Diablillos Project — 2025 Technical Report

The Diablillos Project is a gold-silver mineralized material processing operation designed to treat up to 9,000 metric tons per day of oxide material from the Oculto and JAC deposits in Salta and Catamarca Provinces, Argentina, using a combination of gravity concentration, cyanidation, and the Merrill-Crowe process.

Report context

This process description is based on the NI 43-101 Technical Report for the Diablillos Project, which was carried over in its entirety from the previous Updated Pre-Feasibility Study effective December 3, 2024, with report date January 17, 2025, as incorporated in the Mineral Resource Estimate for the project.

Processing route

Comminution and crushing

The plant begins with a primary jaw crushing station operating in open circuit with an open side setting of 152 mm, producing a product with a nominal P80 of 150 mm and a top size of 254 mm. Material is reclaimed from an enclosed coarse ore stockpile with a live capacity of 13,000 metric tons and total capacity of approximately 52,000 metric tons, via two variable speed belt feeders, one operating and one standby. Pebble lime is metered onto the stockpile feed conveyor to maintain alkalinity in the grinding circuit.

Grinding circuit

Grinding is accomplished in a semi-autogenous grinding (SAG) mill followed by a ball mill, with SAG oversize pebble crushing. The SAG mill is 7.92 m in diameter with an effective grinding length of 3.66 m, equipped with a 4,500-kW variable speed drive. The ball mill is 5.49 m in diameter with an effective length of 8.53 m. The circuit is designed for a nominal rate of 391 metric tons per hour with a final grind size of P80 of 150 microns. The pebble screen aperture is 10 mm, with the pebble recycle rate typically 15% to 35% of SAG fresh feed rate.

Gravity concentration and intensive leaching

A portion of the cyclone underflow is treated by two gravity concentrators, with a mass pull of approximately 190 kg per hour. Gravity concentrate is treated in an intensive cyanidation reactor, with the pregnant solution reporting to the Merrill-Crowe pregnant solution tank. The intensive leach residue reports by gravity to the ball mill feed. Testwork indicates that 10.1% of gold and 7.8% of silver are recovered to gravity concentrate for Oculto material, and 17.3% of gold and 9.1% of silver for JAC material.

Tank leaching

Slurry from the pre-leach thickener is leached in a series of eight tanks (15 m diameter, 20 m height) at 36 hours total retention time, with pH controlled above 10.5 using lime. Sodium cyanide is dosed to maintain a free cyanide concentration of approximately 1.5 g/L, with concentration allowed to decay in the last two tanks. The expected gold recovery is approximately 83% and silver recovery approximately 80% based on laboratory testing.

Counter current decantation (CCD) circuit

The CCD circuit recovers dissolved gold and silver to the pregnant solution. For Oculto material, six stages of CCD thickeners are used; for JAC material, seven stages are required due to higher viscosity and solution flow. The CCD wash ratio is controlled at 3.0, with underflow density approximately 55% solids by weight. The first CCD thickener has a diameter of 32 m and the remaining units 30 m in diameter; for JAC material the first is 40 m and the rest 38 m. The reported recovery of gold and silver in solution to the pregnant solution is approximately 99.6%.

Merrill-Crowe circuit

The pregnant solution is clarified using diatomaceous earth, with a DE precoat of approximately 3 mm thickness and body feed at a target slurry density around 7% solids. Four DE clarifiers are installed, with three operating and one on standby. TSS levels are controlled to below 100 ppm in the pregnant solution, with the clarified solution typically below 1 ppm TSS.

The clarified solution passes through two deaeration towers (3.2 m diameter, 6.3 m height) to remove dissolved oxygen to below 0.5 ppm. Four cementation filter presses are included, with three operating and one standby, precoated with DE before each cycle. Zinc dust is added at the filter feed at a consumption rate of 1.5 kg per kg of gold and silver precipitated.

Foundry and mercury control

The precipitate is retorted to remove mercury and moisture, with mercury collected in flasks for shipment offsite. Dry precipitate is mixed with fluxes and smelted to produce doré bullion. A typical flux recipe for 100 kg of dry cake includes 3 to 5 kg soda ash, 5 to 10 kg borax, and 3 to 5 kg silica sand. Slag is crushed and recycled to the grinding circuit for reprocessing.

