Domeyko Sulfuros — 2026 PEA Technical Report (Recovery Methods)

The PEA evaluates a concentrator processing 35,000 tpd of sulfide ore through SABC-A grinding, seawater flotation, and high-density tailings thickening.

Report context

This technical report for the Domeyko Sulfuros project, dated January 23, 2026, documents the preliminary economic assessment (PEA) prepared by SRK Consulting (Chile) SpA. The Recovery Methods section describes the proposed concentrator plant configuration and process design based on the mine plan, metallurgical testwork, vendor data, industry standards, and benchmarking of similar Chilean operations. The report states that the term "ore" is used solely to describe material scheduled for processing in the conceptual mine plan and does not imply the declaration of Mineral Reserves as defined by NI 43-101.

Processing route

General Process Scenario

The concentrator plant was evaluated in a SAG production line scenario at a 150 µm grind size. For tailings processing, high-density tailings were selected over conventional tailings based on optimizing seawater consumption through reduced make-up and on the technology's sustainability and permitting advantages. Due to water scarcity in the area, untreated seawater was adopted as the primary water supply source, supported by the plant's proximity to the coast, benchmarking of Chilean companies using untreated seawater, and comparative tests between seawater and freshwater indicating no differences in rougher copper and gold recovery.

Crushing

Ore from the mine, with a controlled ROM particle size distribution, is fed to a primary gyratory crusher (42"x55", 450 kW) at 35,000 tpd. The crusher product is smaller than 8 inches, with a P80 of 4 inches. An intermediate stockpile with a live capacity of 35,000 tons for a 24-hour buffer is included. The crushing area utilization is 70%, representing 16.6 hours of runtime. The crusher feed rate is 2,083 tph with a 5" setting; maximum equipment capacity is 3,300 tph.

Grinding

The grinding circuit operates with a SAG mill in series with a single-unit ball mill and a pebble-crushing circuit with recirculation to the SAG mill (SABC-A type circuit). The pebble crusher operates in an open circuit to obtain a product with a P80 of 12 mm. The ball mill operates in a closed circuit with two hydrocyclone banks to obtain a ground product with a P80 of 150 µm. Grinding area utilization is 92%, representing 22.08 hours of runtime.

The SAG circuit was sized using JKSimMet simulation, yielding a 36'x19' SAG mill with 11,500 kW power demand and 12,500 kW motor power, feed rate of 1,585 t/h, energy consumption of 7.25 kWh/t, and pebble production of 21%. The correlation between the Axb parameter (42) and energy consumption, obtained from benchmarking SAG operations, forecasts 7-8 kWh/t for an ore with this Axb value in a standard SABC-A circuit. The Domeyko ore falls on the borderline between hard and medium-hardness ores in terms of Axb value.

The ball mill was sized using Bond's methodology, yielding a 26'x44' ball mill with 13,900 kW power demand and 16,000 kW motor power, feed rate of 1,585 t/h, and energy consumption of 8.77 kWh/t. The hydrocyclone classification system requires two clusters of 10 26" cyclones suitable for fine separation down to 150 µm.

Flotation

The flotation plant comprises rougher, regrinding, cleaner, and scavenger stages. The rougher stage design was based on flotation tests performed on nine representative samples from the resources, using seawater with a particle size between 106 µm and 212 µm. Flotation time for the rougher stage was defined at 30 minutes, based on 15-minute flotation tests and a Plant/Laboratory scaling factor of 2.0. A rougher flotation row comprising six 300 m³ tank cells was selected to achieve 92% copper recovery at this stage.

The cleaner stage design was primarily based on benchmarking data, as testing of this stage is ongoing. Jameson pneumatic cells were selected for their greater efficiency in processing fine particles, with two cleaning stages. The objective of the Jameson cell is to produce a final concentrate with grades exceeding 26.5% Cu from ores with average grades of 0.40% Cu, primarily chalcopyrite, in a seawater environment where lime use as a pyrite depressant is restricted and where some Domeyko ores with higher phyllosilicate content could contaminate concentrates.

The main equipment in this area includes a 2,000 kW Vertimill VTM-3000 for regrinding, Jameson pneumatic cells for primary and secondary cleaning, and 100 m³ scavenger cells. The flotation stage has a 92% utilization rate.

Concentrate Handling

Concentrate from the flotation plant is sent to a preliminary thickener and storage before filtration. Concentrate is filtered to achieve 9% moisture using a Larox horizontal filter press. During this stage, the concentrate is washed with desalinated water to remove residual saltwater containing chlorine and sodium. Main equipment comprises a 10 m-diameter Hi-rate thickener and two 90 m² horizontal pressure Larox filters, suitable for an average production rate of 30 t/h, equivalent to 660 t/d. A reverse osmosis plant provides desalinated water for concentrate washing.

Filtered concentrates are stored in a closed stockpile with a 7-day capacity of 5,000 tons. Using two front-end loaders, concentrate is loaded onto 30-ton trucks for transport to nearby shipping ports.

