McIlvenna Bay Project: Copper-Zinc Flotation Processing Circuit

McIlvenna Bay process plant flowsheet: crushing, SAG and ball milling, copper and zinc flotation with regrind, concentrate thickening and pressure filtration, filtered tailings and paste backfill

Overview

The McIlvenna Bay Project features a conventional copper-zinc processing plant designed to treat 4,900 tonnes per day (1.789 million tonnes annually) of blended ore from the CS and MS mineralization zones. The plant incorporates crushing, grinding, sequential copper-zinc flotation with concentrate regrind, and comprehensive dewatering circuits to produce saleable copper and zinc concentrates while managing tailings through pyrite flotation and paste backfill systems.

Key Process Stages

  • Primary Crushing: ROM ore crushed to 100% passing 245 mm (80% passing 125 mm) using FJ 1000 jaw crusher
  • Grinding Circuit: SAG mill (7.32m × 3.38m EGL, 3,500 kW) with pebble crusher in closed circuit with ball mill (5.03m × 7.85m EGL, 3,500 kW) producing P80 of 75 µm
  • Copper Flotation: Four 50 m³ rougher cells followed by regrind (M1000 IsaMill to P80 25 µm) and three-stage cleaning
  • Zinc Flotation: Four 50 m³ rougher cells with regrind (dual M1000 IsaMills to P80 20 µm) and three-stage cleaning
  • Pyrite Flotation: Jameson cell followed by three 50 m³ conventional cells for tailings desulphurization
  • Concentrate Dewatering: High-rate thickeners (6m for copper, 7m for zinc) producing 55% solids underflow filtered to 9% moisture cake
  • Tailings Management: Thickened to 55% solids, filtered to 15% moisture for dry stacking; pyrite concentrate used for paste backfill

Critical Data

Parameter Value
Nominal Throughput 4,900 tpd (1.789 Mtpa)
Crushing Availability 60%
Grinding Availability 92%
Bond Work Index (Blended) 14.7 kWh/t (Rod Mill), 16.5 kWh/t (Ball Mill)
Plant Feed Grades 1.27% Cu, 3.64% Zn, 0.56 g/t Au, 18.45 g/t Ag
Energy Consumption 18.4 MW average demand
Water Requirement 42 m³/h raw water
Grinding Media Consumption 0.53 kg/t (SAG), 0.66 kg/t (Ball Mill)
Major Reagent Consumption 93 g/t MIBC, 2,229 g/t Quicklime, 350 g/t Na₂S₂O₅

Special Features

The plant incorporates several advanced features including horizontal IsaMills for concentrate regrinding, automated reagent dosing systems, comprehensive water recycling (with 60% solids tailings thickener underflow), and integrated paste backfill production from pyrite concentrate. The metallurgical accounting system includes online stream analyzers (OSA) for real-time process control.

Technical report and processing history

The following archived source profiles have been consolidated here to preserve the project’s processing history and study context.

2025 Technical Report — McIlvenna Bay Project

2025 Technical Report — McIlvenna Bay Project

Company Foran Mining
Mine McIlvenna Bay Project
Date 2025
Region Saskatchewan, Canada
Commodities Copper, Zinc, Gold, Silver
Mine Type Underground
Throughput 4,900 tpd
Mine Life 18 years
Annual Production 1,788,500 dmtpa
Status Under Construction

Executive Summary

The McIlvenna Bay Project is an underground base and precious metals mine currently under construction in east-central Saskatchewan, Canada. The project is designed to treat copper-zinc sulphide ore with a nominal daily throughput of 4,900 tonnes, targeting an annual production of approximately 1.79 million tonnes over an 18-year mine life. The operation will produce saleable copper and zinc concentrates, with recoverable gold and silver credits, utilizing a conventional metallurgical flowsheet based on extensive test work and industry standards.

The processing plant features a comminution circuit comprising a primary jaw crusher, SAG mill, and ball mill in a closed circuit with cyclone classification. This is followed by sequential copper and zinc flotation circuits, utilizing tank cells for rougher and cleaner duties and horizontal IsaMills for concentrate regrinding. Final concentrates are dewatered using thickeners and horizontal pressure filters to produce filter cakes suitable for transport to toll smelters.

Tailings management involves a desulphurization circuit to produce pyrite concentrate for underground paste backfill, while non-sulphide tailings are filtered and dry-stacked in a Filtered Tailings Storage Facility (FTSF). The project infrastructure includes a compact site layout with a 324-person camp, on-site power generation transitioning to a provincial transmission line, and a comprehensive water management system to ensure environmental compliance and operational efficiency.

