Marimaca Feasibility Study Plans 50 kt a Year of Grade A Cathode From Agglomerated Dynamic Heap Leaching and SX-EW

Marimaca Copper's October 2025 feasibility study for the Marimaca oxide deposit in Chile's Antofagasta Region treats 12 Mt a year of oxide ore, then 16 Mt a year of oxide and sulphide ore with salt addition and heap aeration.

The Marimaca Oxide Deposit Project NI 43-101 Technical Report and Feasibility Study, Antofagasta Region, Chile, was prepared by Ausenco Chile for Marimaca Copper Corp. with an effective date of August 25, 2025 and a report date of October 8, 2025. The report states that the recovery methods rest on well-proven unit operations, with nothing unique or novel. Ore is crushed in three stages, agglomerated with acid and leached on a dynamic (on-off) heap, and copper is recovered by solvent extraction and electrowinning (SX-EW) as Grade A cathode at 50 kt a year. The plant uses seawater pumped from Mejillones.

Critical Data

Parameter Value Unit Notes
Report effective date August 25, 2025 Not applicable Ausenco Chile for Marimaca Copper Corp.
Phase 1 (Years 1 to 5) 12 Mt/a oxide ore Not applicable 0.53% Cu head grade, 77.8% recovery
Phase 2 (Years 6 to 13) 16 Mt/a oxide and sulphide ore Not applicable 0.37% Cu, 68.3% recovery
Cathode production 50,000 t/a Grade A
Primary crusher 50 x 65 inch gyratory, 450 kW Not applicable Product P80 148 mm
Secondary and tertiary crushers HP900 standard and short head, 671 kW each Not applicable Not applicable
Final crush P80 12.7 mm Tertiary screens in closed circuit
Lift height 4 m Radial stacker
Irrigation 10 L/h/m² Not applicable Solution to ore ratio 3.0:1 oxides, 2.2:1 sulphides
Solvent extraction 3 extraction, 1 stripping, 2 washing Not applicable Extraction efficiency above 90%
Plant power 244 GWh/a (20.3 kWh/t) Phase 1; 281 GWh/a (17.6 kWh/t) Phase 2 Not applicable Not applicable

Overview

Phase 1, from Years 1 to 5, treats oxide ore at 12 Mt a year. Phase 2, from Years 6 to 13, treats oxide and sulphide ore at 16 Mt a year. In Phase 2, sodium chloride is added at agglomeration to speed up copper dissolution from sulphide minerals, and blowers aerate the heap. Primary crushing runs at 70% availability, secondary crushing to stacking at 75%, and solution handling, SX and EW at 98%.

Key Process Stages

Primary crushing. 220 t trucks unload into a 352 t dump hopper with two-sided dumping and a rock breaker. A 50 by 65 inch gyratory crusher with 450 kW produces P80 148 mm. An apron feeder and overland conveyor carry the product to a coarse ore hopper with 30 minutes of live capacity.

Secondary crushing. A mobile chute splits the ore into two parallel lines, each with a double-deck banana screen and an HP900 standard cone crusher. The product is P80 49 mm in Phase 1 and 56 mm in Phase 2.

Tertiary crushing. Double-deck banana screens close three HP900 short-head cone crushers fed by belt feeders, producing P80 12.7 mm. Primary to secondary crushing is built for 16 Mt a year from the start. Tertiary crushing is built for 12 Mt a year, and Phase 2 adds a third screen and crusher line.

Agglomeration. Concentrated sulphuric acid and raffinate are added in an agglomeration drum: one 12 Mt a year line in Phase 1, plus a 4 Mt a year line in Phase 2. When salt is added in Phase 2, the reactions release gases containing hydrochloric and sulphuric acid, so the drums have extraction and caustic scrubbing systems. Salt arrives in 30 t trucks and is stored in a 3,507 t shed, about four days' supply.

Stacking and dynamic heap leaching. An overland conveyor, tripper, 17 grasshopper conveyors (20 in Phase 2) and a radial stacker place the ore in 4 m lifts on a heap of 12 cells, rising to 15. Each cycle runs loading, rest, irrigation, drain-down and removal of the leached ore. Irrigation is in two stages at 10 L/h/m², first with intermediate leach solution (ILS) and then with raffinate.

SX-EW. Pregnant leach solution goes to a solvent extraction plant with three extraction stages, two washing stages and one stripping stage. The tank house electrowins Grade A cathode, using cobalt sulphate, guar and surfactant as additives.

Additional Interesting Data and Summary

The solution ponds include desanding, PLS, ILS, raffinate, seawater and emergency ponds, enlarged in Phase 2. Leached ore is removed from the pad and disposed of at the end of each cycle, as the dynamic heap method requires.