Cyanide destruction and tailings handling

Cyanide destruction uses the INCO process, with sodium metabisulfite and copper sulphate addition. The target is to reduce WAD cyanide to below 1 ppm in the final tailings. Detox residence time is one hour. Tailings are thickened to approximately 60% solids by weight for Oculto material, with a 40 m diameter tailings thickener used.

Key reported parameters

Parameter Unit Oculto JAC
Daily throughput mtpd 9,000 9,000
Operating days per year days/year 350 350
Annual throughput mtpy 3,150,000 3,150,000
Head grade, Au ppm 0.88 0.13
Head grade, Ag ppm 74 202
Final grind size microns 150 150
Leach retention time hr 36.0 36.0
Leach pH , 10.5 10.5
Gold recovery % 83.0 83.8
Silver recovery % 79.8 84.9
SAG mill power kW 4,500 4,500
Ball mill size m 5.49 x 8.53 5.49 x 8.53
Ball mill circulating load % 250 250
Cyanide consumption, total kg/mt 0.83 1.79
Lime consumption kg/mt 0.93 2.19
Sodium metabisulfite dose g/g WAD CN 4.7 4.7
Copper sulphate consumption mtph 0.02 0
DE consumption mt/day 1.4 2.7
Flocculant consumption g/mt 45 95
Zinc dust consumption kg/hr 34 102
Merrill-Crowe nominal solution flow m³/hr 1,125 1,273
CCD wash ratio , 3.0 3.0
CCD thickener underflow solids % w/w 55 50
CCD stages , 6 7
Tailings thickener underflow solids % w/w 60 55
Total plant power requirement MW ~20 ~20
Raw water requirement mtph 184 184

Project website: https://www.abrasilver.com/projects/diablillos/

Technical qualifications

The process design is based on metallurgical testwork conducted on Oculto material in 2022 and JAC material in 2023. The JAC material, representing approximately 15% of the total resource, has a different metallurgical performance, requiring larger CCD thickeners, higher lime consumption, and increased DE consumption. Testwork on JAC material resulted in different head grades and recoveries, with the plant design accommodating both ore types through equipment sizing adjustments. The design criteria incorporate a design factor of 1.15 for equipment sizing and 1.25 for conveyors and pumps. The process design is based on the recommendation of 99.5% gold and 98.5% silver recovery through the Merrill-Crowe circuit as indicated by testwork.

Source: NI 43-101 Technical Report, Mineral Resource Estimate for the Diablillos Project, Salta & Catamarca Provinces, Argentina.

Consolidated report summaries

The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

Gold-Silver Processing at Diablillos: Crushing, Grinding, and Cyanidation

The Diablillos silver-gold project, located in Salta and Catamarca Provinces, Argentina, is operated by AbraSilver Resource Corp. This high-grade deposit utilizes a conventional cyanidation process to recover gold and silver, with a designed throughput of 9,000 metric tons per day (3.15 million tons annually). The project leverages gravity concentration, intensive leaching, and Merrill-Crowe precipitation to maximize metal recovery.

  • Location: Salta & Catamarca Provinces, Argentina
  • Operator: AbraSilver Resource Corp.
  • Production: Gold (avg. 0.88 ppm) and silver (avg. 74 ppm) from oxide ore
  • Throughput: 9,000 mtpd (3.15 million mtpy)
  • Process Flow: Crushing (150 mm P80) → SAG/Ball Mill Grinding (150 µm P80) → Gravity Concentration (Falcon SB5200) → Intensive Cyanidation (SLR6000) → Tank Leaching (36 hrs) → Merrill-Crowe Precipitation → Doré Production
  • Recovery Rates: 83% Au, 80% Ag (Oculto ore); 84% Au, 85% Ag (JAC ore)
  • Key Equipment: 7.92m SAG mill, 5.49m ball mill, 6-stage CCD circuit, INCO cyanide destruction
  • Power: 20 MW hybrid system (solar + diesel/gas gensets)
  • Water: 184 mtph from wells 13 km away

Source: AbraSilver Resource Corp.

Further Reading

Diablillos Ag-Au Project: Feasibility Study Recovery Methods

AbraSilver Resource Corp.'s Diablillos project in Argentina is designed as a 9,000 tpd silver-gold operation using a conventional cyanidation flowsheet with gravity concentration, tank leaching, CCD washing, and Merrill-Crowe recovery.