Reports

  • entities/McIlvenna_Bay_Mine
  • entities/Foran_Mining

Concepts

  • concepts/Jaw_Crushing
  • concepts/SAG_Milling
  • concepts/Ball_Milling
  • concepts/Flotation
  • concepts/Pressure_Filtration
  • concepts/Paste_Backfill

Website: https://www.eldoradogold.com/

Report Date: 2025

Region: Saskatchewan, Canada

Project Status: Under Construction

Commodity: Copper, Zinc, Gold, Silver

Throughput: 4,900 tpd

Mine Life: 18 years

Mine Type: Underground

Ore type: Sulphide (Copper-Zinc)

McIlvenna Bay Project — 2025 Technical Report

McIlvenna Bay Project — 2025 Technical Report

Company Foran Mining
Date 2025
Region Saskatchewan, Canada
Commodities Copper, Zinc, Gold, Silver
Mine Type Underground
Throughput 4,900 tpd
Mine Life 18 years
Status Under Construction

Executive Summary

The McIlvenna Bay Project is an underground base and precious metals mine located in east-central Saskatchewan, approximately 375 km northeast of Saskatoon. Currently under construction, the project is designed to treat copper-zinc sulphide ore with a nominal annual throughput of 1.789 million tonnes per annum (4,900 tpd). The mine is expected to operate for 18 years, producing copper and zinc concentrates along with payable gold and silver credits. The site benefits from existing infrastructure developed during the ADEX program, including access roads and power connections, with plans to transition to a grid-connected transmission line in Phase 2.

The process plant design utilizes a conventional metallurgical flowsheet featuring a comminution circuit followed by sequential copper and zinc flotation. Ore is crushed via a jaw crusher and ground in a SAG and ball mill circuit to a P80 of 75 µm. Concentrates are reground using horizontal IsaMills to fine particle sizes before flotation. The plant includes a pyrite flotation circuit for desulphurization, with pyrite concentrate used for underground paste backfill and non-sulphide tailings stored in a Filtered Tailings Storage Facility (FTSF).

Infrastructure development includes a compact site layout with a 324-person camp, administration offices, and a paste plant integrated with the process building. Power supply will initially rely on onsite LNG generation supplemented by the existing grid, transitioning to a 110/138 kV transmission line from SaskPower. Environmental management focuses on water conservation, contact water treatment, and progressive reclamation of the tailings facility.

Reports

  • reports/2025_Foran_McIlvenna_Bay

Website: https://www.eldoradogold.com/

Report Date: 2025

Region: Saskatchewan, Canada

Project Status: Under Construction

Commodity: Copper, Zinc, Gold, Silver

Throughput: 4,900 tpd

Mine Life: 18 years

Mine Type: Underground

Ore type:

McIlvenna Bay Project — 2014 PEA Technical Report

McIlvenna Bay Project — 2014 PEA Technical Report

Company Not Specified
Date December 22, 2014
Commodities Copper, Zinc
Throughput 5,000 tpd
Status PEA (Pre-Feasibility Study)

Executive Summary

The McIlvenna Bay Project Pre-Feasibility Study outlines a metallurgical processing plant designed to treat copper and zinc bearing material from three distinct mineralization zones (CSZ, L2MS, UWMS). The plant is designed for a throughput of 5,000 tonnes per day (1,825,000 tonnes per annum) and operates on a continuous basis with two 12-hour shifts per day. The flowsheet is engineered to produce copper concentrate, zinc concentrate, or a bulk concentrate depending on the feed mineralization type.

Processing involves conventional crushing followed by a semi-autogenous mill with a pebble crushing circuit and a ball mill grinding circuit. A unique talc pre-flotation step is included to remove detrimental talc prior to the main copper, zinc, and bulk flotation circuits. The flotation process utilizes rougher and scavenger cells for zinc, while copper and bulk circuits use rougher cells only. All ore types require regrinding prior to cleaning, followed by three stages of cleaning to achieve final concentrate grades.

Concentrates are thickened and filtered using dedicated thickeners and filter presses for each product type. Tailings from the talc pre-float and zinc flotation circuits are directed to a common paste backfill system, with thickener underflow sent to the tailings management facility. Process water is recycled from tailings thickening and the management facility, supplemented by fresh water from a lake for gland service and reagent preparation.

Reports

Website: https://www.eldoradogold.com/

Report Date: December 22, 2014

Region: 

Project Status: PEA (Pre-Feasibility Study)

Commodity: Copper, Zinc

Throughput: 5,000 tpd

Mine Life: 

Mine Type: 

Ore type:

McIlvenna Bay Copper-Zinc Flotation: 4,900 tpd Recovery

McIlvenna Bay Copper-Zinc Flotation: 4,900 tpd Recovery

Source: Eldorado Gold Corporation (2026)
Website: https://www.eldoradogold.com/assets/growth-projects/mcilvenna-bay-canada