In summary, the 2025 Marimaca feasibility study is a seawater-based agglomeration, dynamic heap leach and SX-EW copper operation. It starts on oxide ore at 12 Mt a year and moves to a chloride-assisted, aerated leach of mixed oxide and sulphide ore at 16 Mt a year, holding 50 kt a year of cathode output.

Key Processes

  • Three-stage gyratory and cone crushing to P80 12.7 mm
  • Acid and raffinate agglomeration (with salt in Phase 2)
  • Conveyor stacking in 4 m lifts
  • Dynamic on-off heap leaching with ILS and raffinate irrigation
  • Heap aeration for sulphides (Phase 2)
  • Solvent extraction (3 extraction, 2 washing, 1 stripping)
  • Electrowinning of Grade A copper cathode
  • Seawater supply and scrubbing of agglomeration gases

Source: Marimaca Oxide Deposit Project NI 43-101 Technical Report & Feasibility Study, Antofagasta Region, Chile, prepared by Ausenco Chile Limitada for Marimaca Copper Corp., effective date August 25, 2025.

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

Marimaca Project — 2020 Technical Report

Marimaca Project — 2020 Technical Report

Company Marimaca Copper
Date 2020
Region Chile
Commodities Copper
Mine Type Open Pit
Throughput 5.4 – 9.0 Mt/y
Mine Life 12 years
Annual Production 40,000 t/y Cu
Status Development

Executive Summary

The Marimaca Project is a 12-year development-stage mining operation located in Chile, designed to produce Grade-A copper cathodes through a conventional salt acid leaching process. The project utilizes a comminution circuit followed by crushed mineralized material heap leaching and ROM leach facilities, coupled with Solvent Extraction (SX) and Electrowinning (EW) plants. The process relies on seawater-based solutions with sulphuric acid and salt addition to leach both oxide and sulphide copper mineralization.

The mine plan is divided into two phases. Phase 1 (Years 1-5) focuses on oxide mineralization with a processing capacity of 5.4 Mt/y, while Phase 2 (Years 6-12) expands to 9.0 Mt/y, incorporating a higher proportion of sulphide copper mineralization. The facility is designed for a nominal capacity of 40,000 t/y of copper cathodes, with total LOM production estimated at approximately 430 kt of cathodes. Recovery rates are projected at 79% for Phase 1 and 74% for Phase 2.

Water management is a critical component, utilizing a dedicated reverse osmosis plant for SX/EW requirements and recovering brine reject as process water. The process includes a three-stage crushing circuit, agglomeration drums, and a two-stage leaching cycle involving Intermediate Leach Solution (ILS) and raffinate. The project is currently in the PEA stage as of 2020.

Operational Details

Processing Methods

Reports

Website: https://marimaca.com/marimaca-copper-project-overview/

Report Date: 2020

Region: Chile

Project Status: Development

Commodity: Copper

Throughput: 5.4 – 9.0 Mt/y

Mine Life: 12 years

Mine Type: Open Pit

Technical Report for the Marimaca Copper Deposit

Technical Report for the Marimaca Copper Deposit

Company Coro Mining Corp NCL SpA
Mine Marimaca
Date Unknown
Region Unknown
Commodities Copper

Executive Summary

This technical report covers the Marimaca Copper Deposit, presented by Coro Mining Corp NCL SpA. The document outlines the technical aspects of the project, specifically focusing on recovery methods and project infrastructure.

The primary recovery method identified for the Marimaca deposit involves heap leaching techniques. This process is designed to produce copper cathode through a Solvent Extraction and Electrowinning (SXEW) circuit. The report snippet provided covers Section 15 on Recovery Methods, along with references to Project Infrastructure and Adjacent Properties.

While specific operational metrics such as throughput and mine life are not detailed in this excerpt, the strategic focus remains on the efficient extraction of copper via heap leach methods. Further details regarding the project’s infrastructure and surrounding geological context are included in subsequent sections of the full technical report.

Entities

  • entities/Marimaca_Mine

Website: https://www.listcorp.com/asx/mc2/marimaca-copper-corp/news/marimaca-announces-mod-feasibility-study-3232257.html

Report Date: Unknown

Region: Unknown

Project Status:

Commodity: Copper

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Marimaca 1-23 Claim Project — 2023 Technical Report

This report describes the proposed recovery methods for the Marimaca 1-23 Claim Project, which will use the existing Ivan Plant facilities for copper oxide ore treatment via crushing, agglomeration, heap leaching, solvent extraction, and electrowinning.

Report context

This technical report presents a definitive feasibility study for the Marimaca 1-23 Claim Project, located in the Antofagasta region, II Region, Chile. The processing strategy is based on the acquisition of the Ivan Plant, located approximately 20 km south of Marimaca, with ore to be trucked to the plant for treatment. The plant last operated in 2012.

