Gold Recovery Methods at Serabi’s Palito Complex Plant

Figure 17-1: Serabi Process Plant Flowsheet

Source: Serabi Gold plc (2026)
Website: https://www.serabigold.com/operations/palito-complex/

Critical Data

Parameter Value Unit Notes
Throughput 500 tpd Plant design capacity
Mill Power (Ball Mill 01) 253.6 kW Humboldt Wedag 2.3m x 3.2m; Palito circuit
Target Grind Size 120 µm P80 for all grinding circuits
Head Grade 6.80 g/t 2025 milled ore feed grade
Recovery % 96.7 % 2025 overall gold recovery for milled ore
Processing Capacity 500 tpd Consistent with plant throughput
Energy Consumption N/A kWh/t Not specified in source document
Water Consumption N/A m³/t Not specified in source document
Operating Hours 24 hours/day Continuous operation inferred from process description

Overview

Serabi Gold plc operates a 500 tonnes-per-day (t/d) gold processing facility at the Palito Complex, located in Pará State, Brazil. The plant processes ore from both the Palito and São Chico mines using an integrated flowsheet that combines crushing, grinding, ore sorting, copper flotation, carbon-in-pulp (CIP) cyanidation, intensive leaching, elution, electrowinning, and smelting to produce doré bars. Established well before the effective date of the 2026 NI 43-101 Technical Report, the plant has been operating continuously with consistent performance. Its significance lies in the ability to treat two different ore types efficiently: Palito ore undergoes copper flotation to recover a high-grade copper concentrate carrying 50–70% of the gold, while the flotation tailings report to CIP cyanidation for residual gold and silver recovery. São Chico ore feeds a separate grinding circuit with gravity concentration and intensive cyanide leaching of the concentrate. The combination of ore sorting for low-grade material, selective flotation, and cyanidation ensures a high overall gold recovery, which reached 96.7% in 2025. The facility also processes historical flotation tailings, achieving an average recovery of 77.0% from those stockpiles. The entire process is designed to maximize gold extraction while producing a marketable copper concentrate and a final doré product shipped offsite for refining.

Key Process Stages

  • Stage 1: Crushing – ROM ore is crushed to minus 15 mm using a primary jaw crusher (Metso 6240E, 56 kW), secondary (Faço 60S) and tertiary cone crushers (Faço 60TF and Sandvik H2800) in closed circuit with a double-deck vibrating screen (Simplex SXP 4015/2D). Oversize (+38 mm) returns to secondary crushing; intermediate fraction (-38+15 mm) low-grade material is diverted to the ore sorter. Final product P80 is 12–15 mm at an average feed rate of 35 t/h.
  • Stage 2: Ore Sorting – Low-grade Palito ore (-38+15 mm) is upgraded using a Comex CXR-1000 X-ray/optical sorter. Material is washed over an 8 mm screen before being presented as a single layer on a high-speed conveyor. Each particle is scanned by photometric color and XRT sensors; a computer algorithm classifies particles and directs air jets to separate product from waste. The sorted product (9.79 g/t average grade) is returned to the crushing circuit, while waste (0.64 g/t) is stockpiled. Commissioned in 2020, the sorter has processed 163,207 tonnes of feed through 2025.
  • Stage 3: Grinding and Gravity Concentration – Three parallel ball mill circuits grind ore to 80% passing 120 µm. Circuit 1 (Humboldt Wedag 2.3×3.2 m, 253.6 kW) processes Palito ore for flotation. Circuit 2 (Zanini 2.2×3.5 m, 205.2 kW) grinds São Chico ore and includes a Falcon SB-750B centrifugal concentrator (7.5 kW) to recover free gold. Circuit 3 (Zanini 2.2×3.5 m, 205.2 kW) can treat either ore type. Cyclone overflow from Palito circuits reports to flotation; São Chico overflow combines with flotation tailings for CIP.
  • Stage 4: Intensive Leaching & Copper Flotation – São Chico gravity concentrate is leached in a Gekko In-line Leach Reactor (ILR150) in 800 kg batches using 1.5% NaCN and hydrogen peroxide for 24 hours. The leach solution is circulated through an electrowinning cell (600×600 mm, 25.4 kW) in the gold room. Palito ore undergoes flotation in a conditioning tank followed by rougher, scavenger, and cleaner cells (Emprotec dual cells, 22.8–22.4 kW each). Collector A3894 and lime (pH 10–11) are used. Rougher concentrate ( >20% Cu) is filtered via an Andritz filter press; scavenger tails go to CIP. Flotation recovery captures 50–70% of the gold in Palito ore into a copper concentrate shipped offsite.
  • Stage 5: CIP Cyanidation, Elution & Gold Refining – Flotation tailings and São Chico gravity tails are combined in two leach tanks (185 m³ each) and six adsorption tanks (74 m³ each) providing ~18 hours retention at 35% solids. Cyanide is maintained at 250 ppm NaCN in leach, attenuating to ~100 ppm. Carbon concentration is 20 g/L (40 g/L in first tank). Loaded carbon is acid washed with 2% HCl, then eluted at 130°C using the Zadra process (1.5 t capacity column). Pregnant solution passes through electrowinning cells (Como Eng, 25.4 kW each). Gold/silver sludge is dried, fluxed, and smelted in a Grion 11 L furnace at 1,200°C to produce doré bars. Each elution cycle averages 15 hours. Barren carbon is regenerated at 750°C in a Kemix kiln (75 kg/h) before returning to the circuit.

