Altar Project PEA Technical Report

The Altar Project preliminary economic assessment proposes a 60,000 tpd flotation concentrator to recover copper and gold from a porphyry deposit, based on extensive metallurgical testwork.

Report context

This report is a Preliminary Economic Assessment (PEA) Technical Report for the Altar Project, dated September 2025 and prepared by SRK Consulting (U.S.), Inc. The recovery methods section describes metallurgical testwork results and a proposed processing flowsheet for a copper-gold flotation concentrator.

Processing route

Proposed concentrator flowsheet

The preliminary flotation concentrator flowsheet includes primary crushing followed by grinding in a SAG mill/ball mill grinding circuit, rougher flotation, regrinding of the rougher concentrate and three stages of cleaner flotation. The proposed design capacity is 60,000 tpd, operated on a 365 day/year, 24 hour/day schedule with 92% operating availability.

Crushing (proposed design)

Run of mine (ROM) material will be trucked to the primary gyratory crusher and either direct dumped into the crusher feed bin or dumped on a stockpile. Stockpiled material would be rehandled with a front-end loader. ROM material will be crushed to about -6 inches and conveyed to the crushed stockpile.

Grinding (proposed design)

Material reclaimed from the crushed material stockpile will be fed to a 40 ft x 26 ft EGL SAG mill. The SAG mill discharge will pass across a pebble screen, with oversize conveyed back to the SAG mill feed. The need for a pebble crusher will be assessed during the next phase of study. Screen undersize will be classified in a cyclone cluster. Cyclone underflow feeds a 26 ft diameter x 40.7 ft ball mill operating in closed circuit with cyclones. Cyclone overflow, classified at 80% passing P80 180 µm, advances to copper rougher flotation.

Flotation (proposed design)

Cyclone overflow flows to the rougher flotation conditioner where slurry is conditioned with potassium amyl xanthate (PAX) at pH 10.5 adjusted with lime. Rougher flotation produces a rougher concentrate and a final rougher tailing. Rougher tailing is pumped to the tailing storage facility. Rougher concentrate is reground to about P80 18–20 µm in a stirred media regrind mill (tower mill) in closed circuit with cyclones. The reground rougher concentrate is upgraded in three stages of cleaner flotation to produce a final concentrate.

Rougher flotation retention time is 23 minutes, based on laboratory retention time multiplied by 2.5. Cleaner-1 retention time is 15 minutes, Cleaner-2 is 12.5 minutes, and Cleaner-3 is 10 minutes.

Concentrate thickening and filtration (proposed design)

Final flotation concentrate will be pumped to a thickener and thickened to about 55–60% solids, then filtered in a filter press to about 9% moisture. Filtered concentrate will drop into a covered load-out area for truck transport. Thickener overflow and filtrate will be recycled to the process water tank.

Tailings thickening and TSF (proposed design basis with alternative)

Rougher flotation tailings and cleaner-scavenger flotation tailings will be combined in the tailing thickener and thickened to about 55% solids, then pumped to the tailing storage facility (TSF). Thickener overflow is pumped to the process water tank. Water will also be reclaimed from the TSF. Alternatively, tailings could be disposed in a dry stack TSF, with thickened tailings filtered in a filter press to about 15% moisture. The report notes dry stack disposal would increase capex and opex.

Key reported parameters

Parameter Units Value Basis
Production schedule Design
Operating days per year days 365 Design
Hours per day hours 24 Design
Ore tonnes per day tpd 60,000 Design
Ore tonnes per hour tph 2,717 Design
Operating availability % 92 Design
Ore grade (LOM) Testwork/LOM estimate
Cu % 0.47 Testwork
Au g/t 0.08 Testwork
Estimated average recovery (LOM) Testwork
Cu % 85–87 Testwork
Au % 55 Testwork
Estimated concentrate quality Testwork
Cu % 26–32 Testwork
Au g/t 3–5 Testwork
As % 0.98–1.3 Testwork
Comminution Testwork
SMC, Axb kWh/t 41.5 Testwork
CWi (Porphyry) kWh/t 7.89 Testwork
CWi (Rhyolite) kWh/t 5.86 Testwork
Ai g 0.11 Testwork
BWI (75th percentile) kWh/t 16.6 Testwork
Primary grind size P80 µm 190 Design
Conc regrind size P80 µm 18 Design
Rougher flotation reagents Testwork
Lime g/t 1,000 Testwork
Potassium amyl xanthate g/t 7 Testwork
MIBC g/t 16 Testwork
pH 10.5 Design
Flotation retention time (lab x 2.5) minutes 23 Testwork
Cleaner-1 flotation reagents Testwork
Lime g/t 400 Testwork
Potassium amyl xanthate g/t 7 Testwork
MIBC g/t 8 Testwork
pH 11 Design
Retention time (lab x 2.5) minutes 15 Testwork
Cleaner-2 flotation reagents Testwork
Potassium amyl xanthate g/t 2 Testwork
MIBC g/t as needed Testwork
pH 11 Design
Retention time (lab x 2.5) minutes 12.5 Testwork
Cleaner-3 flotation reagents Testwork
Potassium amyl xanthate g/t 1 Testwork
MIBC g/t as needed Testwork
pH 11 Design
Retention time (lab x 2.5) minutes 10 Testwork
Concentrate thickening & filtration TBD Not yet determined
Tailing thickening & filtration TBD Not yet determined

Project website: https://aldebaranresources.com/projects/altar-copper-gold/overview/

Technical qualifications

The report states that metallurgical testwork demonstrated copper and gold values can be effectively recovered using industry-accepted flotation technologies. Due to expected high arsenic grades in the concentrate, it is likely the copper concentrate will incur penalties and will require blending with low arsenic concentrates prior to smelting.

Concentrate grade will vary depending on whether supergene or hypogene material is being processed. Supergene material contains secondary copper sulphide minerals (chalcocite and covellite) with higher copper content, while hypogene material consists primarily of chalcopyrite with lower copper content. Arsenic in concentrate is expected to range from about 0.5–2.2% As, with the highest levels expected when processing supergene material due to the arsenic-bearing copper mineral enargite (Cu₃AsS₄).

The report notes concentrate thickening and filtration, and tailing thickening and filtration, are designated as TBD (to be determined). Flotation retention times are based on laboratory retention time multiplied by 2.5.

Source: Altar Project PEA Technical Report, September 2025, SRK Consulting (U.S.), Inc., Sections 17 Recovery Methods and 17.1 Process Description.

Mineral processing basics

Scroll to Top