Collahuasi Copper Concentrator: Grinding, Flotation and Expansion

Figure 18-10: Port schematic flow sheet (CDMIC, 2025)

Collahuasi is a high-altitude open-pit copper-molybdenum operation in Chile’s Tarapacá Region. The Ujina concentrator uses primary crushing, three SAG-ball grinding lines, rougher flotation, vertical regrinding and multi-stage cleaning to produce a collective copper-molybdenum concentrate. Molybdenum is separated from the copper concentrate at the Punta Patache port facility. This profile consolidates MillMatters’ duplicate 2025 report summaries and updates the expansion schedule through August 2026.

Owner Anglo American 44%, Glencore 44%, and a Japanese consortium led by Mitsui 12%
Operator Compañía Minera Doña Inés de Collahuasi (CMDIC)
Location Tarapacá Region, northern Chile; mine and concentrator at approximately 4,200–4,800 m elevation
Commodities Copper and molybdenum
Mine type Open pit
Plant route Primary crushing, SAG-ball grinding, rougher flotation, vertical regrinding, cleaner flotation, concentrate thickening and transport to port
Current demonstrated configuration 170,000 t/d design basis; 2025 technical-report data show approximately 168,000 t/d actual feed
Approved debottlenecking stages Approximately 185,000 t/d during 2026 and 210,000 t/d from late 2027, subject to commissioning and current permit context
Profile last reviewed August 30, 2026

Collahuasi processing flowsheet

Collahuasi’s current sulphide concentrator configuration was established by the 2023 expansion from 160,000 to 170,000 t/d. The central change was a fifth ball mill that increased grinding capacity while the overall route remained conventional copper-molybdenum flotation.

1. Primary crushing and coarse-ore storage

Ore from the Rosario pit is reduced in Crusher No. 4, a 60 × 114-inch primary gyratory crusher. Crushed ore is conveyed to the coarse-ore stockpile, which decouples intermittent mine haulage and crushing from the continuously operating grinding plant.

2. Three SAG-ball grinding lines

Grinding lines 1 and 2 each contain a 32 × 13.5 ft SAG mill and one 22 × 36 ft ball mill. Line 3 contains a 40 × 22 ft SAG mill and two 26 × 38 ft ball mills. Pebbles are crushed and recycled, and the ball mills operate in closed circuit with hydrocyclones.

The fifth ball mill installed for the 170,000 t/d upgrade is a 26 × 46.5 ft unit. It receives crushed SAG pebbles and a portion of discharge associated with the other ball-mill circuits, then operates in its own cyclone-classification loop. The technical-report basis cites a primary grind near a P80 of 230 µm.

3. Rougher flotation

Cyclone overflow is conditioned with flotation reagents and distributed among parallel rougher banks using approximately 127 m³ and 180 m³ mechanical cells. Rougher tailings are final concentrator tailings. Additional 300 m³ rougher cells are being introduced in the staged debottlenecking program to maintain recovery as grinding throughput rises.

4. Regrinding and cleaning

Rougher concentrate is classified and reground in a bank of seven 935 kW vertical mills, normally arranged as four duty and three standby units. The fine product passes through first- and second-cleaner stages plus cleaner-scavenger treatment. Column and Jameson cells perform final upgrading; Jameson-cell tailings recycle to the first cleaner, while combined column and Jameson concentrate becomes the final collective copper-molybdenum product.

5. Concentrate thickening and holding

The collective concentrate is thickened in two approximately 40 m diameter thickeners with support from an approximately 43 m clarifier. Thickened concentrate is stored in three approximately 1,000 m³ holding tanks before it enters the pipeline to the coastal port complex.

Principal equipment and reported operating data

Area Equipment or parameter Reported value
Current concentrator 170 kt/d configuration Established by the 2023 expansion; 2025 actual feed approximately 168 kt/d
Primary crushing Crusher No. 4 gyratory 60 × 114 inches
Grinding lines 1 and 2 Two SAG-ball lines Each: 32 × 13.5 ft SAG and 22 × 36 ft ball mill
Grinding line 3 Large SAG with two ball mills 40 × 22 ft SAG and two 26 × 38 ft ball mills
Fifth ball mill Expansion mill 26 × 46.5 ft; installed for the 170 kt/d configuration
Primary grind Nominal cyclone-overflow target P80 approximately 230 µm
Rougher flotation Parallel mechanical-cell banks 127 m³ and 180 m³ cells; staged expansion adds 300 m³ cells
Regrinding Vertical mills Seven × 935 kW; four duty and three standby
Cleaning Mechanical, column and Jameson flotation Two cleaner stages plus cleaner scavenging and final cleaning
Concentrate thickening Thickeners and clarifier Two × approximately 40 m thickeners and one × approximately 43 m clarifier
Concentrate storage Holding tanks Three × approximately 1,000 m³

Equipment values describe the 170 kt/d technical-report configuration. Expansion equipment should not be treated as fully commissioned until the operator confirms operation at the new rate.

