RPMGlobal's June 2024 mineral resource report for Silvercorp's Baiyunpu gold-lead-zinc project in Hunan found the old plant unmaintained after ten years idle; the company plans a larger plant using the same crushing and dual-circuit flotation route.
The National Instrument 43-101 Mineral Resource Technical Report on the Baiyunpu (BYP) Gold-Lead-Zinc Project, Hunan Province, China, was prepared by RPMGlobal Asia Limited for Silvercorp Metals Inc. with an effective date of June 30, 2024. It is a resource report, and it states that the company had not prepared a mineral reserve estimate. Its recovery methods section describes the plant that ran until operations stopped in 2014 and the company's stated restart plan.
Critical Data
| Parameter | Value | Unit | Notes |
|---|---|---|---|
| Report effective date | June 30, 2024 | Not applicable | RPMGlobal Asia Limited for Silvercorp Metals Inc. |
| Existing plant capacity | 500 | t/d | Idle about 10 years |
| Planned plant capacity | 1,500 | t/d | Same flowsheet, as stated by the company |
| Crushing | Two stages | Not applicable | Followed by classification |
| Flotation | Separate lead and zinc circuits | Not applicable | Gold ore used the lead circuit only |
| Operations ceased | 2014 | Not applicable | Waste facilities unused since July 2014 |
| Tailings storage facility | 245,000 m³, 24 m wall | Not applicable | About 333,000 t at 1.36 t/m³ |
| Water recycled, when operating | 75 to 85 | % | From the reclaim pond |
| Power supply | 10 kV line | Not applicable | From Baiyunpu town grid, 7 km away |
Overview
The 500 t/d plant on site treated two types of mineralization, lead-zinc sulphide and gold, separately in batches. It had a two-stage crushing circuit, classification and two flotation circuits. Lead-zinc material used both circuits to produce lead and zinc concentrates, while gold material used only the lead circuit to produce a gold-bearing pyrite concentrate.
During its 2024 site visit, RPM found that the plant needs replacement because it had been idle for about ten years without proper maintenance. Silvercorp told RPM it intends to dismantle the 500 t/d plant and replace it with a 1,500 t/d plant following the same flowsheet. RPM states that it was given no information, studies or plans for future operations, so none are presented in the report.
Key Process Stages
Crushing and classification. Two crushing stages prepared the feed for classification ahead of flotation.
Lead and zinc flotation. For lead-zinc sulphide material, sequential use of the lead and zinc circuits produced separate lead and zinc concentrates.
Gold flotation. Gold material was processed through the lead flotation circuit alone to make a gold-bearing pyrite concentrate.
Tailings and backfill. Tailings went to a valley-fill tailings storage facility about 1 km southwest of the plant, commissioned in August 2011, and a paste backfill plant served the mine.
Additional Interesting Data and Summary
The tailings dam has a masonry wall with a concrete layer, embedded 50 cm into bedrock. Seepage is controlled with geomembrane and geotextile layers, intercepting drains and a downstream pond. Supernatant is removed by a concrete decant structure, and a reclaim pond below the dam allows zero discharge in dry seasons. In operation, 75 to 85% of the water was recycled to the mill. RPM found the facility and its seepage monitoring under limited maintenance, with remote monitoring in place.
In summary, Baiyunpu's 2024 report records a small batch-run flotation plant that has stood idle since 2014, and Silvercorp's stated intention, not yet supported by a study, to replace it with a 1,500 t/d plant on the same crushing and dual-circuit flotation flowsheet.
Key Processes
- Two-stage crushing and classification
- Lead flotation circuit
- Zinc flotation circuit
- Gold-bearing pyrite concentrate from the lead circuit
- Valley-fill tailings storage and paste backfill
Source: National Instrument 43-101 Mineral Resource Technical Report, Baiyunpu Gold-Lead-Zinc Project, Hunan Province, China, RPMGlobal Asia Limited for Silvercorp Metals Inc., effective date June 30, 2024.
Earlier report summaries
Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.
National Instrument 43-101 Mineral Resource Technical Report — Baiyunpu Project
This report documents the historical 500 tpd processing facility, its metallurgical performance during 2011 operations, and the proposed replacement with a 1,500 tpd plant following an identical flowsheet.
