 chambers (3.9 m³ per chamber). Filters bring the moisture content of the filter cake to 12%. Filtrate and wash water are collected and pumped back to the process. Filter cake is discharged onto a conveyor to a stockpile, then loaded onto trucks and transported to the dry stack tailings facility (TMF).

Plant modifications and ramp-up

Several modifications are proposed to the existing Copper Rand processing plant to accommodate treatment of three different mineralized material sources. These include decommissioning of the existing crushing and grinding sections; addition of a new crushing circuit at Corner Bay including a mineral sorter; addition of a new grinding circuit; addition of a conditioning tank; expanded capacity of the concentrate filter; addition of a new tailings filter plant; and reconfiguration of piping around the flotation circuit.

From Year 4 to Year 7, an increase in tonnage is expected with increased mined tonnes from Corner Bay and processing of Joe Mann material. At Year 3, additional capacity will be added at the rougher and cleaner flotation stages to accommodate this increase, including a new 50 m³ rougher tank cell and additional cells to the existing cleaner flotation banks.

Consumables and process water

Primary reagents include collector KAX51 (131 t/y), collector R208 (7 t/y), frother MIBC (25 t/y), hydrated lime (830 t/y), and flocculant (14 t/y). Grinding media consumption is 339 t/y of 50 mm diameter balls for the primary ball mill and 68 t/y of 25 mm diameter balls for the regrind ball mill. Consumption rates are mostly based upon historical operational data.

Process water is provided by recirculation from thickener overflows, surface water, or reclaim water. The process water system supplies the grinding, flotation, and dewatering circuits. Fresh water from surface sources or tailings pond reclaim supplies reagent preparation and equipment gland seals.

Concentrator personnel

A total of 72 employees are required in the process plant, comprising 12 salaried staff and 60 hourly workers. The crushing plant requires 10 hourly workers; the processing plant requires 50 hourly workers.

Electricity

Average power demand is estimated at 40.75 GWh for both the crushing and process plants, based on Hydro-Québec’s average cost of $0.0527/kWh.

Key reported parameters

Parameter Unit Value
General design data
Process plant operating life y 11
Crusher plant availability % 65
Crusher operating hours per year hr 5,690
Mill availability % 95
Mill operating hours per year hr 8,322
Crushing plant feed
Average yearly ROM feed t/y 831,883
Design hourly feed tonnage t/h 220
Average hourly feed tonnage t/h 146
Average ROM grade % Cu 2.61
Mill feed and production
Design mill feed t/h 93
Average mill feed t/h 56
Average yearly mill feed t/y 492,750
Average mill feed grade % Cu 4.71
Average concentrate production t/y 85,475
Average concentrate grade % Cu 23.7
Concentrate humidity % H₂O 8
Copper recovery (Corner Bay)
Overall crushing and sorting copper recovery (A) % 96.4
Gravity and flotation copper recovery (B) % 96.7
Overall copper recovery (A × B) % 93.2
Copper recovery (Devlin)
Overall crushing and sorting copper recovery (A) % 97.2
Gravity and flotation copper recovery (B) % 98.2
Overall copper recovery (A × B) % 95.5
Copper recovery (Joe Mann)
Gravity and flotation copper recovery % 93.9

Project website: https://www.cygnusmetals.com/chibougamau-camp/

Note: The overall combined recovery of the mineral sorter and mill is stated as 93.3% copper in the report text. Table 17-1 reports overall recovery for Corner Bay at 93.2%, Devlin at 95.5%, and Joe Mann at 93.9% (gravity and flotation only; no sorting recovery is reported for Joe Mann).

Technical qualifications

The recovery methods described in this report were established on the basis of historical operational data and testwork as described in Section 13 of the report, equipment information from suppliers, and engineering experience on similar projects. The work forms the basis of the plant design, capital costs, and operating costs developed in this study. All sizing was made to accommodate the highest throughput from ROM with a design factor of 15%. Operating costs are based on average crusher and mill feed over the life of mine. The report presents a preliminary economic assessment and is not a feasibility study.

Source: Doré Copper Mining Corp., NI 43-101 Technical Report, PEA for the Chibougamau Hub-and-Spoke Complex, June 2022, Sections 1.16 and 17.

Mineral processing basics

Scroll to Top