Source: Caledonia Mining Corporation Plc (2026)
Website: https://www.caledoniamining.com/operations/bilboes/
Critical Data
| Parameter | Value | Unit | Notes |
|---|---|---|---|
| Throughput (Phase 1 Isabella McCays) | 2,880,000 | tpa | 240,000 tpm; plant designed for monthly tonnage |
| Throughput (Phase 2 Bubi) | 2,160,000 | tpa | 180,000 tpm due to harder ore |
| Target Grind Size (P80) | 75 | μm | Product size from milling/cyclone overflow |
| Crushed Ore P80 | 20 | mm | Feed to ball mill from 2-stage crushing |
| Ball Mill Work Index (Isabella McCays) | 16.82 | kWh/t | Bond ball work index average |
| Ball Mill Work Index (Bubi) | 21.67 | kWh/t | Bond ball work index average |
| Head Grade Au (Isabella McCays) | 2.54 | g/t | Average feed grade |
| Head Grade Au (Bubi) | 2.43 | g/t | Average feed grade |
| Sulphide Content (Isabella McCays) | 0.77 | % | Average |
| Sulphide Content (Bubi) | 2.64 | % | Average |
| Flotation Mass Pull (Isabella McCays) | 5 | % | Concentrate mass as % of feed |
| Flotation Mass Pull (Bubi) | 10 | % | Concentrate mass as % of feed |
| BIOX® Residence Time | 6.5 | days | Total in primary and secondary reactors |
| CIL Residence Time | 36 | hours | Slurry residence in CIL circuit |
| Gold Dissolution (CIL) | 99 | % | Absorbed onto activated carbon |
| Elution Cycle Time | 10 | hours | Including acid wash, soak, and elution |
| Raw Water Requirement (Phase 1) | 5,300 | m³/day | From Bafana dam |
| Process Water Make-up (Phase 2) | 3,300 | m³/day | From raw water to maintain balance |
| Specific Gravity (Isabella McCays) | 2.78 | t/m³ | Average |
| Specific Gravity (Bubi) | 2.85 | t/m³ | Average |
| WAD Cyanide Limit (Tailings) | 50 | ppm | After detoxification using INCO process |
Overview
Caledonia Mining Corporation Plc, through its feasibility study for the Bilboes Gold Project in Zimbabwe, has designed an advanced processing plant to recover gold from refractory sulphide ores. Located at the Isabella McCays complex, with ore trucked 23 km from the Bubi deposit, the facility will process up to 2.88 million tonnes per annum in Phase 1 (Isabella McCays) and 2.16 million tpa in Phase 2 (Bubi). The project, with an effective date of 31 October 2025, addresses the challenge of ultrafine gold particles encapsulated in sulphide minerals. The selected recovery method integrates comminution, flotation, Metso’s proprietary BIOX® biological oxidation, carbon-in-leach (CIL), carbon treatment, and electrowinning. This multi-stage approach ensures maximum liberation of gold from the refractory matrix. The plant design incorporates a two-stage crushing circuit, ball milling to a P80 of 75 microns, flotation to concentrate sulphides, and a 6.5-day BIOX® residence time for bacterial sulphide destruction. Gold dissolution in CIL achieves approximately 99% recovery onto activated carbon, followed by elution and electrowinning to produce gold doré. The process is designed to handle varying ore characteristics, with average head grades of 2.54 g/t Au at Isabella McCays and 2.43 g/t Au at Bubi, and sulphide contents of 0.77% and 2.64% respectively. The project’s significance lies in its use of proven biological oxidation technology to treat refractory gold ores in Zimbabwe, supported by a robust water supply from Bafana dam and a 132 kV overhead power line.
Key Process Stages
- Stage 1: Comminution – Crushing & Milling: Run-of-mine ore (650 mm top size) is fed to a primary jaw crusher via a vibrating grizzly feeder (150 mm aperture). The secondary cone crushers operate in closed circuit with a double-deck screen (30 mm aperture) to produce a crushed ore stockpile with a live capacity of 24 hours (26,000 tonnes). Milling is performed by a grate-discharge ball mill with steel liners and forged Cr-Mo steel balls (80 mm diameter). Cyclone classification targets a product P80 of 75 microns; the circuit processes 240,000 tpm for Isabella McCays and 180,000 tpm for Bubi due to harder ore (Bond ball work index 16.82 vs 21.67 kWh/t).
- Stage 2: Flotation – Sulphide & Gold Concentration: Cyclone overflow (P80 75 µm) enters a conditioning tank where process water, collector (Sodium Ethyl Xanthate), activator (copper sulphate), and depressants (starch, sodium carbonate) are added. The circuit operates at natural pH in a rougher-cleaner-recleaner-cleaner scavenger configuration. Mass pull is 5% for Isabella McCays and 10% for Bubi. Rougher tails report to neutralisation, while recleaner concentrate is thickened (thickener) and fed to the BIOX® circuit. Water recovery is recycled to process water pond.
