Camino Rojo Gold Recovery via Heap Leach & Merrill-Crowe

Figure 17.1.4: San Agustin Overall Simplified Process Flowsheet

Source: Orla Mining Ltd (2026)
Website: https://orlamining.com/asset/camino-rojo/

Critical Data

Parameter Value Unit Notes
Throughput 19,200 tpd Average nominal crushed ore rate. Temporary ROM campaign at 21,700 tpd from May 11 to August 9, 2025
Mill Power Not specified kW Crushing circuit only; no grinding mill used
Target Grind Size P80 25 mm Two-stage closed crushing circuit achieves this particle size
Head Grade Not specified g/t Head grade not provided in Section 17; see resource/reserve estimates elsewhere
Recovery % Gold 62%, Silver 8.3% % Overall from start-up through Sept 30, 2025 (to doré). Additional 1.6% gold and 0.4% silver in inventory
Processing Capacity 19,200 crushed; 21,700 ROM tpd Crushed ore nominal; ROM ore stacked temporarily in 2025
Energy Consumption Not specified kWh/t No data provided in Section 17
Water Consumption Not specified m³/t No data provided in Section 17
Operating Hours 24 hours/day Continuous operation typical for heap leach; not explicitly stated but inferred

Overview

Orla Mining Ltd. operates the Camino Rojo open pit heap leach gold-silver mine in Zacatecas State, Mexico, which has been in production since late 2021. The processing facility was commissioned in Q4 2021, with the Merrill-Crowe Plant achieving first gold pour on December 13, 2021, and commercial production declared on April 1, 2022. The site employs a two-stage closed-circuit crushing system to reduce ore to a target P80 of 25 mm, followed by conveyor stacking onto leach pads in 10-metre lifts. Lime (CaO) is added at an average rate of 3.6 kg/t for pH control before dilute cyanide solution is applied to dissolve gold and silver. Pregnant solution flows by gravity to a pump box and is then transferred to the Merrill-Crowe Plant, where precious metals are precipitated via zinc cementation, dewatered, retorted to remove mercury, and smelted into doré bars. The operation processes an average of 19,200 tonnes per day of crushed ore, with a temporary campaign of 494,000 tonnes of run-of-mine (ROM) ore placed between May and August 2025 at a nominal rate of 21,700 tpd. Overall gold recovery from start-up through September 30, 2025 is approximately 62% (based on ounces recovered to doré), while silver recovery is 8.3%, with additional metal in solution and precipitate inventories. This efficient heap leach and Merrill-Crowe flowsheet highlights Orla Mining’s commitment to low-cost, scalable gold and silver production in central Mexico.

Key Process Stages

  • Stage 1: Two-Stage Closed-Circuit Crushing – ROM ore from 100-tonne haul trucks is crushed to P80 25 mm using a primary jaw crusher and two secondary cone crushers fed by double-deck vibrating screens. Oversize is handled by a rock breaker, while grizzly undersize bypasses the primary crusher. Product reports to a surge bin before feeding secondary screens and cone crushers in closed circuit.
  • Stage 2: Conveyor Stacking and Lime Addition – Crushed ore is reclaimed from a product stockpile and conveyed via an overland conveyor to the heap stacking system. Pebble lime (CaO) is added on the overland conveyor at an average of 3.6 kg/t (2025 rate) for pH control. Water sprays at all transfer points and a stockpile cover mitigate dust.
  • Stage 3: Heap Leaching – Ore is stacked in 10-metre lifts using a conveyor system comprising index feed, horizontal index, and radial stacker conveyors. A dilute cyanide solution is applied to the heap to dissolve gold and silver. Once a lift is drained, the old lift is cross-ripped before new ore is stacked on top to break compacted or cemented zones.
  • Stage 4: Solution Handling – Pregnant solution flows by gravity to a pump box and is pumped at a nominal rate of 1,000 m³/h (design 1,200 m³/h) to the Merrill-Crowe Plant. Two of three pressure leaf clarification filters (with diatomaceous earth precoat and body feed) remove suspended solids from the pregnant solution.
  • Stage 5: Merrill-Crowe Precipitation and Refinery – Clarified, deaerated pregnant solution is pumped to precipitate filter presses where ultra-fine zinc powder precipitates gold and silver. Lead nitrate is added as needed to improve efficiency. Precipitate is dried in an electric mercury retort, then mixed with fluxes and smelted in a tilting induction furnace. Doré bars are poured, cooled, cleaned, and shipped to a third-party refiner. Slag is re-crushed and re-smelted to recover residual values.