The Diablillos Ag-Au Project is a feasibility-stage silver and gold project owned by AbraSilver Resource Corp., located in Argentina. The NI 43-101 technical report, with an effective date of June 19, 2026, describes a conventional open-pit mining operation with an optimized production sequence targeting high-grade silver and gold mineralization in the early years of the mine plan. The project is designed as a 9,000 tonnes per day (tpd) processing operation with feed grades ranging from 0.18 to 2.46 g/t gold and 22 to 235 g/t silver.

Critical Data

Parameter Value Unit Notes
Nameplate Capacity 9,000 tpd Design value
Crushing Plant Availability 75 % Design value
Process Plant Availability 92 % Design value
Grinding Circuit Feed Size, 80% Passing 160 mm Design value
Grinding Circuit Product Size, 80% Passing 150 µm Design value
Leach Circuit Design Retention Time 36 hours Design value
Leach Feed Design Density 45 % w/w Design value
Leach Dissolved Oxygen, Typical 10-12 ppm O₂ Test result range
Leach pH Target 10.5 – Design value
Leach Design Sodium Cyanide Addition 1.3 kg/t feed Design value
CCD Wash Water Ratio 3.0 – Design value
Cyanide Destruction Retention Time 2 hours Design value
Final Tailings Thickener Underflow Density 55 % w/w Design value
LOM Silver Recovery 80 % Average
LOM Gold Recovery 87 % Average
Total Power Requirement 22 MW Maximum demand
Raw Water Well Field Distance 13 km From mine site

Overview

The recovery methods section describes the design basis for the crushing and processing facilities at Diablillos. Flowsheet development and design criteria came from an interpretation of metallurgical testwork results completed by different laboratories between 1996 and 2025, with all results up to April 2026 considered in this feasibility study. A geo-metallurgical model segregates the deposit into five distinct domains.

Size reduction technology selection was guided by comprehensive crushing and grindability tests conducted across the entire deposit. Additional criteria included electrical power consumption, wear and spare parts usage, fine dust generation, and maintenance requirements. The chosen configuration consists of a primary jaw crusher followed by a semi-autogenous grinding (SAG) mill and a ball mill operating in closed circuit with hydrocyclone-based size classification.

A conventional flowsheet for silver and gold extraction was developed that uses gravity concentration and intensive leach, cyanide-based lixiviation, zinc cementation or electrodeposition, and smelting. A portion of the cyclone cluster underflow will be treated using gravity concentration followed by intensive leaching, which will target liberated gold and silver particles.

Tank leaching was chosen to facilitate contact of the cyclone cluster overflow with sodium cyanide, which selectively dissolves silver and gold. Sodium cyanide operates efficiently under adequate pH and temperature conditions. The process requires a minimum retention time achieved using agitated tanks that enhance reaction kinetics. pH levels will be regulated by the controlled addition of lime slurry. Continuous aeration using oxygen sparged in the tanks will ensure sufficient dissolved oxygen despite the site altitude.

Reagent and water consumption, as well as metal losses in the tailings, will be minimized through a multi-stage counter-current decantation (CCD) washing process. Each CCD stage will involve flocculant addition to improve sedimentation rates. Zinc cementation using the Merrill-Crowe process was selected for recovery of precious metals from cyanide complexes due to its suitability for ores with high silver to gold grade ratios and its capability to produce a high-quality precipitate suitable for smelting in induction furnaces.

The final product will be doré bars produced by casting in induction furnaces. Slag generated during smelting will contain measurable quantities of fine precious metals, so after granulation it will be recycled to the milling circuit for reprocessing.

Following leaching and washing, the leached slurry will undergo cyanide destruction to eliminate reactive cyanide species, including free cyanide and WAD cyanide, using the INCO/SO₂ process. The tailings will be discharged to a fully lined, multi-phase cross valley dam designed to promote separation of solid and liquid phases through natural sedimentation. Supernatant water will be pumped back to the plant, though make-up water will be required to compensate for evaporation and water retained in final tailings moisture.

Key Process Stages

Primary crushing begins with ore transported from the mine by haul trucks and dumped directly into the jaw crusher dump hopper. The hopper, with 280 tonnes of live capacity, includes a stationary grizzly to screen oversized material, which is broken down by a hydraulic rock breaker. Oversized ore exceeding 115 mm goes to the vibrating grizzly, while undersized ore bypasses to the transfer conveyor. The jaw crusher operates with a closed side setting of 150 mm, producing a product with a P80 of 160 mm and a top size of 318 mm. A trash magnet removes tramp metal before material reaches the crushed ore stockpile feed conveyor. The crushing circuit uses a dust collection system with multiple extraction hoods, ducting, and a centralized baghouse.

