Tijirit Project — Technical Report (PEA)

Tijirit Project — Technical Report (PEA)

Company [To be identified from report header]
Date 2021
Region Mauritania
Commodities Gold
Status Preliminary Economic Assessment

Executive Summary

This Technical Report presents the Preliminary Economic Assessment (PEA) for the Tijirit Project in Mauritania. The process plant is designed for two distinct production phases. Phase 1 processes 2,976 tonnes per day of run-of-mine (ROM) material from higher-grade deposits in the Eleonore mining zone, with an average feed grade of 3.33 g/t Au. Phase 2, implemented after approximately four years, expands throughput to 4,500 tpd to process lower-grade material from the Lily and Sophie mining zones at 1.07 g/t Au. The process plant utilizes traditional gravity and Carbon-In-Leach (CIL) circuits, with overall gold recovery ranging from 93.6% to 96.0%. Annual gold production varies between 50,000 oz and 123,000 oz depending on plant feed rate and grade.

The flowsheet includes primary jaw crushing, followed by single-stage SAG milling in Phase 1 (converted to SAB circuit in Phase 2), gravity concentration, CIL leaching, elution, intensive leaching of gravity concentrate, electrowinning, and tailings thickening and filtration. Phase 2 introduces a pebble crusher, ball mill, and additional gravity concentrator to achieve the higher throughput and finer grind size (P80 reduced from 105 to 75 microns). The project employs a dried stacked tailings storage approach with vacuum disc filtration.

Key Parameters

Parameter Phase 1 Phase 2
Plant Capacity 2,976 t/d 4,500 t/d
Feed Grade 3.33 g/t Au 1.07 g/t Au
Overall Recovery 96.0% 93.6%
Annual Production 111,661 oz/y 52,888 oz/y
Target Grind Size (P80) 105 microns 75 microns

Processing Overview

  • Crushing: Primary Jaw Crusher (132 kW), open side setting 100mm (Phase 1) / 150mm (Phase 2)
  • Grinding: Single Stage SAG (Phase 1) → SAG/Ball Mill (Phase 2), SAG mill 3,300 kW, Ball mill 3,300 kW
  • Gravity: Gravity concentrator with intensive leach reactor
  • Leaching: Carbon-In-Leach (CIL) – 7 tanks, 48h residence (Phase 1), 30h (Phase 2)
  • Elution: AARL type, 3-tonne columns
  • Electrowinning: Two cells for pregnant solutions
  • Tailings: Thickening (18m high-rate thickener) and vacuum disc filtration

Reports

Website: https://mininghub.com/project-profile?gid=5269

Report Date: 2021

Region: Mauritania

Project Status: Preliminary Economic Assessment

Commodity: Gold

Throughput: 

Mine Life: 

Mine Type: 

Ore type: 

Scroll to Top