Critical Data

Parameter Value Unit Notes
Throughput 4,900 tpd Nominal daily throughput; annual 1,788,500 tpa
Mill Power 7,000 kW Combined SAG mill (3,500 kW) and ball mill (3,500 kW)
Target Grind Size 75 μm Cyclone overflow P80 for flotation feed
Head Grade 1.27% Cu, 3.64% Zn, 0.56 g/t Au, 18.45 g/t Ag % / g/t Blended plant feed grades
Recovery % % Not specified in Section 17; test work referenced in Section 13
Processing Capacity 1,788,500 tpa Nominal annual throughput
Energy Consumption 14.7 (RWI), 16.5 (BWI) kWh/t Bond work indices for blended ore (62% CS / 38% MS)
Water Consumption m³/t Process water recycled; no specific consumption given
Operating Hours 24 hours/day Two 12-hour shifts, 365 days per year

Overview

Eldorado Gold Corporation operates the McIlvenna Bay Project, a proposed copper-zinc mine located in Saskatchewan, Canada. The project’s recovery methods are based on a conventional metallurgical flowsheet designed to treat 4,900 tonnes per day (1.789 million tonnes per annum) of ore from two primary mineralization zones: the CS Zone (copper sulphide stringer textures) and the MS Zone (higher zinc grades). The process plant, which is at an advanced design stage, incorporates a comminution circuit followed by sequential copper and zinc flotation to produce two saleable concentrates. A pyrite flotation circuit ensures tailings desulphurization, with non-sulphide tailings dewatered and filtered for paste backfill and surface stacking. This integrated approach maximizes metal recovery while minimizing environmental impact through water recycling and underground tailings storage. The plant’s significance lies in its ability to handle variable ore hardness—blending harder CS ore with softer MS ore—through a flexible grinding circuit that includes a SAG mill, pebble crusher, and ball mill. Copper and zinc rougher concentrates undergo regrinding in horizontal IsaMills to achieve fine particle sizes (P80 of 25 µm for copper, 20 µm for zinc) before multi-stage cleaning. Final concentrates are dewatered to 9% moisture using thickeners and pressure filters, ready for toll smelting. The recovery methods at McIlvenna Bay exemplify modern, environmentally responsible mineral processing tailored to complex polymetallic orebodies.

Key Process Stages

  • Stage 1: Primary Crushing and Ore Storage – Run-of-mine ore is crushed to 100% passing 245 mm (P80 125 mm) using a jaw crusher. Crushed material is conveyed to a 2,500-t capacity ore bin providing 12 hours of live storage. Metal detection and dust collection systems ensure feed quality and safety.
  • Stage 2: Grinding Circuit – A SAG mill (7.32 m diameter × 3.38 m EGL, 3,500 kW) in closed circuit with a pebble crusher and a ball mill (5.03 m × 7.85 m EGL, 3,500 kW) grinds ore to a cyclone overflow P80 of 75 µm. The SAG mill operates at 75% solids with 125 mm steel balls; the ball mill uses 50 mm balls at 31-35% charge. Circulating load is 300-350% of fresh feed.
  • Stage 3: Copper Flotation and Regrind – Cyclone overflow enters agitated conditioning tanks before reporting to four 50 m³ tank cells for copper rougher flotation. Rougher concentrate is reground in a 500 kW IsaMill (M1000) to P80 25 µm, then cleaned in three stages (six 11.4 m³ cells for first cleaner, two for second, two for third). Final copper concentrate is pumped to dewatering.
  • Stage 4: Zinc Flotation and Regrind – Copper flotation tailings feed the zinc circuit. After pH conditioning in two tanks, slurry passes through four 50 m³ rougher cells. Rougher concentrate is reground in two 500 kW IsaMills (M1000) to P80 20 µm, then cleaned in three stages (four 10 m³ first cleaner cells, three second, two third). Final zinc concentrate reports to dewatering.
  • Stage 5: Concentrate Dewatering and Pyrite Flotation – Copper and zinc concentrates are thickened (6 m and 7 m diameter thickeners) to 55% solids, then filtered to 9% moisture using dedicated pressure filters. Filter cake is loaded into trucks for transport. Zinc rougher tailings undergo pyrite flotation (Jameson cell plus three tank cells) to recover sulphides for paste backfill. Non-sulphide tailings are thickened, filtered (15% moisture), and stacked at the surface facility.

