Empire State Mines — 2025 Technical Report

Company Titan Mining Corporation
Date December 2025
Commodities Zinc, Lead
Mine Type Underground
Throughput 5,000 tpd (Design)
Status Operating

Executive Summary

The Empire State Mines (ESM) concentrator, originally commissioned in 1970 and last shut down in 2008, was refurbished in late 2017 and resumed processing mineralization in 2018. The facility is designed to handle 5,000 short tons per day, though current operations run on a reduced schedule of one shift per day, four days per week, processing between 10,124 and 11,375 tons per week. The mine operates underground, with mining production typically not exceeding 2,275 tons per day, projected to peak at 2,800 tons per day in 2028.

The processing flowsheet includes crushing, grinding, sequential lead and zinc flotation circuits, concentrate dewatering circuits, and loadout facilities. Primary crushing is performed underground using a 36 in x 48 in jaw crusher or on surface using a 30 in x 42 in jaw crusher. Secondary crushing utilizes an Allis Chalmers Hydrocone crusher. The concentrator is operated intermittently, typically for 10 to 14 hours per day, without notable metallurgical losses from start-up and shutdown cycles.

Reports

  • entities/Empire_State_Mines

Website: https://www.titanminingcorp.com/

Report Date: December 2025

Region: New York

Project Status: Operating

Commodity: Zinc, Lead

Throughput: 5,000 tpd (Design)

Mine Type: Underground

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

Empire State Mines 2025 NI 43–101 Technical Report

Empire State Mines 2025 NI 43–101 Technical Report

Company Titan Mining Corporation
Mine Empire State Mines
Date 2025
Commodities Zinc, Lead
Status Operating

Executive Summary

This technical report details the recovery methods and processing infrastructure for the Empire State Mines (ESM) project, operated by Titan Mining Corporation. The report focuses on the existing ESM concentrator, originally commissioned in 1970 and refurbished in late 2017 to resume processing mineralization in 2018. The facility is designed to handle 5,000 short tons per day, though current operations run on a reduced schedule of one shift per day, four days per week.

The processing flowsheet includes crushing, grinding, sequential lead and zinc flotation circuits, concentrate dewatering, and loadout facilities. Primary crushing occurs underground via a 36 in x 48 in jaw crusher or on surface via a 30 in x 42 in jaw crusher. Secondary crushing utilizes an Allis Chalmers Hydrocone crusher. The concentrator operates intermittently without notable metallurgical losses, with plans to increase throughput to peak LOM production levels of 14,000 tons per week by 2028.

Processing Profile

Website: https://www.titanminingcorp.com/

Report Date: 2025

Region: 

Project Status: Operating

Commodity: Zinc, Lead

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Empire State Mines 2021 NI 43-101 Technical Report

Standfirst The Empire State Mines concentrator, commissioned in 1970 and refurbished in late 2017, currently operates intermittently at 200 t/h to 220 t/h, processing 6,500 to 7,000 tons per week on a one-shift, four-day schedule.

The Empire State Mines (ESM) concentrator, located in the Balmat mining district, processes mineralized material mined from the ESM deposits. Originally commissioned in 1970 and last shut down in 2008, the concentrator was refurbished in late 2017 and began processing mineralization in 2018. The flowsheet for the current operation includes crushing, grinding, sequential lead and zinc flotation circuits, concentrate dewatering circuits, and loadout facilities. The operating philosophy, as documented in the 2021 technical report, is fundamentally different from traditional continuous processing; the facility is designed to operate at its rated throughput but only for as many hours as necessary to match mine production.

Critical Data

Parameter Value Unit Notes
Design capacity 5,000 t/d Concentrator nameplate capacity
Rated hourly throughput 200 – 220 t/h Operating strategy per design
Weekly throughput 6,500 – 7,000 tons Current operating schedule
Operating schedule 1 shift/day Four days per week
Fine ore bin capacity 2,000 t Each of two bins
Screen deck opening 1.5 in Secondary crusher screen
Final grind size 80 – 85 % passing 65 mesh Typical mill feed rates
Underground mine production 1,400 t/d Not stated

Overview

From a metallurgical perspective, the optimal way to operate a concentrator is on a continuous basis to minimize the usual occurrences of sub-standard metallurgy on start-up and product losses on shutdown. However, in practice, the ESM concentrator operates intermittently, which from a metallurgical standpoint introduces some amount of instability during start-up and shutdown. The facility processes material from both underground and open pit sources, with the underground mine plan indicating mill feed with lead values in the order of 0.02%. At this low level, it is not necessary or economic to run the lead circuit, and the current operation uses the lead flotation circuit to pre-float talc and magnesium, as excessive talc in final concentrates results in high magnesium content and incurs penalties.

Key Process Stages

The crushing circuit receives coarse material from either the surface crusher or the shaft hoist via a 36-inch conveyor equipped with an electromagnet for tramp removal. The material discharges into the feed chute of a 6-foot by 14-foot Tyler Tyrock Screen, Model F-900, with a 1.5-inch deck opening. Oversize material reports to a secondary crusher, an Allis Chalmers Hydrocone, Model 1084 EHD (84-inch diameter, extra heavy duty) equipped with a 300 hp motor. The crushing circuit design criteria are documented in Table 17.1 of the technical report, with the actual crusher throughput capacity higher than indicated by production records, which show the hoisting rate rather than crusher capacity.

