Nalunaq — 2022 NI 43-101 Technical Report

Company Nalunaq A/S
Date 2022
Region Greenland
Commodities Gold

Executive Summary

SRK Consulting prepared this NI 43-101 Technical Report for Nalunaq A/S in October 2022. The report outlines recovery methods commissioned from Halyard Inc to investigate future processing and recovery requirements. The plant has not been commissioned, and a detailed report is not available, so the information is summarized for information purposes.

Amaroq currently plans mined material would be fed to the processing facility at a base rate of 104,025 t per year at a nominal feed rate of 300 t per day for 365 days in the year. The processing facility will consist of crushing, grinding, gravity recovery, flotation, thickening, tailings filtering, and a gravity concentrate smelting facility.

The current flowsheet is developed around the high propensity of the gold at Nalunaq to be recovered in a gravity concentration circuit, calculated to be in the order of 65-75%. An additional 20-25% of the gold in the remaining slurry will be recovered by the flotation circuit downstream of the gravity concentration circuit.

Reports

  • entities/Nalunaq_Mine

Website: https://www.amaroqminerals.com/projects/nalunaq/

Report Date: 2022

Region: Greenland

Project Status:

Commodity: Gold

Throughput: 

Mine Life: 

Mine Type: 

Ore type: 

Mineral processing basics

Scroll to Top