Additional Interesting Data and Summary

The Palito processing plant demonstrated robust operating performance from 2014 to 2025, processing over 2 million tonnes of milled ore with an average head grade of 6.80 g/t and a consistent gold recovery of 92.0% for milled ore. In 2025 alone, 208,999 tonnes of ore at 6.80 g/t yielded 44,169 ounces of gold at a record recovery of 96.7%. The plant also processed 139,411 tonnes of historical flotation tailings between 2015 and 2023, achieving an average recovery of 75.8% and contributing 11,361 ounces of gold. Key consumables include sodium cyanide (1.10 kg/t in 2025, representing ~50% of consumable cost), steel balls (1.28 kg/t, ~25% of cost), lime (1.95 kg/t), and sodium metabisulfite for cyanide detoxification (0.65 kg/t). The ore sorter, commissioned in 2020, processed 163,207 tonnes of low-grade Palito ore through 2025, upgrading feed at 1.73 g/t to a product averaging 9.79 g/t while rejecting 88% of the mass at 0.64 g/t, thereby reducing mill feed costs and waste volumes. Environmental management includes cyanide detoxification using the INCO air/SO2 process in a dedicated tank (93 m³, 1.5 hours residence) to reduce CNWAD to <5 ppm before tailings disposal. The plant’s continuous improvement is evidenced by the installation of new 185 m³ leach tanks in 2022–2023, boosting CIP retention time. Production peaked in 2025 at 44,169 ounces of gold, and the operation remains a cornerstone of Serabi’s Brazilian gold production. The integration of gravity concentration, flotation, and cyanidation allows flexible processing of variable ore types, maximizing overall gold and copper value recovery. Forward-looking, the plant’s proven performance and established infrastructure support sustained production from the Palito and São Chico deposits, with potential for additional throughput from ore sorting upgrades and further tailings retreatment campaigns.


Key Processes: Flotation, CIP/CIL, Cyanidation, Gravity Separation, Ball Mill, Crushing

Target Commodities: Gold, Silver, Copper

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

Palito Mining Complex — 2025 Technical Report

Palito Mining Complex — 2025 Technical Report

Company Serabi
Date 2025
Region Pará State, Brazil
Commodities Gold, Silver, Copper
Throughput 500 t/d
Status Operating

Executive Summary

This technical report details the processing methods and operational performance of the Palito Mining Complex in Pará State, Brazil, operated by Serabi. The facility processes ore from both the Palito and São Chico mines with a plant capacity of 500 tonnes per day. The flowsheet is designed to handle complex ore types, utilizing a combination of crushing, grinding, copper flotation, and carbon-in-pulp (CIP) cyanidation to recover gold and silver values.

Key operational highlights include the integration of an ore sorting circuit to upgrade low-grade Palito ore prior to grinding, enhancing overall recovery efficiency. The São Chico ore is processed through a separate grinding circuit featuring gravity concentration and intensive cyanide leaching. The combined tailings from these circuits undergo CIP cyanidation, with gold and silver adsorbed onto activated carbon before elution and electrowinning to produce a final doré product.