Fine crushed mill feed is conveyed to the grinding circuit via a 36-inch conveyor equipped with a four-idler Merrick weightometer, which discharges to the rod mill. The rod mill is an 11.5-foot by 16-foot Allis Chalmers mill with a 1,000 hp Allis Chalmers synchronous motor. The ball mill is a 12.5-foot by 14-foot Allis Chalmers mill with a 1,000 hp motor, charged with 2-inch diameter balls and operated in closed circuit with two Warman 26-inch cyclones. The final grind size was normally 80% to 85% passing 65 mesh at typical mill feed rates of 200 t/h to 220 t/h. Media charges were left in the mills on shutdown, and minimal difficulties were found during mill start-up. The rod mill was relined in January 2018 by Metso in advance of recommissioning.

Cyclone overflow reports by gravity to the head end of the lead flotation circuit. The lead rougher circuit consists of a single bank of seven Wemco 300 ft³ cells, with all air inlet ports wide open as slide gates are not in use. The current lead flotation cleaning circuit is single-pass, 1st stage cleaning only, with no additional cleaning stages. In its current state, the lead circuit functions as a talc pre-float, removing excessive talc from the feed.

The zinc rougher circuit consists of two parallel banks of Wemco 300 ft³ cells. The grinding circuit design criteria are documented in Table 17.2, with the existing circuit deemed adequate for future requirements.

Additional Interesting Data and Summary

Laboratory test work on the proposed mill feed indicates that there is no benefit in grinding any finer than was done in the past. If future plant test work demonstrates that finer grinding improves metallurgical performance, this could be accomplished simply by reducing throughputs and increasing operating time. While the mill has a design capacity of 5,000 t/d, underground mine production is typically no more than 1,400 t/d.

The open pit mine plan indicates that mill feed from open pit sources will have lead and silver grades high enough to produce a saleable lead/silver concentrate. Various options for utilizing the existing lead circuit are put forward for consideration, including maintaining the circuit in serviceable condition for short-term lead spikes, bringing the lead circuit back to its original design by adding 2nd and 3rd stage cleaners, or installing a single vertical cell as final cleaning stage. The second and third options are intended to produce a marketable lead concentrate, which may require handling higher-grade mineralization from open pit sources separately to avoid diluting lead values. At the low lead feed grade of approximately 0.02%, it will not be necessary or economic to run the lead circuit, and the concentrate could simply be pumped to the final tails pumpbox.

Key Processes

  • Crushing circuit with primary jaw crushers and secondary cone crusher (Allis Chalmers Hydrocone, Model 1084 EHD, 84-inch diameter, 300 hp motor)
  • Grinding circuit with rod mill (11.5 ft × 16 ft Allis Chalmers, 1,000 hp) and ball mill (12.5 ft × 14 ft Allis Chalmers, 1,000 hp) in closed circuit with two Warman 26-inch cyclones
  • Sequential lead and zinc flotation circuits, with lead rougher consisting of seven Wemco 300 ft³ cells
  • Concentrate dewatering circuits and loadout facilities
  • Talc pre-float function using lead rougher and 1st stage cleaner

Source: Empire State Mines 2021 NI 43-101 Technical Report, 2021.

Project website: Empire State Mines 2021 NI 43-101 Technical Report

Empire State Mines 2024 NI 43-101 Technical Report Update

Empire State Mines 2024 NI 43-101 Technical Report Update

Company Titan Mining Corporation
Date 2024
Region New York, USA
Commodities Zinc, Lead

Executive Summary

The Empire State Mines 2024 NI 43-101 Technical Report Update by Titan Mining Corporation details the operational status and metallurgical processing capabilities of the Empire State Mines (ESM) zinc operations located in the Balmat region. The concentrator, originally commissioned in 1970 and shut down in 2008, was refurbished in late 2017 and resumed processing mineralization in 2018. The facility is designed for a capacity of 5,000 tonnes per day, though current operations run intermittently to match underground mine production, typically processing between 8,500 and 8,750 tonnes per week.

The flowsheet encompasses crushing, grinding, and sequential lead and zinc flotation circuits. Primary crushing occurs underground via a 36” x 48” jaw crusher or on surface with a 30” x 42” unit, followed by secondary crushing using an Allis Chalmers Hydrocone. The current operation utilizes a single shift per day, four days per week, to optimize throughput while managing the intermittent nature of the underground mine supply. While an economic analysis for graphite mineralization has not been completed, the focus remains on zinc and lead recovery through the existing concentrator infrastructure.

Processing Profile

  • Crushing: Primary Jaw Crusher (36”x48” underground, 30”x42” surface), Secondary Allis Chalmers Hydrocone (84”)
  • Milling: Grinding Circuit (Specific mill sizes not detailed in this section)
  • Flotation: Sequential Lead and Zinc Flotation
  • Leaching: N/A

Reports

  • reports/2024_TitanMining_EmpireStateMines

Website: https://www.titanminingcorp.com/news/news-releases/titan-mining-commences-graphite-processing-at-empire-state-mines-in-new-york

Report Date: 2024

Region: New York, USA

Project Status:

Commodity: Zinc, Lead

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Mineral processing basics

Scroll to Top