Additional Interesting Data and Summary

The McIlvenna Bay recovery plant incorporates detailed design criteria that ensure robust operation across variable ore types. The SAG mill (7.32 m × 3.38 m EGL) operates with a steel charge of 125 mm balls at 7.6-16% volume and total load of 25%, using a variable-speed drive for flexibility. The ball mill (5.03 m × 7.85 m EGL) is rubber-lined with a 300% circulating load. Regrind circuits use horizontal IsaMills (M1000, 500 kW each) to achieve ultra-fine grinds—P80 25 µm for copper and 20 µm for zinc. Flotation equipment includes tank cells: four 50 m³ copper roughers (75 kW each), six 11.4 m³ copper cleaners (22 kW), four 50 m³ zinc roughers (75 kW), and four 10 m³ zinc cleaners (22 kW). The pyrite circuit employs one Jameson cell followed by three conventional tank cells, with a mass pull of 34%. For dewatering, copper and zinc concentrates are thickened in 6 m and 7 m high-rate thickeners respectively, underflow at 55% solids, then filtered to 9% moisture via dedicated pressure filters. The paste plant handles 47% of mill feed (non-sulphide tailings), producing filter cake at 15% moisture for surface stacking. Environmental considerations are central: tailings desulphurization minimizes acid rock drainage, and paste backfill reduces surface footprint. Water is recycled from thickeners and filter filtrate, with makeup from filtered process water. Economic impact is significant—two saleable concentrates (copper and zinc) are produced for toll smelting, with surge capacities of 10.5 hours (copper) and 8.4 hours (zinc). Sustainability initiatives include low-energy IsaMills, closed water circuits, and dust collection systems. The project is in the feasibility/engineering stage, with a flowsheet that can blend ore types (62% CS, 38% MS) to maintain consistent feed grades. Future outlook includes potential optimization of regrind circuits and reagent dosages based on on-stream analyzer feedback (Cu, Zn, Fe). Overall, the recovery methods demonstrate a modern, integrated approach to polymetallic sulphide processing with strong environmental stewardship.


Key Processes: Flotation, Gravity Separation, SAG Mill, Ball Mill, Crushing

Target Commodities: Gold, Copper, Zinc

McIlvenna Bay Process Design Targets Conventional Copper-Zinc Flowsheet

Standfirst: The planned 4,900 tpd operation in east-central Saskatchewan will use SAG milling, sequential flotation, and paste backfill to produce separate copper and zinc concentrates for sale.

The McIlvenna Bay Project is a copper-zinc mine located in east-central Saskatchewan, approximately 375 km northeast of Saskatoon and 85 km west of Flin Flon, Manitoba. The site is accessible year-round via an 18 km all-weather road connected to Saskatchewan Provincial Highway 106. The 2025 Technical Report describes a proposed decline and shaft underground mining operation using long-hole mining methods for ore extraction at a nominal 4,900 tpd Phase 1 Operation. The project is owned by Eldorado Gold Corporation through its wholly owned subsidiary Foran Mining Corporation, which holds the claims through McIlvenna Bay Operating Ltd. As of April 14, 2026, Foran operates as a wholly owned subsidiary of Eldorado. Ore is expected to be processed using conventional single stage crushing with a SAG mill and ball mill design, followed by grinding and flotation circuits to produce both copper and zinc concentrates for transportation from site to Flin Flon for shipment by rail to Canadian smelters and/or offshore. There has been no mineral production on the McIlvenna Bay Project to date. The Technical Report's Phase 1 operation includes a 4,900 tpd underground mine, on-site crushing and mineral processing facilities, paste plant, filtered tailing storage facility, and supporting infrastructure such as water management and treatment facilities, offices, workshop, warehouse, mine dry, and first aid facilities.