- Stage 3: BIOX® Biological Oxidation: Thickened flotation concentrate (≈18% solids) enters two parallel primary reactors followed by three series secondary reactors (total residence time 6.5 days). Mesophilic bacteria (40–45°C) oxidize sulphides at pH 1.2–1.6, controlled by sulfuric acid addition. Oxygen and CO₂ are supplied via medium-pressure blowers (250 kPa) with 15% air hold-up. Temperature is maintained at ~42°C using cooling coils. Oxidized slurry exits to a 3-stage counter-current decantation (CCD) circuit where acidic solution is separated from solids (washed with makeup water). Acidic overflow is neutralized with limestone (Phase 2) and lime to pH 7, precipitating arsenic as basic ferric arsenate. Neutralized slurry is thickened and sent to the flotation tailings storage facility.
- Stage 4: Carbon-in-Leach (CIL): Washed BIOX® product (CCD underflow) is first pH-adjusted with lime and aerated in CIL tank 1 to oxidize cyanide consumers. From tank 2 onward, sodium cyanide is added and activated carbon (retained by interstage screens) adsorbs dissolved gold. Total slurry residence time is 36 hours, achieving ~99% gold loading onto carbon. Carbon is moved counter-currently upstream; loaded carbon from tank 2 is screened and sent to acid wash. Barren slurry is detoxified to WAD cyanide <50 ppm using the INCO SO₂/air process (SMBS, copper sulphate, lime) before disposal to the BIOX® tailings storage facility.
- Stage 5: Carbon Treatment, Electrowinning & Smelting: Loaded carbon (5-tonne batches) undergoes acid wash (3% HCl, 1 hour) to remove calcium, then is eluted using the split AARL method (1% NaCN, 2% NaOH at 110–125°C, 4–5 hours). The gold-bearing eluate feeds two electrowinning cells (each with 16 cathodes of stainless steel mesh, 18 anodes) operating at up to 2,000 A DC over 12 hours. Gold is stripped from cathodes by high-pressure water jets, filtered, dried, and smelted at 1,100°C with fluxes (borax, silica, sodium carbonate) in an electric furnace. Barren carbon is regenerated at 750°C in an electrically heated rotary kiln before returning to CIL.
Additional Interesting Data and Summary
The Bilboes Gold Project’s processing plant is designed to treat refractory gold ores from two deposits: Isabella McCays (Phase 1, years 1–6) and Bubi (Phase 2, years 6–11). The ore bodies exhibit distinct metallurgical characteristics; Bubi ore has higher sulphide content (2.64% vs 0.77%) and greater hardness (Bond work index 21.67 vs 16.82 kWh/t), necessitating phased throughput reduction from 240,000 tpm to 180,000 tpm. The flotation circuit achieves a mass pull of 5–10%, concentrating sulphides for BIOX® treatment. The biological oxidation stage uses mesophilic bacteria at 42°C and pH 1.2–1.6, with a 6.5-day residence time, and includes a CCD washing circuit to separate acidic solution. Neutralisation of acidic effluents is a key environmental control: Phase 1 uses lime only, while Phase 2 requires a dedicated limestone milling circuit to handle the higher acid load from Bubi ore. Arsenic is fixed as basic ferric arsenate, a stable precipitate. Water management is critical: raw water from Bafana dam (5,300 m³/day in Phase 1) supports the process, with a 10,400 m³ process water dam for recycle. The water balance is negative, requiring 3,300 m³/day make-up in Phase 2. Reagents are imported except locally sourced limestone; the plant uses sodium ethyl xanthate, copper sulphate, sulphuric acid, sodium cyanide, caustic soda, hydrochloric acid, and sodium metabisulphite. The gold recovery circuit achieves over 99% gold dissolution in CIL, with electrowinning and smelting producing doré bars. Tailings are detoxified to <50 ppm WAD cyanide using the INCO SO₂/air process before disposal in a dedicated BIOX® tailings storage facility. Sustainability initiatives include recycling process water, fixing arsenic in stable form, and using a 132 kV overhead line for reliable power. The feasibility study, effective 31 October 2025, confirms the technical and economic viability of applying BIOX® technology to Zimbabwean refractory gold ores, positioning Caledonia Mining for long-term production from a complex, high-grade resource.
Key Processes: Flotation, CIP/CIL, Cyanidation, Gravity Separation, Ball Mill, Crushing
Target Commodities: Gold, Copper
Technical report and processing history
The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.
Bilboes Gold Project — Feasibility Study Technical Report
Bilboes Gold Project — Feasibility Study Technical Report
| Company | Bilboes Holdings (Pvt) Limited |
| Date | 2021 |
| Region | Matabeleland North Province, Zimbabwe |
Executive Summary
Bilboes Holdings (Pvt) Limited is a private gold-focussed mining and exploration company registered in Zimbabwe. The Bilboes Gold Project comprises four open-pit mining properties (Isabella North, Isabella South, McCays, and Bubi) located approximately 80-100 km north and northeast of Bulawayo. The project is undergoing feasibility study for the extraction of sulphide ore using a conventional truck and shovel open-pit mining method followed by flotation, biological oxidation (BIOX®), and carbon-in-leach (CIL) processing to recover gold.