Concentrate transport and port processing

Ujina produces a combined copper-molybdenum concentrate rather than two saleable products. After thickening, the slurry is pumped through the concentrate pipeline to Punta Patache. At the port, the concentrate is received and thickened, molybdenum is separated by flotation, and the two products are dewatered for shipment.

The 210 kt/d program includes a new approximately 60 m receiving thickener, a desliming stage, an additional molybdenum-separation flotation circuit sized for about 2,100 t/d of collective concentrate, replacement of molybdenum filtration and drying equipment, and an extension of the No. 2 copper-concentrate storage shed. The technical report notes that parts of the molybdenum expansion still require separate approval and are not all included in the current life-of-mine plan.

Throughput, grade and recovery

Technical-report statistics show why throughput and recovery should be read together. Actual plant feed rose from approximately 54.1 Mt in 2019 to 60.1 Mt in 2024. The 2024 average was about 165,000 t/d. Preliminary 2025 data in the November 2025 report indicate approximately 61.1 Mt, or 168,000 t/d, close to the 170,000 t/d configuration.

Over the same period, the ore blend became more challenging. The reported average copper feed grade fell from 1.19% in 2019 to 1.15% in 2024 and approximately 0.92% in the preliminary 2025 figures. Actual copper recovery was 81.1% in 2024 and approximately 82.8% in the preliminary 2025 data, compared with higher recoveries earlier in the period. Anglo American’s first-quarter 2026 update reported recovery of 71.8% while lower-grade stockpiles were being processed during a mine-phase transition. This is a feed-quality effect as well as a plant-capacity issue.

Expansion from 170 to 210 kt/d

Stage Status at August 30, 2026 Principal scope
170 kt/d Operating reference configuration Fifth ball mill and associated grinding/flotation changes completed in 2023
PG3A to approximately 185 kt/d Approved; commissioning scheduled for Q3 2026, but the new rate is not treated here as demonstrated Refurbished third primary crusher and additional flotation capacity
PG210 to 210 kt/d Approved investment; first production targeted from late 2027 Ore-conveying upgrades, further rougher cells, water and electrical systems, and port debottlenecking
Fourth processing line / larger growth concept Under study and outside the current life-of-mine plan Potential separate processing capacity and mine expansion; subject to studies, permitting and approvals

One former MillMatters page described PG3A as a June 2026 start and the 210 kt/d stage as a 2028 event. Current company sources instead schedule PG3A commissioning during the third quarter of 2026 and expect the 210 kt/d stage to contribute from late 2027. The life-of-mine schedule may model the full 210 kt/d rate in 2028, but that modelling year is not the same as first production.

Desalination and current permit context

The C20+ infrastructure program includes a desalination plant designed to deliver approximately 1,050 L/s and a roughly 194 km pumping system from the coast to the high-altitude mine. Collahuasi reports that about 80% of operational water demand is already supplied through reuse and recirculation, but desalinated water is important to lowering long-term continental-water use and supporting growth.

In May 2026, Chile’s Second Environmental Tribunal set aside the 2021 environmental authorization for review of two aspects concerning a local community and the marine environment. Anglo American said the immediate issue related to desalination infrastructure rather than the whole Collahuasi environmental assessment and did not expect an immediate production impact because alternative water sources were available. Its July 2026 results discussion said the consultation process would need to be reset and that restoring the desalination project remained important for the longer term. Expansion schedules should therefore be read as current company targets subject to this evolving permit process.

Technical-report library and sources

Source period How it is used in this profile
SRK Collahuasi Technical Report, November 2025 170 kt/d flowsheet, equipment, historical operating statistics, PG3A/PG210 scope and larger growth concept
Collahuasi 2024 Sustainability Report Operator’s staged Ujina Growth Project scope and commissioning schedule
Anglo American 2025 full-year results Approved 185 and 210 kt/d investments and expected production timing
Anglo American Q1 and Q2 2026 updates Current feed, recovery, water and operating context
Anglo American May and July 2026 permit updates Current desalination authorization and consultation context

Additional resources and industry links

Mineral processing basics

Scroll to Top