Donlin Gold: Advanced Flotation and POX Recovery Methods

Figure 17-1: Donlin Gold Project Process Plant Simplified Flow Diagram

Source: NOVAGOLD RESOURCES INC (2026)
Website: https://novagold.com/donlin-gold/project-overview/

Critical Data

Parameter Value Unit Notes
Throughput 53,500 t/d Average daily throughput based on 93% plant availability
Mill Power Not specified Power data not provided in source section
Target Grind Size 120–150 (primary) / 50 (secondary) µm P80 Primary ball mill product for flotation feed; secondary ball mill product for rougher flotation
Head Grade Not specified Head grade data not included in recovery methods section
Recovery % Not specified % Overall gold recovery not provided; process uses flotation + POX + cyanidation
Processing Capacity 53,500 t/d Same as throughput; plant design capacity
Energy Consumption Not specified kWh/t Energy consumption data not provided
Water Consumption Not specified m³/t Water consumption data not provided; TSF water reclaim used
Operating Hours Not specified hours/day Annual availability of 93% implies continuous operation

Overview

The Donlin Gold Project, operated by NOVAGOLD RESOURCES INC., is one of the largest undeveloped gold deposits in Alaska, USA. This NI 43-101 technical report (effective November 2025) details a conventional, proven recovery method designed for a massive 53,500 t/d throughput facility with 93% plant availability. The process employs gyratory crushing, SAG mill and two-stage ball milling, followed by flotation circuits to recover gold-bearing sulfides. Because the gold is refractory and finely associated with arsenopyrite, the flotation concentrate (7% sulfur) is treated via pressure oxidation (POX) prior to cyanidation. Tailings are impounded in a Tailings Storage Facility (TSF) with water reclaim for reuse. The process design addresses challenges such as organic carbon preg-robbing and ore stockpile degradation, ensuring robust gold recovery. Located in western Alaska near the Kuskokwim River, the project leverages natural gas power and river barge logistics. The recovery methods are critical to achieving the project’s strong economic returns, including an after-tax NPV of $5.1 billion and 10.3% IRR. This comprehensive approach underscores Donlin Gold’s significance as a world-class gold producer with sustainable water and tailings management.

Key Process Stages

  • Stage 1: Primary Crushing – Run-of-mine ore is fed into a gyratory crusher to reduce particle size before grinding. This is the first step in liberating gold from the host rock.
  • Stage 2: Primary Grinding and Flotation Feed – The crushed ore undergoes SAG mill and primary ball milling to achieve a P80 of 120–150 µm. This slurry is fed to the primary rougher flotation section where gold-bearing sulfides are first concentrated.
  • Stage 3: Secondary Grinding and Rougher Flotation – Rougher tails from the primary circuit are directed to a secondary ball milling circuit, grinding to P80 of 50 µm. The finer material then enters secondary rougher flotation to maximize sulfide recovery.
  • Stage 4: Concentrate Treatment – Pressure Oxidation (POX) – The flotation concentrate (7% sulfur) is refractory and treated in an autoclave circuit (POX) to break down the sulfide matrix, liberating gold for subsequent cyanidation. Excess acid from POX is neutralized with flotation tailings and slaked lime.
  • Stage 5: Cyanidation and Tailings Management – The POX product is cyanidated to dissolve gold for recovery. Process tailings are sent to a TSF, where reclaimed water is recycled back to the plant. This closed-loop water system minimizes freshwater demand.

Additional Interesting Data and Summary

The Donlin Gold Project’s recovery methods are underpinned by extensive metallurgical testwork confirming gold is finely associated with arsenopyrite, with minor pyrite and marcasite. Organic carbon (preg-robbing) in sedimentary ores is managed via stockpile blending and ore aging considerations – material stockpiled less than one year shows no flotation recovery loss. The process plant includes acid neutralization using flotation tails and lime, ensuring environmental compliance. Tailings are stored in a TSF located in the Anaconda Creek valley, with seepage collection and water diversion dams. Reclaimed water from the TSF is reused in the process plant, reducing overall water consumption. Economically, the project boasts a total initial capital of $9.23 billion (Q4 2025 pricing) with sustaining capital of $2.33 billion. Life-of-mine operating costs are $48.54 per tonne processed, with processing costs accounting for $15.29/tonne. The after-tax NPV5% is $5.06 billion with an IRR of 10.3% and payback of 6.5 years, based on a $2,100/oz gold price. Environmental permitting has advanced through the NEPA process with a Joint Record of Decision (2018). A trust fund of $7.8 million per year (total $412 million) is planned for closure, plus financial assurance of $322 million. The project engages with Alaska Native Corporations and local communities, emphasizing workforce development and cultural heritage. Key risks include sulfur variability in mill feed and potential stockpile oxidation affecting flotation performance. Recommendations for future feasibility updates include additional metallurgical studies and geotechnical investigations, budgeted at $1.64 million. Overall, Donlin Gold represents a technically robust, large-scale gold recovery operation with strong environmental stewardship and economic viability in a challenging Arctic environment.