Critical Data

Parameter Value Unit Notes
Nominal annual throughput 1,788,500 dmtpa Design value
Nominal daily throughput 4,900 dmtpd Design value
Operating hours per shift 12 h Design value
Operating shifts per day 2 # Design value
Operating days per week 7 d Design value
Operating days per annum 365 # Design value
Crushing circuit availability 60 % Design value
Grinding circuit availability 92 % Design value
ROM moisture 4 % Design value
Abrasion index (62% CS Zone / 38% MS) 0.256 g Design value
Rod mill work index (62% CS Zone / 38% MS) 14.7 kWh/t Bond, metric
Rod mill work index (CS Zone) 17 kWh/t Bond, metric
Rod mill work index (MS) 12.7 kWh/t Bond, metric
Ball mill work index (62% CS Zone / 38% MS) 16.5 kWh/t Bond, metric
Ball mill work index (CS Zone) 17.9 kWh/t Bond, metric
Ball mill work index (MS) 13.7 kWh/t Bond, metric
Plant feed blend of CS Zone ore, average 62 % Design value
Plant feed blend of MS ore, average 38 % Design value
Blended plant feed grade Cu 1.27 % Design value
Blended plant feed grade Pb 0.21 % Design value
Blended plant feed grade Zn 3.64 % Design value
Blended plant feed grade Au 0.56 g/t Design value
Blended plant feed grade Ag 18.45 g/t Design value
Blended plant feed grade S 13.75 % Design value
Crushing circuit feed F100 450 mm Design value
Crushing circuit product P100 245 mm Design value
Crushing circuit product P80 125 mm Design value
SAG mill feed F100 245 mm Design value
SAG mill feed F80 125 mm Design value
SAG mill discharge % solids 75 % Design value
SAG mill pebble extraction 30 % Design value
Transfer size 1653 µm Design value
Ball mill discharge % solids 73.6 % Design value
Ball mill circulating load 300 % Design value
Cyclone overflow product P80 75 µm Design value
Cu flotation conditioning time required 2 min Design value
Cu rougher residence time required 20 min Design value
Cu rougher mass pull 15 % Design value
Cu regrind mill product P80 25 µm Design value
Cu cleaner 1 residence time required 20 min Design value
Cu cleaner 2 residence time required 10 min Design value
Cu cleaner 3 residence time required 7.5 min Design value
Zn flotation first conditioning time required 6 min Design value
Zn rougher residence time required 15 min Design value
Zn rougher mass pull 25 % Design value
Zn regrind mill product P80 20 µm Design value
Zn cleaner 1 residence time required 12.5 min Design value
Zn cleaner 2 residence time required 10 min Design value
Zn cleaner 3 residence time required 8.8 min Design value
Py rougher mass pull (total Jameson plus rougher cells) 34 % Design value
Cu conc thickener U/F solids content 55 % Design value
Zn conc thickener U/F solids content 55 % Design value
Cu/Zn conc cake moisture 9 % Design value
Py conc thickener U/F solids content 60 % Design value
Py conc live storage 2 x 3182 m3 Design value
Py conc average cake moisture 18 % Design value
Paste plant availability 50 % Design value
Split of mill feed to paste, design 47 % Design value
Paste cement addition Not stated % Table value missing from source
Non-sulphide tailings live storage 2400 m3 Design value
Tailings thickener U/F solids content 55 % Design value
Tailings average cake moisture 15 % Design value
Average demand load, process plant 18.4 MW Design value
Nominal raw water requirements 42 m3/h Design value

Overview

The process plant design for the McIlvenna Bay Project is based on a conventional metallurgical flowsheet to treat copper-zinc ore. The flowsheet draws on metallurgical test work described in Section 13 of the report, industry standards, and conventional unit operations. The two most prevalent mineralization types feeding the mill will be CS and MS. The CS Zone consists mostly of copper sulphide minerals in stringer type textures with minor amounts of zinc, and the MS contains higher zinc grades with additional copper units. The CS Zone material is harder and contains less pyrite than the MS zone.

The plant consists of a comminution circuit followed by sequential copper and zinc flotation, with concentrate regrind and dewatering to produce both copper and zinc concentrates for sale. A pyrite flotation circuit will produce pyrite concentrate and tailings which will be dewatered and filtered for paste fill and tailings storage. The process plant spans several numbered areas, from Area 6100 (crushing) to Area 6800 (reagents).

The plant layout places equipment within one large mill building with a dedicated area for tailings filtration and paste production. The tailings thickeners and storage tanks will be located outdoors and partially clad to ensure effective operation in cold climates. A reagent storage area will be located along one side of the process plant building, with reagents stored and transferred to the reagent day tank and dosing area within the main building.

Key Process Stages

Run-of-mine ore will be hauled from underground or surface stockpiles to the primary crusher using a 50-t capacity haul truck or a front-end loader. The ROM stockpiles will be required to blend the various ore types to achieve targeted mill head grades. Ore dumped into a 50-t ROM bin will discharge onto a vibrating grizzly feeder. The vibrating grizzly oversize will feed a FJ 1000 primary jaw crusher, while the grizzly undersize bypasses the crusher and combines with the primary crusher product in the discharge chute before discharging onto the sacrificial conveyor. The sacrificial conveyor transfers the crushed ore onto a crushed ore overland conveyor that feeds the ore storage bin.

Crushed ore will be stored in a 12-hour, 2,500-t live capacity ore storage bin. The overland conveyor will be equipped with a metal detector to prevent tramp metal from entering the ore bin. Two variable-speed apron feeders draw down the ore bin in a controlled manner to feed the SAG mill feed conveyor, with two ore sliding gates available to isolate the ore feeding the apron feeders as required. A reclaim dust collector will draw from collection points around each apron feeder to mitigate dust buildup.

The grinding circuit includes a SAG mill in closed circuit with a pebble crusher and a ball mill, along with cyclone classification. Crushed ore sized at a P80 of 125 mm is conveyed from the ore bin to the mill building via the SAG mill feed conveyor, where the ore is combined with the pebble product and fed into the SAG mill. Process water maintains a 75% slurry density in the mill. The SAG mill is a 7.32 m diameter by 3.38 m EGL unit equipped with a 3,500 kW variable-speed drive. The steel charge consists of 125 mm balls at 7.6% to 16% of the chamber volume and a total load of steel and ore of 25%. Internal discharge grates use 25 mm slurry ports and 50 mm pebble ports. Slurry exits via a trommel screen with 8 mm by 25 mm slots. The trommel oversize is conveyed to feed a pebble crusher before being recycled back to the SAG mill feed conveyor, with an option to bypass the pebble crusher to an outdoor pebble bunker using a three-way divert chute. The trommel undersize reports to the mill discharge pump box together with the ball mill discharge.