The crushed ore stockpile will be covered to mitigate dust propagation. Live capacity is 9,800 tonnes dry, providing 24 hours of plant feed, with total capacity of 45,370 tonnes dry. Ore will be reclaimed by two variable-speed apron feeders, each capable of handling full plant throughput for redundancy, and transferred to the SAG mill feed conveyor.

The grinding circuit feeds material from the COS to the SAG mill with the feed rate regulated by a control loop between the belt scale and reclaim apron feeders. A lime silo meters quicklime onto the conveyor to maintain an alkaline environment for pH control. Dilution water achieves a slurry density of 70% solids. The SAG mill measures 7.9 m diameter by 3.7 m effective grinding length, powered by a 5,000 kW variable speed drive, operating with a ball charge of 11 to 17% by volume. SAG mill discharge passes through a dual-deck vibrating screen that removes worn steel balls and pebbles. Screen undersize flows to the cyclone feed pumpbox where process water reduces slurry density to 55% solids.

Cyclone underflow returns to the ball mill at a circulating load of 250%, with a 50% portion diverted to the gravity concentration circuit for coarse gold recovery. The ball mill measures 5.5 m diameter by 7.9 m EGL, powered by a 5,000 kW drive, operating at 73% critical speed with up to 37% ball charge. The cyclone overflow is the final grinding product at a P80 of 150 µm, sampled for metallurgical control and monitored by an online particle size analyzer. Lead nitrate solution is introduced into the ball mill to improve leaching efficiency by modifying sulphide mineral behaviour.

The gravity concentration and intensive cyanidation circuit treats half of the cyclone underflow. Slurry is fed to scalping screens to remove particles greater than 2 mm before returning to the ball mill. Screen undersize feeds two parallel centrifugal concentrators in a semi-batch operation. Gravity concentrate is collected in a storage cone before being leached by the intensive cyanidation reactor circuit. Gravity tailings are directed back to the ball mill.

The intensive leach reactor (ILR) leach solution, a mixture of NaCN, NaOH, and an oxidant, is made up within the heated reactor vessel feed tank and circulated through the reaction vessel. Leached residue is washed and the solid gravity leach tailings are pumped back to the ball mill. ILR pregnant solution is treated in the gold room for gold recovery as gold sludge using a dedicated electrowinning cell. The gravity concentration and intensive leach area will be isolated and monitored for security purposes.

Pre-leach thickening begins with cyclone overflow passing through a trash screen and flowing via gravity to a 35 m pre-leach thickener. Thickener overflow reports to the process water tank, while underflow at 55% w/w solids is pumped to the leach tanks where slurry density is adjusted to 45% w/w solids with barren leach solution. Flocculant is added to improve settling, and antiscalant is dosed into the overflow to prevent scale formation.

Tank leaching uses eight atmospheric leach tanks arranged in a cascading configuration for cyanidation, providing a 36-hour residence time. Each tank measures 15 m in diameter and 19.6 m in height, equipped with mechanical agitators and oxygen injection systems via jet spargers to maintain dissolved oxygen at approximately 20 ppm, with a typical range of 10 to 12 ppm. Milk of lime is dosed into Tanks 1 and 2 to maintain pH between 10.5 and 11.0 to prevent hydrogen cyanide gas formation. Sodium cyanide solution is metered into the first three tanks to maintain a free cyanide concentration of approximately 1.5 g/L. Lead nitrate solution is added to enhance leaching efficiency as required.

The counter-current decantation circuit consists of six high-rate thickeners, each 35 m in diameter, with flocculant addition. The leached slurry enters CCD Thickener No. 1 via gravity where it mixes with overflow from the subsequent thickener. Underflow is concentrated to 50% wt solids and pumped to the next stage where it is washed with solution recovered from the following thickener. The wash ratio is typically controlled at 3.0. Final underflow from CCD Thickener No. 6 is pumped to cyanide destruction, while overflow from Thickener No. 1 flows to the PLS clarifier. The PLS clarifier minimizes total suspended solids in the pregnant solution, reducing diatomaceous earth consumption.