Key Processes: Flotation, CIP/CIL, Cyanidation, Gravity Separation, SAG Mill, Ball Mill, Crushing

Target Commodities: Gold, Silver, Copper, Lead, Nickel

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

Donlin Gold Project — 2020 Technical Report (Section 17)

Donlin Gold Project — 2020 Technical Report (Section 17)

Company Donlin Gold Project
Date 2020
Region Alaska, USA
Commodities Gold
Mine Type Open Pit
Throughput 53,500 tpd
Mine Life 27 years
Status Development

Executive Summary

The Donlin Gold Project recovery methods section outlines a comprehensive processing plant design based on conventional technology for large-scale gold operations. The process flow involves sulphide flotation pre-concentration followed by pressure oxidation (POX) and carbon-in-leach (CIL) cyanidation. This configuration is designed to maximize gold recovery from the project’s sulphide mineralization, utilizing autoclave technology to treat the flotation concentrate before leaching. The design criteria remain consistent with the 2011 Technical Report, with cost updates reflecting 2020 power unit rates and reagent pricing.

The plant is designed for a total system throughput of 53,500 tonnes per day with 93% availability. The comminution circuit features a gyratory crusher, SAG mill, and ball mills in a closed circuit with pebble crushing. Flotation utilizes a rougher-cleaner-scavenger circuit with tank-type cells to produce a bulk concentrate. The concentrate is then acidulated and processed through an autoclave circuit to oxidize sulphides, followed by neutralization and CIL recovery. The overall recovery is projected to average approximately 90% over the mine life.

The project is currently in the development phase, with the process design optimized for variable ore hardness and quality. Key operational considerations include effective neutralization of acidic solutions using natural carbonates in flotation tailings, cyanide destruction via SO2/Air, and comprehensive mercury abatement systems across the POX, carbon regeneration, and electrowinning circuits. The final tailings are designed to be non-acid generating, with water recycling capabilities to minimize discharge.

Reports

  • entities/Donlin_Gold_Project

Website: https://novagold.com/

Report Date: 2020

Region: Alaska, USA

Project Status: Development

Commodity: Gold

Throughput: 53,500 tpd

Mine Life: 27 years

Mine Type: Open Pit

Ore type:

Donlin Gold Project — NI 43-101 Technical Report

Donlin Gold Project — NI 43-101 Technical Report

Company: Donlin Gold LLC (Joint Venture: NOVAGOLD Resources Inc. and Barrick Gold Corporation)
Project: Donlin Gold Project
Location: Alaska, USA
Report Date: 22 January 2026
Project No.: 259219

Executive Summary

The Donlin Gold Project is a large-scale gold development project located in Alaska, USA. The process design is based on conventional and proven technology for the concentrator, flotation, POX (Pressure Oxidation), and cyanidation facilities suitable for large, modern gold processing plants. The process plant is designed for an average daily throughput of 53,500 t/d considering a 93% plant availability. This throughput capacity positions Donlin as one of the larger gold projects in North America.

The processing circuit employs a conventional flowsheet starting with primary crushing using a gyratory crusher, followed by SAG milling and two-stage ball milling. The primary ball milling circuit produces a P80 particle size of 120 to 150 µm as feed to the primary rougher flotation section. Rougher tails are then fed to the secondary ball milling circuit, which produces a P80 particle size of 50 µm as feed to the secondary rougher flotation section. Gold-bearing sulfides recovered by flotation generate a concentrate containing 7% sulfur, which is refractory in nature and requires treatment in a POX circuit prior to cyanidation.

Mineralogical studies have shown that gold is not visible and exhibits a high level of association with arsenopyrite. Other sulfides present include pyrite and marcasite with reduced tenors of gold. Organic carbon, a potential preg-robber, is present in the sedimentary ore and at lower levels in intrusive ores (believed to be well-ordered graphite). The project plan includes using stockpiles to manage ore blend from the perspective of gold, sulfur, carbonate, and hardness. Testwork has shown no statistical deviation in flotation recovery for material stockpiled for less than one year.

Processing Details

  • Throughput: 53,500 t/d (design basis)
  • Plant Availability: 93%
  • Crushing: Gyratory crusher (ROM ore)
  • Milling: SAG mill followed by two-stage ball milling
  • Primary Grinding: P80 = 120-150 µm
  • Secondary Grinding: P80 = 50 µm
  • Flotation: Primary and secondary rougher flotation circuits
  • Concentrate: 7% sulfur (refractory)
  • Pressure Oxidation: POX circuit for concentrate treatment
  • Leaching: Cyanidation following POX
  • Tailings Management: TSF with water reclamation for reuse

Website: https://novagold.com/donlin-gold/project-overview/

Report Date: 

Region: 

Project Status:

Commodity: 

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Mineral processing basics

Scroll to Top