The ball mill is a 5.03 m diameter by 7.85 m EGL unit equipped with a 3,500 kW variable-speed drive. The steel charge consists of 50 mm balls at 31% to 35% of the chamber volume. The ball mill is rubber-lined and fed with cyclone underflow, with the mill discharge reporting through a trommel screen with 10 mm by 30 mm slots before laundering to the mill discharge pump box. Slurry is diluted and pumped to a 7 by 400CVD10 hydrocyclone pack, with five operating and two stand-by units. The feed to the hydrocyclone has a densitometer, flowmeter, and pressure transmitter for monitoring and control of feed density, flow, and pressure. Hydrocyclone overflow gravitates to the trash screen prior to reporting to copper conditioning, while the coarser cyclone underflow gravitates to the ball mill retractable feed chute as ball mill feed. The design circulating load in the cyclone underflow varies based on ore hardness and is expected to be between 300% and 350% of primary mill feed tonnage. Grinding balls are added to the SAG and ball mills via a kibble bucket hoisted by overhead crane, with storage bunkers adjacent to the process building holding 125 mm balls for the SAG mill and 50 mm balls for the ball mill.

Copper flotation consists of separate rougher and cleaner flotation equipment with a regrind mill installed to process the rougher concentrate prior to cleaner flotation. Cyclone overflow gravitates from the trash screen through the copper feed sampler and into an agitated copper conditioning tank. The bank of copper rougher cells consists of four 50 m3, 75 kW tank cells, with flotation air supplied by blowers via a low-pressure manifold. Rougher concentrate flows by gravity to the regrind circuit, where it is pumped to two cyclones, one operating and one stand-by. The underflow reports to a 500 kW horizontal M1000 copper regrind mill which reduces the P80 of the low-grade copper rougher concentrate to 25 µm. First stage cleaner flotation is provided by six 11.4 m3, 22 kW tank cells with integrated concentrate launders. The second cleaner concentrate is collected from a bank of two 11.4 m3, 22 kW tank cells and pumped to the third copper cleaner circuit, where final stage copper cleaning is achieved via a bank of two 11.4 m3, 22 kW tank flotation cells. Copper final concentrate is collected prior to pumping to the copper concentrate dewatering circuit.

Zinc flotation is similar in design to the copper circuit and is fed with combined copper flotation tailings slurry. Tailings slurry is pumped from the copper circuit via a sample station into the first of two agitated conditioner tanks in series, with the first primarily for pH control and the second allowing reagent conditioning. The bank of zinc rougher cells consists of four 50 m3, 75 kW tank cells. The concentrate flows by gravity to the regrind circuit, where the zinc regrind cyclone feed pump pumps the slurry to three cyclones, two operating and one stand-by. Each mill feed pump box feeds a corresponding 500 kW horizontal M1000 regrind mill, with the discharge of both mills combined with the zinc cyclone overflow before reporting to the zinc cleaner circuit. The zinc regrind circuit reduces the P80 of the zinc rougher concentrate to 20 µm. First stage cleaner flotation uses four 10 m3, 22 kW tank cells with integrated concentrate launders. The second cleaner concentrate is collected from a bank of three 10 m3, 22 kW tank cells and pumped to the third zinc cleaner circuit, where final stage zinc cleaning is achieved via a bank of two 10 m3, 22 kW tank flotation cells. Zinc final concentrate is collected prior to pumping to the zinc concentrate dewatering section. The zinc first cleaner tails bypass the pyrite circuit and report directly to the pyrite rougher concentrate pump box.

Copper flotation concentrate is pumped through a sampler before entering a 6 m diameter high-rate concentrate thickener for controlled dewatering, while zinc flotation concentrate enters a 7 m diameter concentrate thickener. Both thickeners are equipped with rake lift, bed level detection, and bed mass monitoring. Thickener underflow is withdrawn at 55% solids concentration by peristaltic pumps and sent to agitated concentrate storage tanks, with the copper storage tank surge capacity approximately 10.5 hours and the zinc thickener concentrate storage tank surge capacity approximately 8.4 hours. Concentrate stored in the tanks is pumped to dedicated pressure filters, with filtrate directed to corresponding filtrate de-aeration chambers and filtrate tanks before being pumped back to the appropriate concentrate thickener for recycling. A dedicated cloth and core wash tank services both filter presses to allow high pressure washing of the filter cloth at the end of each cycle. Filter cake discharges from each press to the corresponding concentrate load out bay below, with a wall separating the two concentrates to prevent cross-contamination. A front-end loader loads concentrate into side-tipping trucks for transportation off-site, with trucks weighed and auger-sampled at the weighbridge prior to dispatch.

