Copper Mountain Mine 65 kt/d Expansion Study and Life-of-Mine Plan

This report describes a proposed expansion of the Copper Mountain mill to 65 kt/d through installation of a high-pressure grinding roll and fourth ball mill, with a corresponding life-of-mine plan.

Report context

The technical report, effective September 1, 2020, was prepared for Copper Mountain Mining Corporation to document the 65 kt/d expansion study and life-of-mine plan for the Copper Mountain Mine. The study assumes that the Ball Mill #3 expansion, an ongoing project that will add a third ball mill in parallel with the two existing mills and reduce grind size to 150 µm, is complete. The expansion examined in this report involves installation of an HPGR and a fourth ball mill to enable 65 kt/d throughput at a target grind size P80 of 165 µm. The current mill capacity is 40 kt/d. The report presents design inputs, comminution circuit configuration, and flotation circuit design for the proposed expansion.

Processing route

Current flowsheet basis

The existing Copper Mountain mill flowsheet is described as a relatively simple two-stage crushing, SAG, pebble crusher, ball milling, and sulphide flotation circuit design, currently supporting 40 kt/d of ore processing. The Ball Mill #3 expansion underway will add a third ball mill in parallel with the two existing ball mills. Table 1-7 in the report provides 65 kt/d plant design inputs on the basis that the Ball Mill #3 expansion is complete.

Proposed 65 kt/d comminution circuit design

A 60–89 primary crusher receives run-of-mine ore and reduces material to less than 143 mm. Product is sent to a 14 ft by 24 ft double-deck screen, with oversize material feeding an XL2000 cone crusher operating in open circuit. Because of the maximum top size allowed at the new downstream HPGR, the open screening format will be closed with a security screen that scalps material greater than 90 mm. This oversized material is returned to the secondary crusher feed stockpile. A final crusher product with P80 of 38 mm is then sent to a 164 kt capacity ore stockpile.

The fine ore stockpile will use existing apron feeders to transfer to a modified SAG feed conveyor, serving as the transition point to the new HPGR circuit. A chute will allow material to be sent directly to the HPGR or to the existing SAG, which will remain on standby. The HPGR, installed in a new building serviced by a 160-t crane, will operate in a closed loop with a screening plant. Three parallel 14 ft by 24 ft double-deck screens will wet screen the HPGR product to a 4 mm P80 product size. Fine ore bins above the screens will allow for 30 minutes of operating time if the HPGR is down for inspections or maintenance. Screen undersize material will be pumped to each of the two lines of ball mills.

Ball Mill #4, a 22 ft by 38 ft mill with 12.6 MW of installed power, will be installed adjacent to Ball Mill #3 within the existing building, in the location where the existing regrind mill is currently positioned. The regrind mill will be demolished in this plan. With the addition of Ball Mill #4, the ball milling line will comprise four mills operating in parallel: two identical 24 ft by 30 ft mills and two identical 22 ft by 38 ft mills, designated Lines 1 and 2, respectively. Each line of mills will supply flow to independent rougher flotation lines. The total installed power will allow for an average target grind size of 165 µm.

Proposed flotation circuit design

The existing rougher flotation circuit, with two banks of five 160 m³ tank cells, will receive flow from ball mill Line 2. A new building erected at the northeast corner of the existing concentrator will house additional flotation equipment for the expansion, as specified in the report's flowsheet design.

Key reported parameters

Parameter Unit Value
Daily throughput (design) kt/d 65
Crushing plant operating time (design) % 80
HPGR, milling and flotation availability (design) % 93
Crushing plant nominal throughput (design) t/oph 3,385
HPGR, milling and flotation nominal throughput (design) t/oph 2,912
Head grade (design) % Cu 0.30
Rougher recovery (design) % Cu 87.2
Cleaner recovery (design) % Cu 98
Overall recovery (design) % Cu 85.5
Concentrate grade (design) % Cu 28
Concentrate production (design) t/oph 26.7
Concentrate moisture (design) % w/w 8.5
Current mill capacity (actual) kt/d 40
Target grind size after Ball Mill #3 expansion (planned) µm 150
Target grind size after 65 kt/d expansion (proposed design) µm P80 165
Final crusher product size (proposed design) mm P80 38
HPGR product size (proposed design) mm P80 4
Ball Mill #4 installed power (proposed design) MW 12.6

Project website: https://hudbaycoppermountain.com/

Technical qualifications

The report does not include specific details on metallurgical testwork, pilot plant results, or ore characterization studies underpinning the recovery and grind size assumptions. The 65 kt/d design inputs in Table 1-7 are presented on the basis that the Ball Mill #3 expansion is complete, and the report notes the regrind mill will be demolished as part of the proposed plan. No information is provided on capital or operating cost estimates, economic analysis, environmental permitting, or project execution schedule. The report does not present historical operating data comparisons or testwork results beyond the general description of the existing flowsheet. Performance projections for the HPGR circuit and fourth ball mill are design basis values only and have not been confirmed by operating experience at this configuration.

Source: Copper Mountain Mine 65 kt/d Expansion Study and Life-of-Mine Plan, NI 43-101 Technical Report, effective date September 1, 2020, Section 1.17 Recovery Methods.

Consolidated report summaries

The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

NI 43-101 Technical Report — 2024

NI 43-101 Technical Report — 2024

Company Unknown
Mine Unknown
Region British Columbia, Canada
Commodities Copper, Silver, Gold

Executive Summary

This technical report section outlines the recovery methods and processing plant specifications for a copper-silver-gold sulphide operation. The facility utilizes a standard crush-grind-flotation circuit designed to operate two 12-hour shifts daily, 365 days a year, with a targeted plant availability of 92%. The installed capacity is planned to be stabilized at 45 kilotonnes per day (kt/d) throughout 2024 and 2025, with a subsequent expansion to 50 kt/d by 2027.

The comminution circuit employs a primary and secondary crushing stage to reduce feed size to minus 40 mm before processing through a semi-autogenous grinding mill, ball mill, and pebble crusher circuit. This reduces the feed size to a P80 of 150 micrometers. The resulting slurry enters a sulphide flotation circuit which produces a copper-silver-gold concentrate. The concentrate is dewatered using pressure filters and stored on-site prior to transport via truck to the Port of Vancouver for shipment.

Operational plans indicate a ramp-up schedule where throughput will increase from 41.1 kt/d in 2024 to 50.0 kt/d by 2027. This expansion involves minor capital upgrades to remove bottlenecks in the primary and secondary crushing circuits rather than adding major new equipment. Recovery rates for copper and gold are projected to improve slightly over this period, with copper recovery targeting 86% and gold recovery targeting 68% by 2027.

Website: https://en.wikipedia.org/wiki/There_are_unknown_unknowns

Report Date: 

Region: British Columbia, Canada

Project Status:

Commodity: Copper, Silver, Gold

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Mineral processing basics

Scroll to Top