Tailings Thickening

Tailings from the flotation plant, containing 32% solids, are sent to the tailings storage area located 13 km away via a conveying system with centrifugal pumps. Three high-density tailings thickeners, 45 m in diameter, are located in the storage area to achieve a solids concentration of 65%. High-torque thickeners with diameters less than 45 m process slurries with a yield stress of 100-150 pascals. Thickened tailings are sent to the tailings storage area through a pipeline system with separate spigots and low-energy slurry distribution to facilitate placement in thin layers.

Water Management

Seawater supplied from the coast is stored in a seawater pond. Water recovered from the high-density thickeners is collected in a process water pond in the tailings area, from where it is returned to the plant's process water pond and reinjected into the concentrator's process water loop. This pond also collects filtered water from the concentrate.

Key reported parameters

Parameter Unit Value Basis
Nominal production tpd 35,000 Design
Annual processing capacity ktpy 12,775 Design
Plant utilization % 92.0 Design
Average Cu grade (LOM) % 0.35 Mine plan
Average Au grade (LOM) ppm 0.25 Mine plan
Cu grade first 5 years % 0.40 Mine plan
Au grade first 5 years ppm 0.31 Mine plan
Target grind size P80 µm 150 Design
Cu recovery (overall) % 88.21 Mine plan (LOM)
Au recovery (overall) % 64.61 Mine plan (LOM)
Rougher Cu recovery % 92 Testwork
Cu concentrate grade % 26.5 Design criteria
Concentrate moisture % 9 Design
Tailings solids concentration % 65 Design
Seawater consumption m³/t 0.6 Design
SAG mill dimensions ft 36'x19' Design calculation
SAG mill motor power kW 12,500 Design calculation
SAG mill energy consumption kWh/t 7.25 Design calculation
Ball mill dimensions ft 26'x44' Design calculation
Ball mill motor power kW 16,000 Design calculation
Ball mill energy consumption kWh/t 8.77 Design calculation
Rougher cells Qty x m³ 6 x 300 Design
Regrind mill Type Vertimill VTM-3000 Design
Cleaner cells Type Jameson Design
Total installed power MW 42.9 Design
Total equipment Qty 82 Design

Project website: https://www.scribd.com/document/1000456133/R-05-2898-01-SRK-ABR-20260123-RevD

Technical qualifications

The report includes several specific limitations. The cleaner stage design was primarily based on benchmarking data, as testing of this stage is ongoing. The report states that the selection of reagents needs further study to achieve high recovery in the cleaner stage due to challenges posed by pyrite depression and phyllosilicates in a seawater environment. The impact of seawater on equipment maintenance must also be considered, given corrosion caused by chlorine on metal parts and coatings. The term "ore" is used solely to describe material scheduled for processing in the conceptual mine plan and does not imply the declaration of Mineral Reserves as defined by NI 43-101.

Source: SRK Consulting (Chile) SpA. Technical Report NI 43-101 – PEA Domeyko Sulfuros, Summary Rev. D, January 23, 2026. Relevant sections: 1.14 Recovery Methods and 17 Recovery Methods.

Consolidated report summaries

The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

Seawater Sulfide Flotation for Copper-Gold Recovery at Domeyko

Seawater Sulfide Flotation for Copper-Gold Recovery at Domeyko

Source: Tintina Mines Limited (2026)
Website: https://tintinamines.com/

Critical Data

Parameter Value Unit Notes
Throughput 35,000 tpd Nominal feed to concentrator; design rate with 15% factor is 40,250 tpd
Mill Power 12,500 kW SAG mill motor power; ball mill additional 16,000 kW
Target Grind Size 150 µm P80 for flotation feed
Head Grade 0.35% Cu, 0.25 ppm Au %/ppm Average over LOM; first 5 years 0.40% Cu and 0.31 ppm Au
Recovery % 88.21% Cu, 64.61% Au % Life-of-mine overall recovery from LOM mine plan
Processing Capacity 12,775 ktpy Annual processing capacity at 35,000 tpd and 365 days/yr
Energy Consumption 7.25 (SAG), 8.77 (Ball) kWh/t Grinding circuit specific energy consumption
Water Consumption 0.6 m³/t Seawater make-up per tonne of ore processed
Operating Hours 24 hours/day Crushing at 70% utilization (16.6 hr); grinding/flotation at 92% (22.08 hr)

Overview

Tintina Mines Limited is advancing the Domeyko project in Chile’s Atacama Region, a copper-gold sulfide deposit that will utilize a state-of-the-art concentrator plant with a nominal capacity of 35,000 tpd. The facility, evaluated in a Preliminary Economic Assessment (PEA) by SRK Consulting, adopts seawater as the primary process water due to regional water scarcity and the plant’s proximity to the coast. This innovative approach leverages proven technology already in use at major Chilean operations like Esperanza and Sierra Gorda. The concentrator will process an average head grade of 0.35% Cu and 0.25 g/t Au, with higher grades of 0.40% Cu and 0.31 g/t Au expected during the first five years. The recovery methods center on a sulfide flotation circuit integrated with a SAG mill–ball mill grinding stage (SABC-A configuration), pebble crushing, and a regrind circuit. The plant targets a grind size of 150 µm and achieves overall recoveries of 88.21% for total copper and 64.61% for gold over the life of mine. High-density tailings thickening (65% solids) was selected over conventional disposal to reduce seawater consumption and improve sustainability. The project’s significance lies in its adaptation to arid conditions, use of untreated seawater, and incorporation of Jameson pneumatic cells for cleaner flotation to maintain concentrate grades above 26.5% Cu despite challenging pyrite and phyllosilicate chemistry.