Report context
This National Instrument 43-101 Mineral Resource Technical Report for the Baiyunpu Project is dated 30th April 2019. At the time of report writing, Silvercorp had not prepared an estimate of mineral reserves. The existing 500 tpd processing facility on site had been idle for more than 4 years and was in need of repair or replacement. The Company intended to dismantle the 500 tpd plant and replace it with a 1,500 tpd processing plant that follows the same process flowsheet. The plant was used to process both lead-zinc sulphide and gold mineralized material, treated separately in campaigns. Lead-zinc flotation used both flotation circuits to produce lead and zinc concentrates, whereas gold flotation used only the lead flotation circuit to produce a gold-bearing pyrite concentrate.
Processing route
Historical 500 tpd Plant
The historical plant consisted of a two-stage crushing circuit followed by classification and dual flotation circuits (lead and zinc). Crushing comprised a jaw crusher (Model PE 400×600) with a closed side setting of 90 mm, followed by a cone crusher (Model PYD 1200) with a closed side setting of 25 mm, in closed circuit with a 25 mm aperture vibrating screen (Model YA1536). Discharge from the screen fed ore bins with a live capacity of 100 tons. Dust from crushing and screening was collected in a bag house and transferred as slurry to a pre-flotation tank.
The milling circuit was a closed circuit consisting of two grate ball mills (Model MQCG 1500 x 4000 mm) and two spiral classifiers (Model FG-15). The ball charge was made of Mn-steel balls with diameters ranging from 60 mm to 120 mm. The target grind size was 70% passing 200 mesh (74 micron). Overflow density was maintained at 40% solids by weight for feeding to conditioning tanks for lead flotation.
Flotation comprised a lead circuit and a zinc circuit. The lead flotation bank consisted of one stage of roughing, two stages of scavenging, and three stages of cleaning. Lead scavenger tails flowed to zinc flotation, which consisted of one stage of roughing, two stages of scavenging, and four stages of cleaning.
Both lead and zinc concentrates were discharged to six settling bays for dewatering by evaporation. Moisture averaged 14-16% in final concentrate products.
Proposed 1,500 tpd Plant
The Company intends to dismantle the 500 tpd plant and replace it with a 1,500 tpd plant that follows the same process flowsheet. The same reagents will be used for the planned 1,500 tpd processing plant. Tailings will be pumped to a surface plant constructed for paste backfill, with half used for underground backfill and the remainder dewatered and sold to third party cement plants.
Process Control
There was no centralized automation station or control room for entire plant process monitoring or control. Ore feed to ball mill was controlled via an electronic scale, and water addition was controlled via slurry density and experience. Pulp density of mill spiral classifiers was monitored and adjusted to maintain between 28% and 35% solids. Chemical dosages were controlled via a localized PLC system for each set of equipment, adjusted in a narrow range based on assay feedback every half hour. Automatic sampling of key metallurgical accounting streams was conducted. A central control room in the grinding-flotation building allowed TV imaging of key production flow points. Samples were taken every 0.5 hour for quality control, mass balance, and recovery calculation.
Ancillary Facilities
The on-site laboratory was equipped with sample preparation, wet chemistry, basic photometric analytical equipment, and metallurgical testing equipment for crushing, grinding, flotation, gravity separation, and fire assay. The laboratory processed up to 100 samples per day and conducted routine analysis of ores and concentrates, water quality, and environmental testing. Silvercorp’s QA/QC procedures included inserting standards in sample batches and submitting duplicate pulps to an independent external laboratory on an intermittent basis. The on-site laboratory had been idle for more than 4 years, and most measuring instruments needed repair or replacement.
During historical production, daily maintenance was serviced through section-specific workshops equipped with cranes, welding capability, and basic machine-shop facilities. Current maintenance workshops needed to be restored before providing basic maintenance services.
Key Inputs
Mill power (10 kV power line) was drawn from the town of Baiyunpu, Hunan Province power authority grid, 7 km from the mine. Another power source (30 kV power line) was planned from the town of Jukoupu, 1.74 km away. To meet 1,500 tpd mining capacity, one 1000 KVA transformer would be used for underground operation, one 630 KVA transformer for fill station, and two 500 KVA transformers for the processing plant.