The report provides comprehensive data on equipment specifications, consumable requirements, and operating performance from 2017 to 2022. Gold recovery rates have remained consistent, averaging around 92% for milled ore, with the ore sorter demonstrating significant value in upgrading low-grade material. The facility employs robust cyanide detoxification processes to ensure environmental compliance before tailings disposal.

Processing Overview

  • Crushing: Jaw Crusher (Metso 6240E), Cone Crushers (Faço, Sandvik)
  • Ore Sorting: XRT/Optical (Comex CXR-1000)
  • Grinding: Ball Mills (Humboldt Wedag, Zanini), Hydrocyclones (Weir Cavex)
  • Flotation: Emprotec Dual Cells (Rougher, Scavenger, Cleaner)
  • Leaching: CIP (Carbon-in-Pulp), Intensive Leach (Gekko ILR150)
  • Elution: Zadra Process
  • Detoxification: INCO Air/SO2 Process

Reports

Website: https://www.serabigold.com/operations/palito-complex/

Report Date: 2025

Region: Pará State, Brazil

Project Status: Operating

Commodity: Gold, Silver, Copper

Throughput: 500 t/d

Mine Life: 

Mine Type: 

Ore type:

Palito Mining Complex — 2023 Technical Report

Palito Mining Complex — 2023 Technical Report

Company Serabi
Mine Palito Mining Complex
Date 2023-11-20
Region Pará State, Brazil
Commodities Gold, Silver, Copper

Executive Summary

This technical report details the recovery methods and processing operations for the Palito Mining Complex in Pará State, Brazil, operated by Serabi. The facility processes ore from both the Palito and São Chico mines with a plant capacity of 500 tonnes per day. The processing flowsheet is designed to handle complex ore types, utilizing a combination of crushing, grinding, ore sorting, copper flotation, and cyanidation circuits to recover gold, silver, and copper values.

The Palito ore undergoes a primary crushing circuit followed by grinding and copper flotation. Gold and silver values from the flotation tailings are recovered via Carbon-in-Pulp (CIP) cyanidation. Low-grade development ore is upgraded using an XRT/optical ore sorter prior to grinding. The São Chico ore is processed through a separate grinding circuit that includes gravity concentration and intensive cyanide leaching of the gravity concentrate, with the tailings combined with the Palito flotation tailings for CIP processing.

The report outlines the equipment used throughout the process, including jaw and cone crushers, ball mills, hydrocyclones, flotation cells, and CIP tanks. Operating performance data from 2017 to 2022 indicates consistent milled ore tons and recovery rates, with total gold production reaching 31,819 ounces in 2022. The plant also includes a cyanide detoxification circuit using the INCO air/SO2 process to ensure environmental compliance before tailings disposal.

Website: https://www.serabigold.com/operations/palito-complex/

Report Date: 2023-11-20

Region: Pará State, Brazil

Project Status:

Commodity: Gold, Silver, Copper

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Palito Mining Complex — 2018 Technical Report

Palito Mining Complex — 2018 Technical Report

Company Serabi Gold
Date 2018
Region Brazil
Commodities Gold, Silver, Copper

Executive Summary

Serabi Gold operates a 500 t/d processing plant serving the Palito and São Chico mines within the Palito Mining Complex. The facility processes ore from two distinct sources with different metallurgical characteristics. Palito ore is treated through a circuit involving crushing, grinding, copper flotation, and Carbon-in-Pulp (CIP) cyanidation to recover gold and silver from the flotation tailings. São Chico ore follows a separate grinding circuit featuring gravity concentration and intensive cyanide leaching of the gravity concentrate, with the tailings combined into the main CIP circuit.

Production data from 2015 to 2017 indicates consistent operation with improving recovery rates. Palito ore gold recovery averaged approximately 91%, while São Chico ore recovery increased from 87.1% in 2015 to 95.8% in 2017 Q1. The plant also processes old flotation tailing stockpiles directly into the CIP circuit. Major equipment includes Metso jaw crushers, Faco cone crushers, Humboldt Wedag and Zanini ball mills, and Gekko Intensive Leach Reactors for gravity concentrates.