Key Process Stages

  • Stage 1: Primary Crushing – Run-of-mine ore with controlled particle size is fed into a 42”x55” gyratory crusher (450 kW) at 2,083 tph. The crusher product passes at 80% minus 4 inches and is conveyed to a 35,000-ton covered stockpile, providing a 24-hour buffer. The crushing area operates at 70% utilization (16.6 hours/day) and achieves a product P80 of 4 inches for efficient downstream grinding.
  • Stage 2: SAG & Ball Mill Grinding (SABC-A Circuit) – Ore from the stockpile enters a 36 ft x 19 ft SAG mill (12,500 kW) in closed circuit with a pebble crusher and a ball mill (26 ft x 44 ft, 16,000 kW). The SAG mill operates at 7.25 kWh/t, producing a pebble fraction of 21%. The ball mill receives feed with an F80 of 2500–3500 µm and reduces the particle size to a target P80 of 150 µm. Two clusters of 10 hydrocyclones (26”) achieve a circulating load of 300%. Grinding utilization is 92%, equivalent to 22.08 hours per day.
  • Stage 3: Rougher Flotation & Regrinding – Flotation begins with six 300 m³ tank cells in series, providing 30 minutes of residence time (scaled from 15-minute lab tests). The rougher stage recovers 92% of copper from a feed slurry at 32% solids, using seawater. The rougher concentrate (9% mass yield) is reground in a Vertimill VTM-3000 (2,000 kW) to a P80 of 45 µm, with energy consumption of 4.84 kWh/t. Regrinding hydrocyclones classify the slurry before cleaning.
  • Stage 4: Cleaner Flotation with Jameson Cells – The reground product enters two stages of Jameson pneumatic cells (Mod. B6500/24 and B4000/24) for primary and secondary cleaning. These cells are chosen for their efficiency in fine particle processing and ability to handle the high-pyrite, phyllosilicate-bearing ores in a seawater environment. Cleaner copper recovery is 95%, with gold recovery of 90%. The final concentrate grade is targeted at 26.5% Cu. Four 100 m³ scavenger cells (24 min residence time) recover residual values, with recirculation of 25% to the first cleaner.
  • Stage 5: Concentrate Thickening, Filtration & Washing – The final concentrate (30 t/h, 660 t/d) is thickened in a 10 m Hi-rate thickener to 65% solids, then filtered using two Larox horizontal pressure filters (90 m² each). The filter cake is washed with desalinated water from a reverse osmosis plant to remove chlorine and sodium contaminants, achieving 9% moisture. The washed concentrate is stored in a 5,000-ton covered stockpile (7-day capacity) before truck transport to ports.

Additional Interesting Data and Summary

The Domeyko concentrator plant design includes additional technical details critical for project evaluation. The flotation circuit uses a total installed power of 42.9 MW across 82 equipment items. Rougher flotation tests confirmed 92.01% Cu recovery and 72.69% Au recovery at a feed P80 of 150 µm using seawater. The regrind circuit (Vertimill VTM-3000) reduces concentrate to 45 µm to liberate fine sulfides. Jameson cells in the cleaner stage are essential for producing a final concentrate grade of 26.5% Cu from lower-quality chalcopyrite ores, particularly in the presence of pyrite and phyllosilicates where lime depression is limited. Tailings are thickened to 65% solids using three high-torque thickeners (45 m diameter, torque 14 MN-m) located at the storage site 13 km away, with an elevation gain of 275 m. The tailings storage facility (Sector 4) has a capacity of 310 Mt. Water management employs a seawater pond (24-hour capacity) and multiple recovery ponds (45,000 m³ each) to recycle process and drainage water. Concentrate handling uses two Larox horizontal filters (90 m²) to achieve 9% moisture with desalinated water washing. The project’s economic impact is underpinned by annual copper production of 39.1 kt and gold production of 67 koz, based on the PEA mine plan. Sustainability initiatives include high-density tailings to minimize water loss and energy consumption, and the use of untreated seawater reduces freshwater demand in an arid region. Reagent consumption is optimized for seawater chemistry, including 20 g/t main collector (256 t/yr), 100 g/t lime (1,280 t/yr), and 20 g/t corrosion inhibitor (256 t/yr). Total grinding media consumption is 60 g/t (768 t/yr for SAG and ball mills). The plant layout covers 7 hectares northeast of the mine, integrating all major unit operations. Future studies will focus on optimizing reagent selection for cleaner flotation and confirming equipment sizing through pilot testing. The Domeyko project represents a significant advancement in seawater sulfide flotation technology, offering a blueprint for sustainable copper-gold processing in water-constrained regions.


Key Processes: Flotation, Gravity Separation, SAG Mill, Ball Mill, Crushing

Target Commodities: Gold, Copper

Mineral processing basics

Scroll to Top