Processing route

Plant acquisition and design basis

The project will process ore from the Marimaca mine at the Ivan Plant facilities. The proposed flowsheet is a conventional copper oxide treatment circuit comprising crushing, acid agglomeration, heap leaching, solvent extraction, and electrowinning.

The plant design is based on annual working rates of 360 days for the crushing plant and 365 days for the leaching and SX-EW circuits. The crushing, agglomeration, and leaching circuits have a nominal throughput of 1.8 Mtpa, while the SX-EW plant will operate at a nominal capacity of 10.0 ktca.

The average head grade considered for plant design is 0.80% CuT. Available resources were estimated at 24.6 Mt, establishing a Life of Mine of 12 years and a Life of Plant of 15 years.

Crushing

The Ivan plant has two crushing lines, designated Line 1 and Line 3. A previously existing Line 2 was disabled and its equipment was redistributed to the other lines. The design incorporates an expansion of Line 1 with a third comminution stage to achieve a nominal capacity of 278 t/h, feeding an existing 1,600 live tons capacity stockpile.

The first crushing stage operates in open circuit with pre-screens and a jaw crusher. The second stage also operates in open circuit with pre-screens and a cone crusher. The third stage has a closed inverse circuit with a pre-screen and two parallel cone crushers. The two tertiary crushers are to be taken from Line 3.

The crushing plant will use nine re-utilized conveyors, with required maintenance. Specifically, conveyor 2204403-005 will require motor and reducer replacement to 30 HP to increase belt velocity. The dust suppression system will be rehabilitated, with new connections added for ore transfer in the tertiary stage.

Agglomeration

The existing agglomeration plant will be reconditioned for a nominal capacity of 278 t/h. The Line 1 agglomeration circuit will be utilized, including a vibrating feeder and conveyor feeding an existing 2.0 m diameter by 6.0 m long agglomeration drum.

A new sample cutter will be installed for ore control from the crushing stage. The acid and water supply manifolds to the agglomeration process will be replaced, with new manifolds featuring instrumentation and automation control. Due to high corrosion levels, conveyor 220-4403-007 at the drum discharge, the feeding chute, and the acid and water dosing flutes will be replaced.

Heap leaching

Agglomerated ore will be transported by trucks to the leaching pads, where a surface area of approximately 170,184 m² is available. Ore will be treated in 25 dynamic heaps, each 1.5 m high, with two modules per heap. The projected pad area is equivalent to 50 leaching days, for an estimated leaching cycle of 35 effective leaching days.

Five existing ponds are located in the leaching area. Three will be reutilized for normal operation and reconditioned according to the process circuit, while one old pond will be reconditioned as an emergency reserve for controlled conduction of operational pond overflows.

Pregnant leach solution is expected to have an approximate copper concentration of 4 g/L, collected in an 8,300 m³ capacity PLS pond. Spent ore pads will be irrigated with raffinate and an intermediate solution, conveyed to a 13,550 m³ capacity ILS pond. A reconditioned 2,700 m³ raffinate pond is also included.

Irrigation will be by aspersion using grids over the heaps, maintaining the original plant grid configuration. A main matrix will allow heaps to be irrigated with raffinate or ILS according to heap stage. Each heap will have a pipeline manifold with adjustable irrigation flow.

Two horizontal centrifuge pumps in parallel with 110 kW engines will propel ILS through a 315 mm HDPE PN16 main pipe. The raffinate system will also have two horizontal centrifuge pumps in parallel, each with a 150 kW engine and a 315 mm HDPE PN16 main pipe. PLS will be pumped to the SX plant by two parallel 55 kW pumps through a 315 mm HDPE PN10 main pipe.

Spent ore will be transported to the existing ripio waste disposal site, with the authorized area verified as having sufficient capacity for the total amount throughout the Life of Mine.

Solvent extraction

The SX circuit is based on a reversible chemical reaction of ionic exchange between a copper-bearing PLS solution and an immiscible organic solution. The extraction step transfers copper ions to the organic phase, releasing hydrogen ions and increasing acidity of the resulting raffinate. In the re-extraction step, the loaded organic is contacted with poor electrolyte from the EW plant, where high acidity reverses the reaction. Copper transfers to the aqueous phase and is returned to the electrolyte.

Because the PLS concentration is calculated at close to 4 g Cu/L, the existing mixer-settler equipment was verified as having insufficient capacity for expected project flows. New equipment will be used for a nominal capacity of 263 m³/h. The SX circuit will comprise four mixer-settlers: two extraction stages in series (E1 and E2), one washing stage (L1), and one re-extraction stage (S1).

The tank farm requires no modifications, apart from adding a second charged organic tank of 5 m diameter and 3 m high. All piping and electrical engines in the SX area and tank farm will be replaced to comply with explosion-resistant standards.