The Merrill-Crowe circuit includes four DE-coated clarifier filters, two deaeration towers, and four zinc cementation precipitate filter presses. Pregnant leach solution is stored in a PLS tank measuring 11.5 m diameter by 16.3 m height, providing a one-hour buffer capacity. The target TSS in feed solution is below 100 ppm. Each DE clarifier filter operates in cycles lasting 12 to 47 hours depending on TSS load. Clarified solution contains less than 1 ppm TSS and flows through two deaeration towers operating in parallel under vacuum to reduce dissolved oxygen to below 0.5 ppm. Zinc dust is introduced at the suction of the precipitate filter feed pumps via a water-covered zinc feed cone to prevent oxygen entrainment. Four plate-and-frame precipitate filter presses operate with three in parallel and one on standby. Typical operating cycles range from 3 to 7 days depending on DE precoat quality, zinc dust stoichiometric ratio, PLS grades, and precipitate filterability.

The refinery receives PLS from the ILR circuit directed to a single electrowinning cell equipped with stainless steel mesh cathodes. Gold is electrochemically deposited onto cathode surfaces. Gold-bearing sludge is removed using high-pressure water sprays and dewatered in a plate-and-frame filter press. The filter cake is combined with the Merrill-Crowe precipitate and transferred to the retort circuit. Mercury is removed in a retort furnace under vacuum, achieving approximately 99% mercury recovery. After retorting, material is blended with fluxes and smelted in an induction furnace to produce doré bullion and slag. Off-gases from retorting and smelting are treated in a gas scrubbing system with dust collection.

Cyanide destruction and tailings thickening direct the washed slurry from CCD Thickener No. 6, containing approximately 50% w/w solids, to two agitated cyanide destruction tanks arranged in parallel. These tanks provide a combined retention time of 2 hours. Cyanide destruction uses the SO₂/Oxygen method with sodium metabisulphite, lime, and copper sulphate dosed into the tanks while oxygen is sparged. A 31 m diameter tailings thickener produces an underflow with 55% w/w solids, with overflow routed to the process water tank for reuse.

Raw water for the process plant comes from wells drilled in approved basins, pumped via eight raw water well pumps located approximately 13 km from the mine site. The raw water storage tank stores sufficient water for 24 hours of process plant operation. A reverse osmosis water treatment plant supplies treated water to a tank with 24 hours of storage plus a fire water reserve of 1,760 m³. The process water tank receives overflow from the pre-leach thickener and tailings thickener as well as reclaim water from the TSF. Potable water treatment uses three modular units incorporating filtration, RO, chlorination, and UV disinfection with a 72-hour residence time. Gland seal water uses treated water with a two-hour residence time. Barren solution is recycled back into the process for applications including wash liquor, flocculant dilution, and leach tank dilution.

Power will be supplied to the plant main substation from an onsite power plant within permitted project boundaries. The onsite power plant may be a hybrid facility consisting of diesel generator sets with an n+2 configuration. Electrical power will be distributed at 6.6 kV to all process and ancillary facilities via overground cable trays. Site distribution steps down to 400/230 V to supply motor control centres and low voltage switchgear. In-line samplers will be installed at key stages including post-grinding, leaching circuit tails, and cyanide destruction inlet and outlet. Six wire samplers will monitor pregnant and barren solutions throughout the Merrill-Crowe plant and electrowinning circuit.

Additional Interesting Data and Summary

The SAG mill uses a variable speed drive, which allows operational flexibility in response to ore hardness variations. The grinding circuit includes space for a future pebble crusher circuit, and the final two leach tanks are depicted in a different colour in the process model to denote a future expansion with provisions incorporated into the plant layout. The cyanide destruction tanks can also be operated in a series configuration, which is expected to be required during processing of Oculto ore.

Oxygen generation uses Vacuum Pressure Swing Adsorption technology selected due to the remote location and logistical constraints associated with liquid oxygen transport and storage. The system supplies approximately 1,950 Nm³/h of gaseous oxygen at 92% purity. Raw water has a natural pH of 5.6 and is strongly corrosive because it is undersaturated in calcium carbonate, so a corrosion inhibitor and antifouling agent is recommended based on a study performed by SNF Water Science in 2025.