Net fresh water usage was approximately 1 cubic metre per tonne of ore. Recycled water from the tailings dam helped maintain a zero-discharge water balance for most of the year, with wet season discharges via a water treatment facility.
Reagents used included depressants/modifiers (sodium sulfide, zinc sulfate, sodium sulphite, copper sulfate), collectors (di-ethyl dithiocarbamate, ammonium dibutyl dithiophosphate, butyl xanthate), and frother (MIBC). Reagent storage and mixing was located adjacent to the grinding/flotation plant.
Key reported parameters
| Parameter | Value | Unit | Basis |
|---|---|---|---|
| Historical plant throughput | 500 | tpd | Design/actual |
| Proposed plant throughput | 1,500 | tpd | Proposed design |
| Feed grade (Pb) | 0.5 | % | Historical testwork (2011) |
| Feed grade (Zn) | 2.5 | % | Historical testwork (2011) |
| Feed grade (Au) | 3.6 | g/t | Historical testwork (2011) |
| Lead concentrate grade | 50 | % Pb | Historical testwork (2011) |
| Zinc concentrate grade | 45 | % Zn | Historical testwork (2011) |
| Gold-bearing pyrite concentrate grade | 40 | g/t Au | Historical testwork (2011) |
| Lead recovery | 82 | % | Historical testwork (2011) |
| Zinc recovery | 90 | % | Historical testwork (2011) |
| Gold recovery | 90 | % | Historical testwork (2011) |
| Target grind size | 70% passing 200 mesh (74 micron) | , | Design |
| Crusher closed side setting (primary) | 90 | mm | Design |
| Crusher closed side setting (secondary) | 25 | mm | Design |
| Screen aperture | 25 | mm | Design |
| Ore bin live capacity | 100 | tons | Design |
| Mill overflow density | 40 | % solids | Design |
| Spiral classifier pulp density range | 28-35 | % solids | Design |
| Concentrate moisture | 14-16 | % | Historical testwork |
| Net fresh water usage | 1 | cu. m/t ore | Design |
| Lead flotation stages | 1 rougher, 2 scavenger, 3 cleaner | , | Design |
| Zinc flotation stages | 1 rougher, 2 scavenger, 4 cleaner | , | Design |
| Laboratory throughput | 100 | samples/day | Design |
| Sampling frequency | Every 0.5 hour | , | Design |
| Assay frequency | Every 0.5 hour | , | Design |
| Power supply (existing) | 10 kV from Baiyunpu grid | , | Facility |
| Power supply (planned) | 30 kV from Jukoupu grid | , | Planned |
| Transformer capacity (underground) | 1,000 | KVA | Planned |
| Transformer capacity (fill station) | 630 | KVA | Planned |
| Transformer capacity (processing plant, each) | 500 | KVA | Planned |
Project website: https://silvercorpmetals.com/silvercorp-reports-an-updated-ni-43-101-resource-estimate-for-the-byp-gold-lead-zinc-property-in-hunan-province-china/
Technical qualifications
- At the time of report writing, Silvercorp had not prepared an estimate of mineral reserves.
- The word “ore” was used in a generic sense and does not imply that mineral reserves had been estimated.
- The historical metallurgical data (Table 17-1) represents production data from 2011; feed tonnage of 420 tpd (strikethrough in original) and certain concentrate values were presented with strikethrough formatting in the original table.
- The existing 500 tpd processing facility had been idle for more than 4 years and was in need of repair or replacement.
- The on-site laboratory had been idle for more than 4 years, with most measuring instruments needing repair or replacement.
- The existing 500 tpd plant was to be dismantled and replaced, not upgraded or expanded.
- No centralized automation station or control room existed for entire plant process monitoring or control; the planned level of process control and automation was described as basic but adequate.
- Current maintenance workshops needed to be restored before providing basic maintenance services.
*Source: National Instrument 43-101 Mineral Resource Technical Report , Baiyunpu Project, 30th April 2019, Section 17 Recovery Methods.*