Additional Interesting Data and Summary

Section 17 of the NI 43-101 Technical Report provides detailed operational performance data for the Camino Rojo Project. As of September 30, 2025, the heap leach operation had stacked approximately 494,000 tonnes of run-of-mine (ROM) ore during a temporary campaign (May 11 to August 9, 2025) at an assumed recovery of 50% for gold and 9% for silver, which was implemented to address production shortfalls from higher proportions of Ki and transitional material. The overall gold recovery to doré averaged 62%, while silver recovery was 8.3%, with additional values in Merrill-Crowe precipitate and leach solutions (1.6% gold, 0.4% silver). The booked metals inventory as of the effective date is estimated at approximately 29,800 ounces of gold and 507,000 ounces of silver, including metals in solution, partially leached ore, and unleached areas such as newly stacked ore and side slopes. Gold inventory peaked in June 2023, declined steadily, then increased from September 2024 through September 2025. Silver inventory peaked in April 2024 and has since remained relatively steady. The Qualified Persons (QPs) note that modeled versus actual gold recoveries are in good agreement with reasonable inventory levels, but silver recoveries show a larger variance, possibly due to slower leach kinetics, insufficient free cyanide, or the need for better calibration of silver recovery estimates. The QPs recommend maintaining current silver recovery estimates while closely monitoring monthly composite columns to determine if a write-down of silver inventory is warranted. Environmental controls include water sprays at all crushing transfer points and a cover for the crushed product stockpile to manage dust. Mercury removed during the retort process is classified as hazardous waste and transported off-site for disposal. The Merrill-Crowe plant operates at a nominal pregnant solution flow of 1,000 m³/h (design 1,200 m³/h), with two clarification filters online and one on backwash/clean/precoat cycle. Precipitate filter presses are cycled offline periodically for compressed-air drying and collection. The tilting induction furnace produces doré bars that are stored in a vault pending shipment to a third-party refiner. Future outlook includes ongoing monitoring of silver recovery and heap inventory trends to optimize process efficiency and reconcile model assumptions, particularly for ROM ore. The Camino Rojo operation remains a significant gold and silver producer in the Zacatecas region, leveraging a proven heap leach and Merrill-Crowe flowsheet that delivers robust metallurgical performance with manageable environmental impact.


Key Processes: Heap Leaching, Cyanidation, Gravity Separation, Crushing

Target Commodities: Gold, Silver, Zinc

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

Camino Rojo Project — 2019 Technical Report

Camino Rojo Project — 2019 Technical Report

Company Orla Mining Ltd.
Date 2019-06
Region Zacatecas, Mexico
Commodities Gold, Silver
Mine Type Open Pit
Throughput 18,000 tpd
Mine Life 6.8 years
Status Development

Executive Summary

This NI 43-101 Technical Report presents the Feasibility Study for the Camino Rojo Project, owned by Orla Mining Ltd. The project is located in the Municipality of Mazapil, State of Zacatecas, Mexico. The study confirms the technical and economic viability of an open-pit mine utilizing heap leaching for gold and silver recovery. The project design includes a processing rate of 18,000 tonnes per day with an estimated mine life of approximately 6.8 years.

The ore body consists primarily of oxide and transition material amenable to heap leaching. Processing involves a two-stage closed crushing circuit to a P80 of 28mm, followed by heap leaching with sodium cyanide solution. Gold and silver are recovered from the pregnant leach solution using a Merrill-Crowe zinc cementation plant, followed by smelting to produce doré bars. The project demonstrates strong economics with a pre-tax IRR of 38.6% and an after-tax IRR of 28.7% based on a gold price of US$1,250/oz.

Infrastructure plans include on-site diesel generation initially, transitioning to grid power in Year 2. Water supply is sourced from production wells on the property. The project is currently in the development phase, pending final permitting and construction agreements with adjacent landowners.