Processing Overview

  • Crushing: Primary Jaw Crusher (Metso 6240E), Secondary and Tertiary Cone Crushers (Faco 60S/TS/TF).
  • Milling: Ball Mills (Humboldt Wedag 2.3m, Zanini 2.1m) in closed circuit with cyclones.
  • Flotation: Copper flotation using Emprotec Dual Cells with thionocarbamate collector.
  • Leaching: Carbon-in-Pulp (CIP) for tailings, Intensive Leach Reactor (ILR) for gravity concentrate.
  • Refining: Electrowinning and smelting to produce doré.

Reports

Website: https://www.serabigold.com/operations/palito-complex/

Report Date: 2018

Region: Brazil

Project Status:

Commodity: Gold, Silver, Copper

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Palito Complex: Ore Sorting, Flotation, and Cyanidation in Brazil’s Tapajós Region

Serabi Gold's Palito Complex in Pará State, Brazil, uses a multi-stage recovery flowsheet that combines ore sorting, copper flotation, gravity concentration, and CIP cyanidation to process gold ore from two underground mines.

The Palito Complex is an operating gold mining operation located in the Tapajós Mineral Province in the western part of Pará State in central north Brazil, near the eastern municipal boundary with the Novo Progresso Municipality. The complex consists of the Palito and São Chico gold deposits and forms part of the Jardim do Ouro property, a group of 26 claims totalling 64,707 hectares in the Tapajós valley. Serabi Gold plc, a United Kingdom registered gold mining and development company based in London, owns the complex through its wholly owned subsidiaries Serabi Mineração S.A. and Gold Aura do Brasil Mineração Ltda. Serabi initially acquired surface rights to the immediate Palito Mine area through a purchase agreement with artisanal miners in 2002 and has since acquired additional parcels of land. Ore mining at the Palito Mine is scheduled to continue until 2034, while mining at São Chico ends in 2030. The processing facilities have been operating continuously, with the recovery methods described in the 2025 Technical Report still valid for this update.

Critical Data

Parameter Value Unit Notes
Plant capacity 500 t/d Processing ore from both Palito and São Chico mines
Crushing feed rate 35 t/h Average feed rate using front-end wheel loader
Primary crusher product 60 mm Nominal size after jaw crusher
Screen top deck 38 mm Double-deck vibrating screen
Screen bottom deck 15 mm Double-deck vibrating screen
Ore sorter feed silo 20 t Capacity
Ore sorter washing screen aperture 8 mm Vibrating washing screen panels
Dewatering screen aperture 1 mm Screen-cloth aperture
Fine ore bins 100 t Separate bins for Palito and São Chico ore
Grinding product size 80% passing 120 µm All three grinding circuits
Hydrocyclone diameter 250 mm Grinding circuits 1 and 2
Intensive leach batch size 800 kg Gekko In-line Leach Reactor (ILR150)
Intensive leach duration 24 h Per batch
NaCN concentration in intensive leach 1.5 % Maintained solution concentration
Hydrogen peroxide addition 200 L Per batch in intensive leach
Flotation cell capacity 3.2 m³ Two duplex cells
Flotation retention time 10–12 min Rougher-scavenger circuit
Flotation pH 10–11 , Lime added in grinding circuit
Copper concentrate grade >20 % Cu Cleaner flotation product
Gold recovery to copper concentrate 50–70 % Of gold contained in Palito ore
Filter press capacity 300 kg/hr Two Andritz filter presses
Concentrate moisture 9 % Typical
Concentrate packaging 1 t wet Big bags
Concentrate shipping lots 20 t Shipped offsite for refining
Leach tank volume 185 m³ Two mechanically agitated tanks
Adsorption tank volume 74 m³ Six mechanically agitated tanks
CIP retention time 18 h Total
CIP slurry density 35 % solids Maintained in circuit
NaCN in leach tanks 250 ppm Maintained concentration
NaCN at adsorption discharge 100 ppm Attenuated concentration
CIP pH 10.5–11.0 , Maintained with lime
Carbon concentration in tanks 2–6 20 g/L Adsorption tanks
Carbon concentration in tank 1 40 g/L First adsorption tank
Loaded carbon removal frequency 24 h From adsorption tank 1
Elution column capacity 1.5 t Nominal
Elution temperature 130 °C Zadra process strip solution
Strip solution composition 2% caustic, 1% cyanide , Heated and pumped through column
Elution cycle duration 15 h Typical per cycle
Carbon regeneration temperature 750 °C Kiln heating
Cyanide detoxification residence time 1.5 h Nominal in destruction tank
Cyanide discharge level <5 ppm CNWAD After INCO air/SO2 process
Tailings feed rate Not stated , Slurry from last CIP tank
Sodium cyanide consumption 1.100 kg/t 2025 value
Grinding media consumption 1.282 kg/t 2025 value, steel balls
Lime consumption 1.947 kg/t 2025 value
Collector consumption 0.059 kg/t 2025 value
Frother consumption 0.029 kg/t 2025 value
Sodium hydroxide consumption 0.096 kg/t 2025 value
Hydrogen peroxide consumption 0.015 kg/t 2025 value
Sodium metabisulfite consumption 0.653 kg/t 2025 value
Activated carbon consumption 0.108 kg/t 2025 value
Big bag consumption 0.024 kg/t 2025 value
Cyanide share of consumables cost 50 % Of total consumables cost
Grinding media share of consumables cost 25 % Of total consumables cost
Mining rate since 2014 ~450 t/d Palito and São Chico combined
Total mined 2014–January 2026 1.8 Mt At 6.75 g/t Au
LOM average processing rate 334 t/d Range 306–366 t/d based on Mineral Reserves
Mine dewatering, Palito 10 L/sec Approximate
Mine dewatering, São Chico 17 L/sec Approximate
Total mine airflow, Palito 5,950 m³/min Approximately 210,000 cfm
Total mine airflow, São Chico 1,060 m³/min Approximately 63,400 cfm
Process water requirement 40 m³/h Total
Recycled water from tailings 32 m³/h 80% of total requirement
Freshwater from dam 8 m³/h 20% of total requirement
Freshwater consumption 60 m³/day Approximate, camp use
Tailings Area 16 volume 114,588 m³ Clay lined disposal area
Tailings Area 17 volume 145,000 m³ Clay lined disposal area
PDR capacity 3,918,330 m³ Final dry tailings disposal area, equivalent to 8.6 Mt
Power supply, Palito 1,000,000 kWh/month Approximately, from grid and diesel generators
Installed electric load, Palito 2.5 MW
Power supply, São Chico 594 kW Approximately 700 kVA
Diesel storage, Palito 80 m³ Includes 10 m³ dedicated for power generation
Diesel storage, São Chico 35 m³

Overview

The Palito process plant handles ore from both the Palito and São Chico underground mines. Palito ore follows a flowsheet that includes crushing, grinding, copper flotation, and carbon-in-pulp (CIP) cyanidation of the gold and silver values contained in the copper flotation tailings. Low grade development ore from the Palito mine is upgraded by an ore sorter after crushing and before grinding. São Chico ore is processed in a separate grinding circuit that includes gravity concentration and intensive cyanide leaching of the gravity concentrate. The São Chico gravity tailings are combined with the Palito copper flotation tailings in the CIP cyanidation circuit.

Gold and silver values extracted in the CIP circuit are adsorbed onto activated carbon. Loaded carbon is eluted to remove the adsorbed values into an upgraded solution that flows through electrowinning cells. Gold and silver are recovered as a cathodic precipitate, which is then fluxed and smelted to produce a final doré product.

The processing facilities have been operating continuously since the effective date of the 2025 Technical Report without differences in plant performance. The process description that follows was taken from that report and remains valid for this update.

Due to the high variability of Palito and São Chico run-of-mine ore, material from each front and stope in both mines is crushed separately on a batch basis and stockpiled individually. The crushed product from each batch is sampled as it falls onto the product conveyor. After sample analysis, the separate stockpiles are blended using a front-end wheel loader to produce a consistent mill feed blend.

Key Process Stages

Crushing begins with run-of-mine ore transported by trucks and stockpiled in an area close to the crushing plant. A front-end wheel loader feeds the ore to a jaw crusher at an average rate of 35 t/h, where it is reduced to a nominal size of 60 mm. A conveyor transports the primary crushed ore to a double-deck vibrating screen with a top deck size of 38 mm and a bottom deck size of 15 mm. Material larger than 38 mm reports to the secondary crusher. Material between 15 mm and 38 mm either reports to two tertiary crushers operating in parallel or, if grade is low, is removed from the circuit and stockpiled for ore sorting. The secondary and tertiary crushers operate in closed circuit with the screen and produce a product of less than 15 mm. The final product is transported via stacker conveyor to crushed ore stockpiles.