Onsite reagent storage includes at least one week of quicklime, crushed quicklime, sodium hydroxide, diatomaceous earth, zinc dust, flocculant, SMBS, copper sulphate, lead nitrate, and antiscalant. Sodium cyanide storage accommodates one month of supply. Milk of lime is prepared at 15% solids with approximately one day of retention capacity. Diatomaceous earth precoat slurry density is controlled to 2% solids, while body feed slurry density is 7% solids. Flux composition for smelting includes 30% silica, 40% borax, 10% nitre, and 20% soda ash.

Key Processes

  • Primary jaw crushing with grizzly screening and hydraulic rock breaker
  • Semi-autogenous grinding with variable speed drive and dual-deck vibrating screen
  • Ball mill grinding in closed circuit with hydrocyclone classification at 250% circulating load
  • Gravity concentration using centrifugal concentrators treating 50% of cyclone underflow
  • Intensive cyanidation of gravity concentrate in heated reactor with electrowinning recovery
  • Pre-leach thickening with flocculant addition and antiscalant dosing
  • Atmospheric tank leaching in eight cascading tanks with oxygen sparging
  • Six-stage counter-current decantation washing with flocculant addition
  • Merrill-Crowe zinc cementation with DE clarification, vacuum deaeration, and filter pressing
  • Retorting for mercury removal followed by induction furnace smelting to doré bars
  • Cyanide destruction using the SO₂/Oxygen method with sodium metabisulphite and copper sulphate catalyst
  • Tailings thickening to 55% w/w solids with supernatant water recovery and reuse
  • Reverse osmosis water treatment with treated water distribution for fire suppression and process use
  • Onsite diesel genset power generation with n+2 configuration at 6.6 kV distribution

Source: NI 43-101 Technical Report, Feasibility Study for the Diablillos Ag-Au Project, July 20, 2026. Project website: Diablillos Ag-Au Project

Diablillos Employs Cyanidation, Merrill-Crowe Flowsheet for Silver-Gold Recovery

The Diablillos silver-gold project, located in Argentina and owned by AbraSilver Resource Corp., is a mineral resource development project targeting silver and gold. The project is not yet in operation. Its processing plant is designed with a daily capacity of 9,000 metric tons of material, based on a throughput stipulation by AbraSilver. The plant design assumes 350 operating days per year, for a yearly throughput of 3.15 million metric tons. Construction timing is not stated in the provided source material. The recovery methods described in this article are drawn from a technical report prepared for AbraSilver.

Critical Data

Parameter Value Unit Notes
Daily throughput 9,000 mtpd Design value
Annual throughput 3,150,000 mtpy Based on 350 operating days per year
Average head grade, Au (Oculto) 0.88 ppm Resource model
Average head grade, Ag (Oculto) 74 ppm Resource model
Average head grade, Au (JAC) 0.13 ppm Resource model
Average head grade, Ag (JAC) 202 ppm Resource model
Final grind size 150 micron P80, design specification
Leach retention time 36 hr Design specification
Gold recovery (Oculto) 83.0 % Design value based on laboratory testing
Silver recovery (Oculto) 79.8 % Design value based on laboratory testing
Gold recovery (JAC) 83.8 % Design value based on laboratory testing
Silver recovery (JAC) 84.9 % Design value based on laboratory testing
CCD stages (Oculto) 6 Not applicable Design specification
CCD stages (JAC) 7 Not applicable Design specification
Merrill-Crowe gold recovery 99.5 % Expected recovery from test work
Merrill-Crowe silver recovery 98.5 % Expected recovery from test work
Total power requirement 20 MW Estimated from mine site
Sodium cyanide consumption (Oculto) 0.83 kg/mt Design consumption
Sodium cyanide consumption (JAC) 1.79 kg/mt Design consumption
Lime consumption (Oculto) 0.93 kg/mt Design consumption
Lime consumption (JAC) 2.19 kg/mt Design consumption
Raw water requirement 184 mtph Design value

Overview

The Diablillos deposit contains gold and silver mineralized material that laboratory test work has shown can be economically recovered through cyanidation. The process flowsheet combines centrifugal gravity concentration with the Merrill-Crowe zinc precipitation process. Metallurgical test work was conducted primarily on Oculto material in 2022. JAC material, representing about 15% of the total resource, was tested in 2023 and shows somewhat different metallurgical performance. The process design criteria and flowsheet address both ore types. When JAC material is processed alone, certain circuit adjustments are required, including seven stages of counter current decantation instead of six and larger thickener diameters.

