Lac a Paul Project — 2013 Technical Report

The 2013 technical report presents a feasibility-study design for a 55,000 tpd phosphate ore beneficiation plant at the Lac a Paul site to produce 3 million tonnes per year of apatite concentrate.

Report context

This NI 43-101 technical report, dated November 2013, documents a feasibility study to produce 3 million tonnes per year of high purity apatite concentrate at the Lac a Paul Project in Québec, Canada. The processing plant is designed for a nominal milling capacity of 55,000 tpd of run-of-mine ore and is located at the Lac a Paul site.

Processing route

Overview

The phosphate ore beneficiation activities at the Lac a Paul site include crushing, grinding, flotation, filtration and drying of the concentrate. The phosphate rock concentrate is then transported from the site by trucks. Process flowsheets and plant layouts were prepared for a milling rate of 55,000 tpd of ROM ore.

Crushing and stockpiling

The crushing plant is designed with an overall availability of 70% and is scheduled to operate on average 18 hours per day at an average hourly rate of 3,041 t/h (dry basis). The ROM stockpile has a total capacity of 500,000 tonnes. Crushed ore is fed to a 50,000 tonne dome storage silo, which supplies the milling plant.

Grinding

The milling plant will be fed from the 50,000 tonne dome storage silo. The nominal SAG mill capacity is 2,289 tph, with a maximum SAG mill capacity of 2,726 tph. The turndown capacity is 1,245 tph, based on one ball mill being removed from service along with a flotation train. The milling and downstream plants have an overall availability of 93%, equating to 339 days of effective mill operation per year. Plant capacity is dependent on the type of ore being processed from the mine, with changes in ore density impacting throughput and grind size.

Flotation, filtration and drying

The flowsheet includes flotation as the primary concentration method, followed by filtration and drying of the concentrate.

Key reported parameters

Parameter Unit Value Basis
Nominal milling rate tpd 55,000 Design
Annual ROM feed rate tpy 18,648,025 Design
Concentrate average production rate tpy 3,000,000 Design
Concentrate nominal production rate tpd 8,740 Design
Average head grade (weighted) % P₂O₅ 6.88 Design
Concentrate grade % P₂O₅ 38.6 Design
Concentrate recovery % 90 Design
Overall concentrate weight recovery % 16.04 Design
Crushing plant overall availability % 70 Design
Overall beneficiation plant availability (milling and downstream) % 93 Design
Crusher nominal feed rate (dry basis) tph 3,041 Design
Nominal SAG mill capacity tph 2,289 Design
Maximum SAG mill capacity tph 2,726 Design
Turndown SAG mill capacity tph 1,245 Design
Crushed ore silo capacity t 50,000 Design
ROM stockpile capacity (total) t 500,000 Design
Concentrate storage capacity (mine site) t 200,000 Design
Final P₂O₅ product moisture % 1 ± 0.5 Design

Project website: https://www.arianne-inc.com/about/

Technical qualifications

The 2013 technical report is a feasibility study. The processing plant design is based on run-of-mine from the mine pits with a weighted average P₂O₅ content of 6.88%. The report states that the plant capacity is dependent on the type of ore being processed, with changes in ore density impacting throughput and grind size. No historical operating data or testwork results are reported in the processing sections of this document. The report notes that detailed process information may be found in the Feasibility Study Report. No economic parameters, ownership details, current project status, or links are provided in the processing sections reviewed.

Source: Feasibility Study to Produce 3Mtpy of High Purity Apatite Concentrate at the Lac a Paul Project, Québec, Canada, NI 43-101 Technical Report, November 2013, Section 17 Recovery Methods.

Mineral processing basics

Scroll to Top