Ore sorting processes the low grade medium fraction material between 15 mm and 38 mm. This material is loaded into a 20 tonne silo and withdrawn by variable speed vibrating feeder onto a washing screen fitted with 8 mm aperture panels. Water jets wash the ore as it passes over the screen to remove fine material from particle surfaces. Screen oversize falls onto the ore sorter feed conveyor. Screen undersize reports to a dewatering screen fitted with 1 mm aperture cloth that recovers coarse particles between 1 mm and 15 mm into a bunker for reclaim. The dewatering screen undersize flows to a decantation pond where fine material smaller than 1 mm settles and is periodically removed for mill feed.

Washed ore passes under two scanning principles on a high-speed conveyor. Photometric colour measures surface colour of each particle. X-ray transmission measures atomic density. A computer algorithm classifies each particle as ore or waste based on selection criteria. Air jets separate the classified particles at the end of the conveyor. The upgraded ore product returns to the crushing circuit where it is crushed to minus 15 mm for mill feed. Barren waste is loaded into trucks and transported to a waste stockpile.

Grinding uses three parallel circuits that process Palito or São Chico ore independently. Ore is loaded into separate 100 t fine ore bins. Variable speed vibrating feeders withdraw ore onto mill feed conveyors. Feed is weighed and sampled every 30 minutes with automatic cross-cut samplers. Grinding circuit 1 processes Palito ore exclusively in a ball mill in closed circuit with a 250 mm hydrocyclone. The final ground product of 80% passing 120 µm reports to copper flotation. Grinding circuit 2 processes São Chico ore exclusively and includes a Falcon SB-750B centrifugal concentrator. Concentrate reports to intensive leaching. Cyclone overflow at 80% passing 120 µm reports directly to CIP cyanidation where it combines with the Palito flotation tail. Grinding circuit 3 can process either ore. Its final product reports to copper flotation for Palito ore or to CIP cyanidation for São Chico ore.

Intensive leaching treats the gravity concentrate from São Chico ore. Concentrate is discharged to a 4 ton hopper and leached in 800 kg batches in a Gekko In-line Leach Reactor for 24 hours. Leaching uses a cyanide solution maintained at 1.5% NaCN with 200 L of hydrogen peroxide added per batch. The leach solution circulates through a separate electrowinning cell in the gold room. Recovered gold is smelted as doré and shipped offsite for final refining.

Flotation consists of a conditioning tank followed by rougher, scavenger, and cleaner cells. A thiocarbamate collector (A3894) is added for selective copper flotation. Lime maintains pH at 10–11. Methyl isobutyl carbinol serves as frother. The rougher-scavenger circuit has two duplex cells with 3.2 m³ capacity each and 10 to 12 minutes retention time. The first rougher cell product advances to one stage of cleaner flotation. Scavenger concentrate recycles to the conditioning tanks. Cleaner flotation produces a copper concentrate containing more than 20% copper with 50% to 70% of the gold from Palito ore recovered into it. Scavenger tails pump to CIP cyanidation. The cleaner concentrate is filtered in two Andritz filter presses at 300 kg/hr capacity each. Filtered concentrate discharges into 1 t wet big bags at 9% typical moisture. The bagged concentrate ships offsite in 20 t lots for refining.

CIP cyanidation uses two 185 m³ mechanically agitated leach tanks and six 74 m³ mechanically agitated adsorption tanks. Total retention time is about 18 hours at 35% solids. Cyanide concentration is maintained at 250 ppm NaCN in the leach tanks and attenuates to about 100 ppm NaCN at adsorption tank discharge. Lime maintains pH at 10.5 to 11.0. Carbon concentration in the adsorption tanks is 20 g/L except the first tank at 40 g/L. Inter-tank screens retain carbon in tanks 1 to 6. Loaded carbon from tank 1 is removed every 24 hours and transferred to elution. After elution, barren carbon is regenerated and returned to tank 6. Carbon advances counter-currently using airlifts. New leaching tanks were installed during 2022 and commissioned at the end of 2022 and the first quarter of 2023.