The project has a total Mineral Reserve of 26.6 Mt at 2.29 g/t Au containing approximately 1.96 million ounces of gold. The mine is designed with a two-phase processing strategy: Phase 1 processes 2.88 Mtpa from Isabella McCays for years 1-6, while Phase 2 processes 2.16 Mtpa from Bubi for years 6-11. The processing plant will utilize a proven flowsheet comprising crushing, milling, flotation, BIOX® biological oxidation, CIL cyanidation, carbon treatment, electrowinning, and smelting. Projected gold recovery is 90.0% for Isabella McCays ore and 91.1% for Bubi ore. The project shows strong economics with an IRR of 38.4% (pre-tax) and NPV of $440 million at a 10% discount rate.
Key Project Parameters
- Mine Type: Open Pit
- Processing Throughput: Phase 1: 240 ktpm; Phase 2: 180 ktpm
- Mine Life: ~10.8 years
- Status: Feasibility Study / Development
- Ore Type: Sulphide (refractory)
- Commodity: Gold
- Annual Production: ~200,000 oz Au
- Head Grade: Isabella McCays: 2.51 g/t; Bubi: 1.80 g/t
Reports
Website: https://www.caledoniamining.com/operations/bilboes/
Report Date: 2021
Region: Matabeleland North Province, Zimbabwe
Project Status:
Commodity:
Throughput:
Mine Life:
Mine Type:
Ore type:
Bilboes Gold Project — Preliminary Economic Assessment
Bilboes Gold Project — Preliminary Economic Assessment
| Company | Not Specified |
| Date | Unknown |
| Region | Zimbabwe |
| Commodities | Gold |
Executive Summary
This Preliminary Economic Assessment details the recovery methods for the Bilboes Gold Project, located in Zimbabwe. The project involves mining from two main areas, Isabella McCays and Bubi, utilizing an open pit mining method. The ore is characterized as transitional and sulphide, with gold particles being ultrafine and encapsulated within sulphide minerals, making it refractory to standard free milling processes.
The selected processing plant design incorporates a biological sulphide destruction step using the Outotec proprietary BIOX® process to liberate the gold particles. Following biological oxidation, the gold is recovered via a Carbon-in-Leach (CIL) circuit. The plant is designed for a phased operation over a 10-year life of mine, with Phase 1 focusing on Isabella McCays (2,880,000 tpa) and Phase 2 on Bubi (2,160,000 tpa).
Key operational parameters include a primary jaw and secondary cone crushing circuit, followed by a ball mill grinding circuit producing a P80 of 75 microns. Flotation is used to concentrate sulphides and gold before biological oxidation. The process also includes carbon treatment, electrowinning, smelting, and tailings detoxification using the INCO SO2/Air process to manage cyanide levels.
Reports
Website: https://www.caledoniamining.com/operations/bilboes/
Report Date: Unknown
Region: Zimbabwe
Project Status:
Commodity: Gold
Throughput:
Mine Life:
Mine Type:
Ore type:
Bilboes Gold Project Feasibility Study
Bilboes Gold Project Feasibility Study
| Company | Bilboes Gold Project |
| Date | Unknown |
| Region | Zimbabwe |
| Commodities | Gold |
| Mine Type | Open Pit |
| Throughput | 2,880,000 tpa (Phase 1) |
| Mine Life | 11 years |
| Status | Development |
Executive Summary
This Technical Report outlines the Feasibility Study for the Bilboes Gold Project located in Zimbabwe. The project focuses on the recovery of gold from refractory sulphide ore bodies, specifically the Isabella McCays and Bubi deposits. Due to the ultrafine gold particles being encapsulated within sulphide minerals, the selected process design incorporates a biological sulphide destruction step using the Metso proprietary BIOX® process to liberate the gold before cyanide leaching in a Carbon-in-Leach (CIL) circuit.
The plant is designed with a phased approach to handle varying ore characteristics and tonnages over the Life of Mine (LoM). Phase 1 targets the Isabella McCays deposit with an annual throughput of 2,880,000 tonnes per annum (tpa) and an average head grade of 2.54 g/t Au. Phase 2 will process the Bubi deposit with a throughput of 2,160,000 tpa and a head grade of 2.43 g/t Au. The total mine life is approximately 11 years, with the processing plant situated at the Isabella McCays complex.
The processing plant layout includes comminution, flotation, biological oxidation, CIL, carbon treatment, electrowinning, and smelting sections. Key infrastructure includes a primary jaw crusher, secondary cone crushers, a ball mill circuit, and a BIOX® section utilizing mesophilic bacteria. The process ensures complete cyanide destruction in tailings and efficient gold recovery through activated carbon elution and smelting into doré bars.
Website: https://www.caledoniamining.com/operations/bilboes/
Report Date: Unknown
Region: Zimbabwe
Project Status: Development
Commodity: Gold
Throughput: 2,880,000 tpa (Phase 1)
Mine Life: 11 years
Mine Type: Open Pit
Ore type:


