Eskay Creek Updated Feasibility Study Floats a Gold Concentrate From a SAG-Ball, Stirred-Mill and 10 µm Regrind Circuit

Skeena Resources' 2023 updated feasibility study for the Eskay Creek project in British Columbia starts at 3.0 Mt a year and expands to 3.5 Mt a year from Year 6, trucking dried concentrate grading above 35 g/t gold.

The Eskay Creek Project, British Columbia, NI 43-101 Technical Report on Updated Feasibility Study, was prepared by Sedgman Canada Limited and others for Skeena Resources Limited and filed in 2023. The process design rests on the testwork in Section 13 of the report. The plant uses crushing, grinding and flotation to liberate and recover gold from run-of-mine ore. The flotation concentrate is thickened, filtered, dried and stockpiled, then loaded into haul trucks.

Critical Data

Parameter Value Unit Notes
Report Updated feasibility study, 2023 Not applicable Sedgman Canada and others for Skeena Resources Limited
Throughput, Years 1 to 5 3.0 Mt/a (8.22 kt/d) Not applicable Not applicable
Throughput, Years 6+ 3.5 Mt/a (9.59 kt/d) Not applicable Not applicable
Crushing Single-stage jaw, 489 t/h nominal Not applicable 70% availability
Primary grind P80 100 µm SAG, pebble crusher (Year ~3) and ball mill
Tertiary grind P80 40 µm High-intensity stirred mill
Regrind P80 10 µm High-intensity stirred mill
Cleaners Two stages Not applicable High-intensity flotation cells
Concentrate grade Above 35 g/t Au Not applicable
Filter cake About 18% moisture, dried to below 9% Not applicable Vertical plate pressure filter, direct heat dryer
Concentrate storage 2,300 t (about 5.5 days) Not applicable Not applicable
Bond ball mill work index (75th percentile) 20.4 kWh/t Range 12.4 to 27.6

Overview

The project is built in two phases. The initial 3.0 Mt a year plant has a single jaw crusher, a coarse ore bin fed by an overland conveyor, a SAG mill with pebble crusher (added around Year 3), a ball mill in closed circuit with cyclones, a stirred-mill tertiary grind, rougher flotation with concentrate regrind, two cleaner stages and cleaner scavenging. The expansion to 3.5 Mt a year from Year 6 adds cyclones and filter plates and upgrades pumps and piping, with a larger tertiary mill motor if further testwork requires it. The jaw crusher, SAG and ball mills, thickener and plant building are all sized from the start for 3.5 Mt a year at the final ore hardness. That removes the need for a secondary crusher later, because the duty shifts to the SAG mill.

Key Process Stages

Crushing. Run-of-mine ore is tipped into a surge bin or stockpiled for loader reclaim. An apron feeder and vibrating grizzly feed a single jaw crusher at 489 t/h nominal. A weighed conveyor fills a coarse ore bin with about eight hours of live capacity, backed by an overflow and emergency stockpile.

Primary grinding. The SAG mill and ball mill have squirrel-cage induction motors sharing one variable speed drive. The drive starts the ball mill, transfers it to direct-on-line, and then controls the SAG mill speed. SAG discharge is screened, oversize goes to the pebble crusher, and cyclones close the ball mill at P80 100 µm. About 15% of the cyclones will be blanked off until the Year 6 expansion.

Tertiary grinding. After a trash screen, cyclone underflow feeds a high-intensity stirred mill that grinds to P80 40 µm ahead of rougher conditioning.

Flotation and regrind. Conventional tank cells serve as roughers, with PAX collector and MIBC frother. Rougher concentrate is reground in a second high-intensity stirred mill to P80 10 µm to free fine gold and raise concentrate grade. The first cleaner, a high-intensity cell, acts as a scalper for fast-floating mineral at final grade. Cleaner 1 and 2 tails go to a conventional cleaner scavenger, whose concentrate is re-cleaned in Cleaner 2.

Concentrate handling. A high-rate thickener brings the concentrate to about 45% solids. A filter feed tank with eight hours of surge feeds a vertical plate pressure filter, which produces cake at about 18% moisture. A direct-heat dryer takes it below 9% for bunker storage and truck loading.

Tailings. Rougher and cleaner scavenger tails, with any excess contact water, are pumped by four pumps in series to the tailings management storage facility (TMSF), because of the pipeline's length and elevation.

Additional Interesting Data and Summary

The ore is hard and variable: Bond ball mill work index ranges from 12.4 to 27.6 kWh/t, with a 75th-percentile design of 20.4 kWh/t, and Axb is 38.6. The plant has a metallurgical laboratory and sampling of flotation feed, tailings and concentrate for quality control and optimization, and PLCs control the process.

In summary, the 2023 Eskay Creek updated feasibility study is a flotation-only gold plant that relies on fine grinding, to 40 µm and then 10 µm for the concentrate, to make a dried concentrate above 35 g/t gold for sale. It is sized to grow from 3.0 to 3.5 Mt a year with few equipment changes.

Key Processes

  • Single-stage jaw crushing and coarse ore bin
  • SAG milling with pebble crushing and ball milling to P80 100 µm
  • High-intensity stirred-mill tertiary grinding to 40 µm
  • Rougher flotation with PAX and MIBC
  • Stirred-mill regrind of concentrate to 10 µm
  • Two-stage high-intensity cleaning and cleaner scavenging
  • Concentrate thickening, pressure filtration and drying
  • Tailings pumping to the TMSF

Source: Eskay Creek Project, British Columbia, NI 43-101 Technical Report on Updated Feasibility Study, prepared for Skeena Resources Limited, 2023.

Earlier report summaries

Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.

Eskay Creek Project — 2022 Technical Report

The Eskay Creek Project is designed as a two-phase gold and silver flotation concentrator, with initial throughput of 3.0 Mt/a expanding to 3.7 Mt/a.

Report context

This technical report presents the recovery methods for the Eskay Creek Project as described in the NI 43-101 Technical Report and Feasibility Study dated September 2022. The report documents the proposed process plant design, including comminution, flotation, concentrate dewatering, and tailings disposal. The project is based on a feasibility-level study, with the processing route selected from testwork analysis and subsequent economic assessment. The process design is presented in two phases: initial operation from years 1 to 5 and expansion from year 6 onward.

Processing route

Overall process design

The project will be constructed in two distinct phases. Initial operation of 3.0 Mt/a for years 1 to 5 includes a single-stage jaw crushing circuit fed from the open pit mine, a coarse ore stockpile with reclaim system, and primary grinding consisting of a semi-autogenous grinding (SAG) mill, pebble crusher (installed for year 4 operations), and ball mill in closed circuit with hydrocyclones. The initial phase also includes rougher flotation with concentrate regrind and two stages of cleaning, rougher tails slimes classification via two stages of hydrocyclones, secondary grinding with ball mill and IsaMill plus scavenger flotation, fines flotation with two stages of cleaning, concentrate thickening, filtration, drying and storage, and concentrate load-out by front-end loader. Final tailings will be pumped to the TMSF.

Expansion to 3.7 Mt/a for the remaining mine life includes the initial equipment with the addition of a secondary cone crushing circuit, a second ball mill and extra cyclones in the primary grinding circuit, and an additional IsaMill in the secondary grinding circuit, all installed for year 6 operation.

Crushing and stockpile

The crushing facility initially consists of a single-stage crushing circuit processing run-of-mine ore at a nominal rate of 489 t/h at 70% availability for years 1 to 5. Following installation of the secondary crusher, nominal processing rate will be 603 t/h at 70% availability for year 6 onward. Major equipment includes a stationary ROM bin grizzly, ROM surge bin, primary crusher apron feeder, vibrating grizzly, primary jaw crusher, and secondary screen and cone crusher installed for the expansion. The coarse ore stockpile is uncovered with reclaim via apron feeders. The overland conveyor from the primary crusher to the coarse ore stockpile has a route length of 725 m with a 150 m lift and is fitted with a weightometer. Live stockpile capacity is approximately 8 hours initially and approximately 6.5 hours after expansion.

Grinding and classification

The primary grinding circuit for years 1 to 3 consists of a SAG mill and ball mill in closed circuit with classifying cyclones. A pebble crusher begins operating at the start of year 4. A second ball mill is installed in a new building starting at the beginning of year 6. The proposed ball mill circulating load is a nominal 250% of new feed. Primary grinding is designed for a product size P80 of 100 µm. The SAG mill is driven by a single wound rotor drive motor with liquid resistance starter and slip energy recovery unit for variable speed operation. Process water is added to the SAG mill to achieve a slurry density of approximately 70% solids by weight. Cyclone overflow reports to a trash screen, with undersize flowing by gravity to rougher flotation.

Flotation and regrinding

The flotation area comprises a primary rougher and cleaner circuit, rougher scavenger circuit, and fines rougher and cleaner circuit. Regrinding of rougher concentrate occurs prior to cleaning. Rougher tailings are classified for slimes separation prior to secondary grinding and scavenger flotation. Conventional tank cells are used in all flotation circuits. Flotation reagents include potassium amyl xanthate (PAX; collector), copper sulphate (promoter), and methyl isobutyl carbinol (MIBC; frother). The regrind mill targets a discharge size P80 of 15 µm. Slimes classification overflow targets P80 of 20 µm, and the secondary regrinding circuit targets a final discharge P80 of 30 µm. Rougher concentrate is pumped through the regrind mill cyclone cluster, with cyclone underflow ground in the regrind mill. Cleaner 2 concentrate gravitates to the concentrate thickener. Rougher flotation tailings are pumped to the slimes classification circuit. Underflow from both classification stages feeds the secondary grinding circuit. For the expansion, extra cyclones are added to the secondary grinding cyclopaks, and a portion of dewatering cyclone underflow is pumped to the new IsaMill in the expansion building.

Concentrate dewatering

Cleaner 2 concentrate combines with fines cleaner 2 concentrate and is pumped to a static trash screen, then to a feed de-aeration tank and high-rate thickener. Flocculant is added to enhance settling. Thickener underflow solids density ranges from 40% to 55% w/w depending on ore feed. The filter feed tank provides 12 hours of surge capacity. Concentrate is filtered in one of two vertical plate pressure filters to produce filter cake at approximately 15% w/w moisture. A Holo-Flite dryer reduces moisture to below 13.5% w/w for transport. Dried concentrate is stored in a normally empty storage area with nominal capacity of 4 days or 2,407 t.

Tailings disposal

Scavenger tailings, cleaner 1 tailings, fines rougher tailings, and fines cleaner 1 tailings combined with excess contact water are pumped to the TMSF. In-line flocculant is added to enhance settling and minimize turbidity.

Reagents and consumables

PAX is supplied in 1,000 kg bulk bags as a dry reagent and mixed to a 15% w/w solution, with consumption of approximately 2,100 t/y. Copper sulphate pentahydrate is supplied in 1,200 kg bulk bags and mixed to 15% w/w, with consumption of approximately 1,800 t/y. MIBC is supplied in 810 kg IBC totes and dosed directly, with consumption of approximately 450 t/y. Flocculant MF336 (or similar) is supplied in 25 kg bags and mixed to 0.25% w/v, with consumption of approximately 10.100 t/y split evenly between concentrate and tailings thickening.

Services

Fresh water is sourced from borehole wells, with consumption of approximately 2,330 m³/d for years 1-5 and 2,820 m³/d for years 6+. The fresh water tank provides 10 hours of capacity. Potable water is treated on site with 44 hours of storage tank live capacity. Process water consists predominantly of mine dewatering, contact water, concentrate thickener overflow, and TMSF reclaim water as required, with 1.2 h of live storage capacity.

Process control strategy

Field instruments provide inputs to programmable logic controllers (PLCs), with each process area controlled by a single PLC. PLCs collect drive and instrument status, provide drive control and process interlocking, and perform PID control for process control loops. Control is performed in two centralized control rooms. HMI operator stations provide graphical representation of process equipment and perform interlocks, level control, alarms, trends, and report generation.

Key reported parameters

Parameter Units Year 1–5 Year 6+
Ore throughput (base case) Mt/y 3.0 3.7
Daily throughput, average kt/d 8.22 10.14
Process plant capacity, nominal @ 92% availability t/h 372 459
Process plant availability % 92 92
Crushing plant availability % 70 70
Filter plant availability % 85 85
Average head grade, Au g/t 2.99 (life of mine) ,
Average head grade, Ag g/t 78.55 (life of mine) ,
Recovery to concentrate, mass % plant feed 5–10 5–10
Concentrate grade, Au g/t 25–50 25–50
Primary grinding product size P80 µm 100 100
Regrind mill discharge P80 µm 15 15
Slimes classification overflow P80 µm 20 20
Secondary grinding discharge P80 µm 30 30
Thickener underflow density % w/w 55 55
Filter cake moisture, nominal % w/w 15 15
Dryer cake moisture % w/w <13.5 <13.5
Ball mill circulating load % new feed 250 250

Project website: https://skeenagoldsilver.com/eskay-creek/

Project website: https://skeenaeskaycreek.com/

Technical qualifications

The report states that testwork was thoroughly analysed with several process route options considered in the initial feasibility study stages. The selected process route was chosen as best suited to the testwork results and subsequent economic analysis. Recoveries and process parameters are presented as design criteria and annual production estimates; they do not represent actual operating data. Annual gold recoveries range from 76% to 87% and silver recoveries from 82% to 90% across the mine life. Comminution parameters, including Bond work indices and A×b values, vary by period, showing changing ore characteristics. Grinding media consumption figures are estimated from power input and industry-standard calculation methods based on expected mill operating conditions and abrasion indices from testwork. The report notes that the process plant design incorporates flexibility for treatment of all ore types. Equipment specifications in the major equipment list include "or equivalent" designations for several items, indicating that final equipment selection may vary.

Source: Eskay Creek Project, NI 43-101 Technical Report and Feasibility Study, September 2022, Section 17 Recovery Methods.

Mineral processing basics

Scroll to Top