Elution and gold refining starts with loaded carbon washed free of pulp and transferred to an acid wash column. The carbon is washed with 2% hydrochloric acid solution, rinsed with water, and transferred to an elution column with 1.5 tons nominal capacity. Elution follows the Zadra process. Strip solution containing 2% caustic and 1% cyanide is heated to 130°C and pumped through the column. The pregnant solution passes through an electrowinning cell where gold precipitates onto steel wool cathodes. Cathodes are washed to recover gold and silver sludge. The sludge is dried, mixed with flux reagents, and smelted to produce doré. The doré bar is sampled and shipped offsite for final refining. Barren solution returns to a holding tank and recirculates until elution completes. Each elution cycle is typically 15 hours.

Carbon regeneration processes barren carbon from the elution column. The carbon is screened for particle size control and heated to 750°C in the kiln to remove organic contaminants and regenerate the carbon surface near its new adsorption capability. After regeneration the carbon returns to the last adsorption tank in the CIP circuit.

Cyanide detoxification treats the slurry from the last CIP tank in a mechanically agitated destruction tank with a nominal residence time of 1.5 hours. The INCO air/SO2 process reduces cyanide levels to less than 5 ppm CNWAD. The detoxified slurry passes through a carbon safety screen and is pumped to the tailings dam.

Additional Interesting Data and Summary

The ore sorter was commissioned in January 2020. Operating results for 2020 through 2025 show only low grade Palito ore passed through the sorter. Total feed over this period was 163,207 t at 1.73 g/t Au. Total product was 19,399 t at 9.79 g/t Au. Total reject was 143,808 t at 0.64 g/t Au.

Plant production results for 2014 to 2025 show total milled ore of 2,008,740 t at 6.80 g/t Au with 92.0% recovery, producing 404,020 oz Au. Flotation tailings processed over the same period totalled 139,411 t at 3.34 g/t Au with 75.8% recovery, producing 11,361 oz Au. Combined total production was 415,381 oz Au. Milled ore tons and recovery remained relatively consistent for 2017 to 2021. The milled ore feed grade declined for a period in 2020 for reasons relating to the COVID-19 pandemic. Old flotation tailing stockpiles were processed by directly feeding into the CIP circuit, with average gold recovery of 77.0%.

Process plant consumables for 2018 to 2026 show sodium cyanide as the largest consumable cost item at 50% of total, followed by grinding media at almost 25%. Consumable consumption rates for 2025 included sodium cyanide at 1.100 kg/t, steel balls at 1.282 kg/t, lime at 1.947 kg/t, collector at 0.059 kg/t, frother at 0.029 kg/t, and sodium metabisulfite at 0.653 kg/t.

Tailings are disposed into existing clay lined disposal areas 16 and 17 located adjacent to the processing plant. Deposition alternates between the two areas, with one active and receiving fresh tailings while the other is in a drying process. Dry tailings are removed and dry-stacked in the final dry tailings disposal area, the Pilha de Rejeito. Tailings areas 16 and 17 are then re-used until the remaining Mineral Reserves are processed.

The process water requirement is 40 m³/h, of which 80% is recycled from the tailing disposal areas and 20% comes from the freshwater dam. Electrical power at Palito is provided from the local power grid through a 34.5 kV overland line and by diesel generators. Approximately 40% of power needs come from on-site generators and 60% from the grid.

Key Processes

  • Crushing: Single stage jaw crusher followed by double-deck screening and closed-circuit secondary and tertiary cone crushers producing minus 15 mm product
  • Ore sorting: X-ray transmission and photometric colour sorting of low grade 15–38 mm fraction with air jet separation
  • Grinding: Three parallel ball mill circuits with hydrocyclone classification producing 80% passing 120 µm
  • Gravity concentration: Falcon SB-750B centrifugal concentrator on São Chico ore
  • Intensive leaching: Gekko In-line Leach Reactor treating gravity concentrate in 800 kg batches with cyanide and hydrogen peroxide
  • Flotation: Thiocarbamate collector based copper flotation with rougher, scavenger, and cleaner stages producing concentrate above 20% copper
  • CIP cyanidation: Two leach tanks and six adsorption tanks recovering gold and silver from combined flotation tailings and gravity tailings
  • Elution: Zadra process with acid wash, electrowinning, and smelting to produce doré
  • Carbon regeneration: Thermal kiln treatment at 750°C
  • Cyanide detoxification: INCO air/SO2 process reducing cyanide to below 5 ppm CNWAD

Source: NI 43-101 Technical Report, Palito Complex, Para State, Brazil, June 1, 2026. Project website: Palito Complex

Mineral processing basics

Scroll to Top