GMV Minerals' August 2025 updated preliminary economic assessment for the Mexican Hat gold project in Cochise County, Arizona, crushes 3.5 Mt a year to 38 mm and stacks it in 10 m lifts on a 32.6 Mt pad.
The NI 43-101 Technical Report, Updated 2025 Preliminary Economic Assessment, Mexican Hat Project, Cochise County, Arizona, was prepared for GMV Minerals Inc. with an effective date of August 8, 2025 and an issue date of August 20, 2025. The deposit is to be mined by open pit. A contractor will run a two-stage crushing plant at a nominal 10,000 t/d. The crushed ore will be heap leached with cyanide, and gold will be recovered in an adsorption, desorption and recovery (ADR) plant supplied as a vendor package.
Critical Data
| Parameter | Value | Unit | Notes |
|---|---|---|---|
| Report effective date | August 8, 2025 | Not applicable | Updated PEA for GMV Minerals Inc. |
| Throughput | 3.5 Mt/a (10,000 t/d) | Not applicable | 350 days a year |
| Crushing rate | About 1,110 | t/h | 75% availability; contractor-operated |
| Crushed product | 80% passing 38 | mm | From 1,400 mm feed |
| Crusher work index | 15.4 | kWh/t | Not applicable |
| Stacking | 833 t/h, 12 h/d | Not applicable | 10 m lifts |
| Lime | 1.5 | kg/t | Added on the reclaim conveyor |
| Heap capacity | 32.6 | Mt | Two phases, about 9.3 years; maximum height 72 m |
| CIC | Two trains of five columns | Not applicable | Carbon loading 2,523 g/t nominal, 4,000 g/t maximum |
| Elution | 3 t pressure strip at about 145°C | Not applicable | 11 bed volumes at 2 BV/h |
| ADR availability | 92 | % | Not applicable |
| Liner | 80-mil LLDPE over GCL | Not applicable | Designed to Arizona BADCT criteria |
Overview
Run-of-mine ore is crushed in two stages from 1,400 mm to 80% passing 38 mm and conveyed to a stockpile with 24 hours of live capacity. Two 4 by 15 ft feeders reclaim it onto a 1,000 m long, 42 inch overland conveyor, with lime added on the way. Grasshopper conveyors and a radial stacker place it on the heap leach pad. Cyanide solution is applied, and the pregnant leach solution (PLS) is collected in a lined pond and pumped to the ADR plant.
Key Process Stages
Crushing. The two-stage plant is supplied, operated and maintained by the crushing contractor. It is designed to crush 3.5 Mt a year at 75% availability.
Stacking and leaching. Ore is stacked 12 hours a day at 833 t/h in 10 m lifts. The heap leach facility (HLF) is built in two phases, of about 192,201 m² and 373,311 m², for a total capacity of 32.6 Mt at a heap density of 1.5 t/m³. Phase 1 holds about two years of ore in four lifts. Phase 2 expands west to hold the life-of-mine ore in seven lifts, to a maximum heap height of 72 m at an overall slope of 2.5H:1V.
Carbon adsorption. PLS is pumped through two trains of five carbon-in-column (CIC) tanks in series, with carbon advanced counter-current so the richest solution meets the most loaded carbon. Loaded carbon is transferred daily to elution.
Acid wash and elution. Carbon is acid washed with hydrochloric acid at atmospheric pressure, rinsed for 30 minutes, and stripped under pressure at about 145°C with caustic strip solution. About 11 bed volumes are pumped at 2 bed volumes an hour through the electrowinning cells.
Electrowinning and refining. Two electrowinning cells plate gold onto steel wool. A 20% bleed of barren solution is recommended to prevent contaminant build-up. Sludge is filter pressed, oven dried, retorted for mercury and smelted in an electric induction furnace at about 1,230°C to doré.
Carbon regeneration. Stripped carbon is regenerated in a horizontal rotary kiln at 750°C after every strip. The report notes that skipping regeneration lowers loading efficiency and increases gold losses in solution.
Additional Interesting Data and Summary
The HLF liner is a composite of 80-mil double-sided textured LLDPE geomembrane over a geosynthetic clay liner or low-permeability soil (no more than 1×10⁻⁶ cm/s), on compacted bedding. It is protected by at least 0.6 m of free-draining overliner, with a herringbone network of 100 mm perforated pipes at up to 6 m centres feeding 450 mm and 600 mm collectors. Two ponds serve the pad: a PLS pond and an event pond sized for the 100-year, 24-hour storm. The design is to meet or exceed the Arizona Department of Environmental Quality's prescriptive BADCT criteria.
In summary, the 2025 Mexican Hat PEA is a conventional Arizona crushed-ore heap leach at 10,000 t/d, with contractor crushing to 38 mm, a tall two-phase pad and a packaged two-train CIC ADR plant.
Key Processes
- Contractor two-stage crushing to 80% passing 38 mm
- Stockpile reclaim and overland conveying with lime addition
- Grasshopper and radial stacker placement in 10 m lifts
- Cyanide heap leaching on a composite-lined pad
- Two-train carbon-in-column adsorption
- Acid wash and pressure elution
- Electrowinning, mercury retorting and induction smelting
- Rotary kiln carbon regeneration
Source: NI 43-101 Technical Report, Updated 2025 Preliminary Economic Assessment, Mexican Hat Project, Cochise County, Arizona, USA, prepared for GMV Minerals Inc., effective date August 8, 2025.
Earlier report summaries
Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.
Mexican Hat Project — 2018 Technical Report
This report presents the mineral processing and metallurgical testing for the Mexican Hat Project as of December 2018.
Report context
This Technical Report is dated December 18, 2018, with an effective date of December 6, 2018. The report was prepared in accordance with Form 43-101F1 for the Mexican Hat Project. It addresses mineral processing and metallurgical testing, mineral resource estimates, and supporting technical information.
Processing route
McClelland Testwork
Section 13.1 of the report describes metallurgical testing conducted by McClelland. The testwork examined processing characteristics relevant to the project but no specific flowsheet details, performance results, or design parameters are provided in the available report sections.
Bureau Veritas Testwork
Section 13.2 of the report identifies metallurgical testing performed by Bureau Veritas. The testing program evaluated processing factors for the project materials. No flowsheet design details, operational performance data, or specific testwork outcomes are contained in the supplied report excerpts.
Key reported parameters
| Parameter | Value | Basis |
|---|---|---|
| Report effective date | December 6, 2018 | Technical report date |
| Report issue date | December 18, 2018 | Technical report date |
| Report reference number | M3-PN180154 | Document identifier |
| Testwork laboratories | McClelland, Bureau Veritas | Sections 13.1 and 13.2 |
| Resource estimate basis | Current estimate, previous estimates, database, assays, composites | Section 14 |
Project website: https://www.discogs.com/release/14568765-Unknown-Artist-Mexican-Hat-Dance
Project website: https://miningdataonline.com/property/3426/Mexican-Hat-Project.aspx
Project website: https://gmvminerals.com/projects/mexican-hat/overview/
Technical qualifications
This article is limited to the original technical-report Markdown evidence provided. No flowsheet details, design parameters, performance data, economic analysis, ownership information, or current project status are available from the supplied report sections. The report states that mineral resource estimates are presented in Section 14, which includes basis of current resource estimate, previous estimates, database, input data analysis, assays, and composites. The testwork summary in Section 13 contains only laboratory names without process or performance details.
*Source: Mexican Hat Project , Form 43-101F1 Technical Report, December 18, 2018, Sections 13 and 14.*