Electrowinning

The existing EW building will house the electrowinning plant, which is divided into two sectors with thirty electrolytic cells. Each cell is constructed of vinyl-ester polymer concrete with capacity for 36 permanent stainless steel cathodes and 37 lead/calcium/tin alloy anodes. An electric circuit fed by two transformers and two DC rectifiers generates the current for electrolytic copper deposition on the stainless steel cathodes. No modifications are planned for the electrowinning stage, only flooring and structure refurbishment.

Rehabilitation works

The rehabilitation plan characterizes damage to existing concrete and steel facilities into categories. Light damage involves surface rehabilitation through partial stripping of linings and installation of acid protection systems. Medium damage involves deep cleaning or partial demolition to remove residues that may cause long-term structural weakening. Severe damage involves demolition of concrete in poor condition and removal of polluted soil to reach ground suitable for new foundations. Steel structures damaged by acid exposure will be replaced.

New works include construction of new structures according to plant expansion requirements, including excavation, compacted filling, concrete, and structure erection.

The rehabilitation program by area identifies severe damage and new works needed at the crushing, agglomeration, and leaching areas. The EW, SX, and tank farm areas each require light, medium, and severe damage repairs plus new works. The acid supply area requires light and severe damage repairs plus new works, and the water supply area requires severe damage repairs and new works.

Leaching pond recovery and new pad construction

For solution reservoirs, the project considers removing existing HDPE geomembranes and support material from ponds detected as eroded or not fit for new lining. Two HDPE layers (primary and safety) will be installed with a permeable geonet medium between them for conducting and detecting filtrations through a leak detector system.

Fifty leaching pads are configured according to process requirements, projected in existing available space across three terraces of different dimensions. Works include removing sterile material from existing pads, surface profiling, and preparation for new pad structures. The pad system includes base impermeabilization and a draining system with drains for collecting and conducting solutions to a main collecting gutter, then to PLS or ILS reservoirs.

Key reported parameters

Parameter Value Basis
Processing rate 1.8 Mtpa Design
Crushing plant annual operating days 360 days/year Design
Leaching/SX-EW annual operating days 365 days/year Design
Cathode production 10.0 ktca Design
Average head grade 0.80% CuT Design
Design criteria average grade 0.75% Design
Average recovery 65% based on CuT Design
Acid consumption 35 kg/t Design
Agglomeration/leach crushing capacity 278 t/h Design
Agglomeration drum 2.0 m dia. x 6.0 m long Existing equipment
PLS pond capacity 8,300 m³ Reconditioned
ILS pond capacity 13,550 m³ Reconditioned
Raffinate pond capacity 2,700 m³ Reconditioned
SX plant nominal capacity 263 m³/h New equipment
SX circuit stages 2 extraction, 1 wash, 1 re-extraction Design
Leaching pad area Approx. 170,184 m² Existing
Number of leaching heaps 25 Design
Heap height 1.5 m Design
Leaching cycle 35 effective days Design
Leaching days projected 50 days Design
Trucking distance 24 km Design
Water supply 54 m³/h (15 L/s) Design
Water consumption 0.25 m³/t Design
ILS pumps 2 x 110 kW horizontal centrifuge, parallel Design
Raffinate pumps 2 x 150 kW horizontal centrifuge, parallel Design
PLS pumps 2 x 55 kW, parallel Design
ILS/raffinate pipe 315 mm HDPE PN16 Design
PLS pipe 315 mm HDPE PN10 Design

Project website: https://marimaca.com/coro-consolidates-100-ownership-of-marimaca-project-and-announces-c16-8-million-financing/

Technical qualifications

The report does not include metallurgical testwork results beyond referencing general flow diagrams based on metallurgical test work. No specific recovery, grade, or throughput performance data based on actual operating experience from the Ivan plant is presented. The design parameters for recovery, acid consumption, and PLS concentration are stated as design criteria, not demonstrated operational results.

The report does not provide detail on the metallurgical testwork methodology, sample representativity, or testwork laboratory. No information is given on locked-cycle or pilot-scale test programs.

The leach cycle of 35 effective days is described as estimated, and the projected area equivalent to 50 leaching days appears to be a design assumption. The SX circuit configuration was determined from calculated PLS concentration, with verification that existing equipment has insufficient capacity for expected flows.

Where equipment is described as re-utilized, the report identifies required maintenance or rehabilitation works but does not quantify the condition assessment methodology or remaining equipment life. The reported pond capacities and pad areas are from the existing site configuration, with reconditioning or partial new construction required.

The EW plant description confirms no modifications beyond flooring and structure refurbishment, but no production rate for historical EW operation is provided. The two-electrode configuration and cell counts are given as existing plant details, not performance data.

Source: Marimaca 1-23 Claim Project, 2023 Technical Report, Recovery Methods section.

Mineral processing basics

Scroll to Top