Website: https://orlamining.com/asset/camino-rojo/

Report Date: 2019-06

Region: Zacatecas, Mexico

Project Status: Development

Commodity: Gold, Silver

Throughput: 18,000 tpd

Mine Life: 6.8 years

Mine Type: Open Pit

Ore type:

Camino Rojo — 2018 Preliminary Economic Assessment

Camino Rojo — 2018 Preliminary Economic Assessment

Company Not Specified
Date 2018
Commodities Gold, Silver
Mine Type Open Pit
Throughput 18,000 tpd
Mine Life 6.6 years
Status Development

Executive Summary

The Camino Rojo Preliminary Economic Assessment outlines a heap leaching project designed for the recovery of gold and silver from the Camino Rojo mineral resource. The project utilizes standard open pit mining methods to extract material, which is then processed at an average rate of 18,000 tonnes per day. The ore is crushed to a size where 80% passes 38mm using a two-stage closed crushing circuit before being stacked on a leach pad in 10m lifts.

The processing circuit involves adding lime for pH control prior to leaching with a dilute cyanide solution. Pregnant solution flows by gravity to a pond and is subsequently pumped to a Merrill-Crowe plant for metal recovery. Gold and silver are precipitated from the solution via zinc cementation. The resulting precious metal precipitate is dewatered, dried in a mercury retort to remove mercury values, and smelted to produce the final doré product.

The project has an estimated mine life of 6.6 years with an annual processing tonnage of 6.57 million tonnes. Power is provided by line power to all process elements, and an event pond is included to collect contact solution from storm events for return to the process.

Processing Design Criteria

  • Annual Tonnage Processed:: 6,570,000 tonnes
  • Crushing Production Rate:: 18,000 tonnes/day average
  • Crushing Product Size:: 80% -38mm
  • Average Oxide Gold Recovery:: 70%
  • Average Transition-Hi Gold Recovery:: 60%
  • Average Oxide Silver Recovery:: 13%
  • Average Transition-Hi Silver Recovery:: 17%

Website: https://orlamining.com/asset/camino-rojo/

Report Date: 2018

Region: 

Project Status: Development

Commodity: Gold, Silver

Throughput: 18,000 tpd

Mine Life: 6.6 years

Mine Type: Open Pit

Ore type:

Camino Rojo Project: Heap Leach Gold-Silver Processing Circuit

Overview

The Camino Rojo Project features a state-of-the-art heap leach processing facility designed to recover gold and silver from oxide and transition ores. With an annual processing capacity of 6.57 million tonnes (18,000 tpd average), the operation utilizes a two-stage crushing circuit, conveyor stacking system, and Merrill-Crowe recovery plant to produce doré bars.

Key Process Stages

  • Crushing Circuit: Two-stage closed circuit (primary jaw crusher + secondary cone crushers) producing 80% passing 28mm material
  • Conveyor Stacking: Radial stacker system building 10m-high lifts with 80m maximum heap height
  • Leaching: 80-day leach cycle with drip irrigation (switching to sprinklers in Year 5)
  • Solution Management: Pregnant solution collection through perforated PCPE piping system
  • Merrill-Crowe Recovery: Zinc precipitation with clarification filters, deaeration tower, and precipitate presses
  • Refining: Electric mercury retort and induction smelting furnace producing 40kg doré bars

Critical Data

Parameter Value
Throughput 18,000 tpd average
Crushing Availability 75%
NaCN Consumption 0.35 kg/t
Lime Consumption 1.25 kg/t
Overall Gold Recovery 62%
Overall Silver Recovery 20%
Solution Application Rate 10 L/h/m²
Leach Pad Liner System 2mm LLDPE + 300mm compacted clay (1×10⁻⁶ cm/sec)

Process Infrastructure

The crushing circuit features a 1500mm x 2000mm primary jaw crusher and two 500 HP cone crushers operating in closed circuit with double-deck screens. The Merrill-Crowe plant includes 280m² clarification filters, 13m deaeration tower, and 231m² precipitate presses. The refinery utilizes a 113L induction smelting furnace with comprehensive fume treatment system.

Water Management

The facility maintains three solution ponds with total capacity of 410,355m³. The water balance shows average makeup water requirements of 90.6m³/h (25 L/s), with evaporation systems installed by Year 5 to manage pit dewatering inflows.

Mineral processing basics

Scroll to Top