Los Ricos South PEA — 2021 Technical Report

This article summarizes the process design and metallurgical testwork reported in the February 22, 2021 preliminary economic assessment for the Los Ricos South project in Jalisco, Mexico, distinguishing planned facilities from historical and laboratory data.

Report context

The February 22, 2021 technical report (effective January 20, 2021) presents a preliminary economic assessment for the Los Ricos South project located in Jalisco, Mexico, at latitude 21° 02’ 45” N and longitude 103° 56’ 08” W. The report was prepared for GoGold Resources Inc. and includes a proposed processing facility, associated infrastructure, and metallurgical testwork programs. This article focuses solely on the processing and recovery methods sections, with no coverage of economic analysis beyond stated report contents.

Processing route

Proposed plant design

The report describes a processing plant designed to treat open pit and underground feed, with the flowsheet presented in section 17.0 of the technical report. The design criteria and plant description are presented as the basis for the preliminary economic assessment, with no claim of construction or operational status.

Primary crushing

Ore is delivered to a primary crushing circuit, where run-of-mine material is reduced to a size suitable for conveying to a crushed feed stockpile. The design specifies a primary crusher followed by a crushed feed stockpile and reclaim system.

Grinding circuit

The grinding circuit comprises a semi-autogenous grinding mill, a ball mill, and associated classification equipment. The design criteria include a target grind size to achieve suitable liberation for downstream leaching, with the circuit configured to process the planned throughput.

Pre-leach thickening and filtration

Following grinding, the slurry reports to a pre-leach thickener and pre-leach filter to adjust pulp density and remove excess water prior to cyanidation. This step is designed to optimize leach performance by controlling cyanide and oxygen concentrations.

Leaching and recovery

The report specifies a carbon-in-leach or Merrill-Crowe recovery process, with the Merrill-Crowe circuit and refinery detailed for gold and silver recovery. A SART (Sulfidization, Acidification, Recycling and Thickening) circuit is included to recover cyanide and base metals, with the report noting the need to manage reactive sulfur and prevent cyanide losses.

Tailings dewatering

Tailings are processed through a dewatering circuit to recover water for recycle to the plant, reducing fresh water demand and minimizing environmental impact.

Ancillary facilities

The plant includes reagent handling and storage, an assay and metallurgical laboratory, water supply, and air supply systems. These are described as supporting infrastructure for continuous plant operation.

Historical processing data

The report references historical metallurgical treatment of Cinco Minas mineralization from 1910–1911, where the deposit was processed using conventional cyanidation and amalgamation methods of that era. No modern performance data is provided from these operations, and the historical records are noted as qualitative context rather than design basis.

Testwork program (2020)

A 2020 testwork program was completed by SGS and reported on November 27, 2020, covering grindability, leaching characteristics, and acid-base accounting. The testwork included:

  • Head assays for multi-element analysis
  • Grindability testing via SPI®, Bond rod mill, Bond ball mill, and Bond abrasion tests
  • Unconfined compressive strength (UCS) tests
  • Acid-base accounting (ABA/NAG) testing

The metallurgical testwork investigated cyanidation behavior and recovery, with results supporting the proposed process flow sheet. The report notes that additional testwork and optimization are recommended for the next phase of project evaluation.

Design vs. actual basis

The processing route is presented as a design basis for the PEA, with no actual operating data from a commercial plant at this project. The 2020 SGS testwork provides laboratory-scale evidence of grindability and leach response, while the historical 1910–1911 data is qualitative and not used for design purposes.

Key reported parameters

Parameter Value Units Basis
Primary crushing Single-stage jaw crusher Proposed design
Crushed feed stockpile Covered, with reclaim Proposed design
Grinding SAG mill + ball mill, closed circuit Proposed design
Target grind size Not stated in extracted text µm Design
Pre-leach thickening High-rate thickener Proposed design
Pre-leach filtration Pressure or vacuum filter Proposed design
Leach Carbon-in-leach or Merrill-Crowe Proposed design
Recovery circuit Merrill-Crowe + refinery Proposed design
SART circuit Included Proposed design
Tailings dewatering Thickening + filtration Proposed design
Grindability – SPI® Reported kWh/t 2020 SGS testwork
Bond rod mill work index Reported kWh/t 2020 SGS testwork
Bond ball mill work index Reported kWh/t 2020 SGS testwork
Bond abrasion index Reported 2020 SGS testwork
UCS Reported MPa 2020 SGS testwork
Head grade (Au, Ag) Reported g/t 2020 SGS testwork
Leach recovery Reported % 2020 SGS testwork
Historical treatment (1910–1911) Cyanidation + amalgamation Historical records

Project website: https://gogoldresources.com/properties/los-ricos/

Technical qualifications

The following limitations apply to the processing and metallurgical sections of the technical report:

  • The process plant design is based on preliminary engineering at a PEA level of confidence; it is not a feasibility study and does not provide a basis for construction.
  • The 2020 SGS testwork was performed on limited samples and may not be fully representative of the deposit’s variability.
  • Grindability and leach test results are laboratory-scale; scale-up to commercial operation requires further testwork and engineering.
  • The historical 1910–1911 metallurgical data is provided for context only and does not constitute a modern process design basis.
  • The SART circuit design is based on conceptual considerations for cyanide management; no pilot-scale data is mentioned in the extracted text.
  • ABA/NAG testing indicates acid-generating potential, but the report notes that additional geochemical testing is needed to confirm long-term water quality implications.
  • The report recommends additional testwork and optimization for the Los Ricos South process, including variability testing, pilot plant runs, and trade-off studies for the SART circuit.

Source: GoGold Resources Inc., *Preliminary Economic Assessment of the Los Ricos South Project, Jalisco, Mexico*, NI 43-101 Technical Report, Report No. 390, effective date January 20, 2021, report date February 22, 2021, Sections 13.0, 17.0.