The plant is designed around several unit operations. Crushing uses a primary jaw crusher in open circuit. Grinding is accomplished in a semi-autogenous grinding mill and ball mill circuit with pebble crushing. Gravity concentration treats cyclone underflow, and gravity concentrates undergo intensive cyanidation. Tank leaching follows, with a 36-hour retention time. The leached slurry is washed in a counter current decantation circuit. Pregnant solution reports to the Merrill-Crowe plant for gold and silver recovery by zinc dust precipitation. The precipitate is processed in a foundry to produce doré bullion. Tailings are detoxified using the INCO process before thickening and deposition.

Key Process Stages

The crushing circuit begins with ore trucked from the mine to a run-of-mine stockpile. A front-end loader feeds material to the jaw crusher dump pocket, which has a live capacity of 200 metric tons. A stationary grizzly retains oversize boulders. A hydraulic rock breaker handles material too large for the grizzly. Material is conveyed from the dump pocket by apron feeder to the jaw crusher. The crusher open side setting is 152 mm. Crusher product has an expected P80 around 152 mm and a top size of 254 mm. A belt scale monitors the crushing production rate. Pebble lime is metered onto the stockpile feed conveyor to establish an alkaline environment for grinding. The coarse ore stockpile is enclosed due to high wind velocity at the mine site. Live capacity is 13,000 metric tons. Total stockpile capacity is about 52,000 metric tons. Two variable speed belt feeders, one operating and one standby, reclaim material onto the SAG mill feed conveyor. Dust control uses two wet type dust collector systems.

In the grinding circuit, material from the stockpile goes to the SAG mill. Dilution water maintains slurry density inside the SAG mill at about 75% solids by weight. The SAG mill is 7.92 m in diameter with an effective grinding length of 3.66 m and a 4,500 kW variable speed drive. Ball charge is controlled between 8% and 15% by volume. The SAG mill discharge passes over a vibrating screen with 10 mm aperture. Screen oversize goes to a cone crusher, a HP 100 short head or equivalent, with a close side setting around 9 mm or smaller. Crushed pebbles are recycled to the SAG mill. Pebble recycle rate is typically 15% to 35% of fresh feed. The pebble screen undersize discharges to a pump box that also receives ball mill discharge. The ball mill is 5.49 m in diameter with an effective grinding length of 8.53 m and installed power of 4,500 kW. It operates at 76% of critical speed with a maximum ball charge of 33 volume percent. Dilution water maintains cyclone feed slurry density around 55% solids by weight. Two cyclone feed pumps are installed, one operating and one standby. Cyclone overflow is the final grinding product at about 150 microns. Ball mill circulating load is 250%. An online particle size analyser monitors the grinding circuit product.

The gravity concentration and intensive cyanidation circuit treats a portion of the cyclone underflow. Two Falcon SB5200 gravity concentrators or equivalent are installed. Mass pull is about 190 kg per hour. Each concentrator operates on about a one-hour cycle. Concentrate is flushed to an intensive cyanidation circuit using an SLR6000 unit manufactured by Sepro Mineral Systems or equivalent. Gravity tails report back to the ball mill feed continuously. Laboratory testing indicates that for Oculto material, 10.1% of gold and 7.8% of silver report to the gravity concentrate. For JAC material, those figures are 17.3% for gold and 9.1% for silver. The intensive cyanidation process assumes 99% gold and 97% silver recovery to pregnant solution.

In the cyanide leach circuit, cyclone overflow goes to a 34 m diameter pre-leach thickener. For JAC material only, the pre-leach thickener would be 40 m in diameter with underflow density around 50% solids by weight. The leach retention time is 36 hours. Barren solution dilutes the leach slurry to 45% solids. Milk of lime maintains pH at 10.5. Eight leach tanks, each 15 m diameter and 20 m height, in series, with agitators and air injection. Sodium cyanide solution maintains free cyanide at about 1.5 grams per liter. Laboratory testing indicates about 83% gold recovery and 80% silver recovery for Oculto material. For JAC material, gold recovery is about 84% and silver recovery about 85%.

The counter current decantation circuit uses six stages of high-rate thickeners with flocculant for Oculto material. Wash ratio is 3.0. First CCD thickener diameter is 32 m. The remaining thickeners are 30 m diameter. An additional thickener for clarification, 32 m diameter, minimizes total suspended solids in the pregnant solution. For JAC material alone, seven CCD stages are required. The first CCD thickener would be 40 m diameter, the remaining six would be 38 m diameter. About 99.6% of gold and silver in solution is recovered to pregnant solution for Oculto material, and about 99.8% for JAC material.