Zinc rougher tailings slurry is pumped to the pyrite rougher flotation circuit for tailings desulphurization. The pyrite flotation step ensures that the dry stack tailings facility contains material with no more than 0.5% sulphur, on average. A non-selective bulk sulphide collector reagent SIPX is added to encourage flotation of the remaining sulphide minerals. The zinc rougher tails are pumped to the pyrite cell 1 feed box, a Jameson cell, where the tails are combined with a recirculated fraction of the tails stream. The feed is pumped through cavitation downcomers in the cell, with air aspirated through intakes located in the downcomers and cavitated with the pumped slurry. Wash water is added to the top of the froth to clean the froth as required. The tails flow by gravity to a bank of conventional pyrite rougher cells consisting of three 50 m3, 75 kW tank cells. The sulphide concentrate produced is combined with the zinc first cleaner tailings, dewatered, and directed to the paste backfill circuit for incorporation into the backfill mixture and safe storage underground.

Tailings slurry from the final cell in the bank of pyrite roughers reports to a 16 m diameter tailings thickener for dewatering and dry stack tails production. Thickener overflow gravitates to the combined tails thickener overflow pump box, where it is pumped through in-line filters prior to reporting to the process water tank for re-use within the process. Thickener underflow slurry is pumped from the thickener cone at 55% w/w solids concentration to a non-sulphide tailings surge tank located outside. This tank is agitated and holds approximately 18.5 hours of thickened tailings production. Thickened slurry from the surge tank is pumped to pressure filters for further dewatering, with filter cake discharged via conveyors into a filtered tailings bin. The tailings bin discharges the filtered tailings into trucks for placement on the nearby dry-stack tailings storage facility. The non-sulphide filtrate gravitates to a combined filtrate tank, from which it is pumped back to the pyrite concentrate thickener as feed dilution water.

Pyrite concentrate thickener underflow slurry is pumped from the thickener cone at 60% w/w solids concentration to two pyrite concentrate storage tanks located outside. These tanks are agitated and can hold approximately 72 hours of thickened pyrite concentrate to allow for time when paste backfill cannot be received underground. Pyrite concentrate slurry from the storage tanks is pumped to pressure filters for further dewatering, with filter cake discharged via a collector conveyor and incline conveyor into the paste plant. Dewatered pyrite filter cake enters a conditioning mixer with trim water to prepare the filter cake. The filter cake mixture is gravity-fed into a continuous mixer where it is mixed with binder to create cemented paste backfill. The paste is gravity-fed through the paste hopper to the paste pumps in a duty and future configuration. Binder delivery trucks add binder to the binder storage silo, which is equipped with a dust collector and rotary feeder that loads the binder onto a weigh belt feeder followed by a screw conveyor.

Plant services include plant and instrument air provided by four compressors. Three main compressors, two duty and one standby, feed a main distribution header. Two large plant air receivers fed from the main header act as buffer capacity due to large air requirements for the tailings filter presses. Concentrate filters are fed directly from the main header as no buffer capacity is required. Instrument air is provided from the main header after pressure regulation and fed through an instrument air dryer. A fourth smaller air compressor provides instrument air needed in a power outage to maintain control of instruments. Air compressors, including mine units, are cooled through a dedicated glycol-based heat recovery system, with recovered heat feeding the main HVAC system during winter. Low-pressure flotation air is supplied by two sets of blowers, three for the rougher flotation cells with two operating and one standby, and two for the cleaner flotation cells with one operating and one standby.

Water conservation measures will be implemented at the processing facility. Process water will be collected and reused within the process plant. The sole source of treated or raw water will be provided from the mine water treatment plant, which compensates for water losses in tailings and concentrate moisture. Water is recovered from the concentrate thickeners into copper and zinc spray water tanks, from which the water is filtered using automated inline filters and pumped to the respective flotation circuits as spray water. Process water is also recycled from the tailings and pyrite concentrate thickeners, with the overflow from both thickeners combined, filtered using an automated inline filter, and pumped to insulated process water storage tanks located outside, immediately adjacent to the process plant building. Potable water will be trucked to site and discharged into a fresh water tank, which supplies water to the mill offices and the tepid water tank. Raw water needs for the process plant from the MWTP feed the reagent and gland seal water tank, making up water losses in the process due to moisture in the concentrate and tailings while providing treated water adequate for reagent mixing and gland seal water. The water is pumped through a 25 µm inline filter and distributed to four piping branches: a reagent header for intermittent reagent mixing, gland seal water to the plant slurry pumps, gland seal high-pressure booster pumps for distribution to the paste plant slurry pumps, and excess water feeding into the process water tank to ensure circuit stability.