The Merrill-Crowe circuit treats the pregnant solution. Maximum solution total suspended solids is recommended below 100 ppm. Four diatomaceous earth coated clarifiers operate, with three running and one on standby. Each clarifier has about a twelve-hour operating cycle. DE precoat thickness is 3 mm. Clarified solution has total suspended solids less than 1 ppm. Two deaeration towers, 3.2 m diameter and 6.3 m height, remove dissolved oxygen to below 0.5 ppm. Four filter presses are included, with three operating and one standby. Zinc dust is added at the filter feed pipe. From test work, 99.5% gold and 98.5% silver recoveries are expected through the Merrill-Crowe process.

In the foundry, a retort unit removes mercury and moisture from the wet precipitate. Mercury is collected in flasks and shipped off site. Dry precipitate is mixed with fluxes and placed in a fuel fired smelting furnace. Slag is crushed and recycled to the grinding mill.

Tailings detoxification uses two cyanide destruction tanks in series with the INCO process. Sodium metabisulfite and copper sulphate are dosed based on WAD cyanide content. Total retention time is one hour. Slurry after detox contains less than 1 ppm WAD cyanide. A tailings thickener, 40 m diameter, achieves at least 60% solids by weight for Oculto material. For JAC material, underflow density is controlled around 55% solids. Thickener overflow is recovered to the process solution tank.

Additional Interesting Data and Summary

Total raw water requirement is 184 mtph. Raw water comes from wells about 13 km away. The freshwater tank is 20 m diameter and 24 m height, holding 24 hours of water with an additional fire water reserve of 1,760 m3. Process air requirements include 3,138 Nm3/h for cyanide leach tanks and 2,713 Nm3/h for cyanide destruction tanks. Total power requirement for the mine site is about 20 MW. Power comes from a hybrid facility with a photovoltaic plant and dual fuel diesel or natural gas gensets. The photovoltaic plant has one 3 MW array with battery storage and one 17 MW array without batteries, with excess energy stored in the 3 MW battery system. Off-site facilities use diesel generators.

The process design criteria are based on either Oculto or JAC feed. Equipment size differences appear mainly in the metal recovery circuit, particularly the Merrill-Crowe plant, CCD, and tailings handling. For a potential ore blend, equipment size changes would be minimal with minimal impact on process capital costs. Process operating costs for the two ore types should be considered in ore blending for cash flow analysis.

The overall process flowsheet is depicted in the technical report, showing the sequence from crushing through grinding, gravity concentration, intensive cyanidation, tank leaching, CCD, Merrill-Crowe precipitation, foundry, and tailings detoxification.

Key Processes

  • Crushing: Primary jaw crusher in open circuit, open side setting of 152 mm, product P80 around 152 mm, enclosed coarse ore stockpile with live capacity of 13,000 metric tons
  • Grinding: SAG mill 7.92 m diameter by 3.66 m effective grinding length, ball mill 5.49 m diameter by 8.53 m effective grinding length, final grind P80 of 150 microns
  • Gravity concentration: Two Falcon SB5200 concentrators treating cyclone underflow, mass pull about 190 kg per hour
  • Intensive cyanidation: SLR6000 unit treating gravity concentrate, 99% gold and 97% silver recovery assumed
  • Tank leaching: Eight tanks in series, 36 hours retention time, 45% solids, pH 10.5
  • Counter current decantation: Six stages for Oculto, seven for JAC material, wash ratio of 3.0
  • Merrill-Crowe: DE coated clarifiers, deaeration towers, zinc dust cementation filter presses, 99.5% gold and 98.5% silver recovery expected
  • Foundry: Retort for mercury removal, flux mixing, smelting to doré bullion, slag crushed and recycled
  • Cyanide destruction: INCO process, sodium metabisulfite and copper sulphate, one hour retention time, less than 1 ppm WAD cyanide in final effluent
  • Tailings handling: 40 m diameter thickener, underflow at least 60% solids for Oculto, 55% for JAC material

Source: NI 43-101 Mineral Resource Estimate Diablillos Silver-Gold Project, 19 June 2026. Project website: Diablillos Silver-Gold Project