Metallurgical accounting will be carried out each shift and summarized daily, with an inventory check and reconciliation at the end of each month. Equipment includes weightometers on the crusher ore overland conveyor, SAG feed conveyor, and pebble transfer conveyor, with a calibration chain and hoist installed for routine calibration checks. Density and flow meters on the copper, zinc, pyrite, and tailings thickener underflow lines provide instantaneous mass flow and totalized tonnes. A Metso C6X SL Online Assay Analyzer located in the flotation area measures elemental concentrations in 12 process slurry streams, with the analyzer probe equipped with multiple channels to measure iron, copper, zinc, and density. Manual sampling equipment is installed for concentrate sampling when loading each copper or zinc concentrate truck, with a load-out scale installed to weigh the concentrate trucks before and after leaving the site.

Reagents delivered to site by road are stored in the warehouse and moved to the plant reagents area on an as-needed basis. Reagent dosing pump flow is adjusted remotely from the control room or operator desk, with the operator adjusting reagents based on flotation performance feedback from the online analyzer. Liquid AERO 5100 promoter is delivered in 1,100 kg IBC totes and metered by peristaltic hose pumps to the zinc flotation circuit, with approximately 35.8 t consumed per year. Liquid AERO 3894 collector is delivered in 1,000 kg IBC totes and metered to the copper flotation circuit, with approximately 44.7 t consumed per year. Liquid AERO 3501 collector is delivered in 1,100 kg IBC totes and metered to the copper flotation circuit, with approximately 17.9 t consumed per year. Liquid MIBC frother is delivered in 900 kg IBC totes and metered from a single IBC tote to several addition points throughout the plant, with approximately 165 t consumed per year. Sodium metabisulphite powder is delivered in 1,250 kg supersacks and mixed with water to create a depressant solution, with approximately 625 t consumed per year. Zinc sulphate powder is delivered in 1,000 kg supersacks and mixed with water to create a depressant solution, with approximately 357 t consumed per year. SIPX briquettes are delivered in 750 kg supersacks and mixed with water to create a collector solution, with approximately 80.5 t consumed per year. Copper sulphate powder is delivered in 1,250 kg supersacks and mixed with water to create an activator solution, with approximately 849 t consumed per year. Quicklime powder is delivered in bulk tankers and stored in a lime silo, with a vendor-package lime slaking plant mixing the quicklime with water on an as-needed basis and transferring the slaked lime solution to an agitated storage and dosing tank within the plant building. Approximately 4,241 t of quicklime will be consumed per year. Silicate gangue depressant PE26, a carboxy methyl cellulose based product, is delivered in 25 kg bags and mixed to create a 0.5% depressant solution, with approximately 59 t consumed per year. Flocculant Magnafloc 10 powder is delivered in 25 kg supersacks and mixed to create flocculant, with approximately 41.5 t consumed per year.

Additional Interesting Data and Summary

The average demand load for the process plant will be 18.4 MW. Nominal raw water requirements for the process plant will be 42 m3/h. Reagent consumption rates are expressed in grams per tonne of feed, with AERO 5100 at 20 g/t, AERO 3894 at 25 g/t, AERO 3501 at 10 g/t, MIBC at 93 g/t, sodium metabisulphite at 350 g/t, zinc sulphate at 200 g/t, SIPX at 45 g/t, copper sulphate at 475 g/t, quicklime at 2,229 g/t, and CMC at 33 g/t. Flocculant consumption varies by thickener, with 30 g/t thickener feed for the copper thickener, 30 g/t for the zinc thickener, 25 g/t for the pyrite thickener, and 20 g/t for the tailings thickener. Grinding media consumption includes forged steel SAG mill grinding media at 0.53 kg/t feed, forged steel ball mill grinding media at 0.66 kg/t feed, and ceramic regrind mill grinding media at 8 g/kWh for both the copper and zinc regrind mills.

Key Processes

  • Primary crushing with a jaw crusher to achieve a product P80 of 125 mm.
  • Ore storage in a 12-hour, 2,500-t live capacity bin with apron feeder reclaim.
  • SAG mill in closed circuit with a pebble crusher and a ball mill, with cyclone classification.
  • Sequential copper and zinc flotation circuits, each with rougher flotation, regrind, and multi-stage cleaning.
  • Copper and zinc concentrate dewatering via dedicated thickeners and pressure filters to produce filter cake at 9% moisture.
  • Pyrite flotation using a Jameson cell and three conventional tank cells for tailings desulphurization.
  • Tailings dewatering via thickener and pressure filtration for dry stack tailings and paste backfill production.
  • Reagent delivery and dosing systems covering promoters, collectors, frothers, depressants, activators, pH modifiers, and flocculants.

Source: Technical Report on the McIlvenna Bay Project, Saskatchewan, Canada, June 8, 2026. Project website: McIlvenna Bay Project

Mineral processing basics

Scroll to Top