NI 43-101 Technical Report for the Kurmuk Gold Project, Ethiopia

The Kurmuk Gold Project proposes a conventional carbon-in-leach processing plant designed to treat 5 Mt/a of oxide ore and 4 Mt/a of fresh ore.

Report context

This report, dated 09 June 2023, presents the NI 43-101 Technical Report for the Kurmuk Gold Project in Ethiopia, prepared for Allied Gold Corp and Mondavi Ventures Ltd (to be renamed Allied Gold Corporation). The processing plant design was developed by Lycopodium using metallurgical testwork managed by Allied and Lycopodium. The proposed design is based on a robust metallurgical flowsheet using well-proven equipment, with equipment selection driven by suitability for duty, expected mine life, process performance, reliability, and ease of maintenance.

Processing route

Primary crushing and grinding

Ore is processed through primary crushing followed by crushed ore storage and reclaim. The grinding circuit uses a SAG/Ball Mill (SAB) combination with cyclone classification. An assessment by Orway Mineral Consultants indicated that a throughput of up to 5 Mt/a could be processed through the SAG/Ball circuit for oxide ores and 4 Mt/a for Ashashire fresh ores, with 7.5 MW drives on both mills. The milling rate ranges from 3.74 Mt/a for Ashashire pelite fresh to 5.26 Mt/a for Dish Mountain oxide ore. The target grind size is P80 75 µm.

Gravity concentration and cyanidation

The flowsheet includes gravity concentration with intensive cyanide leaching of concentrate and electrowinning. The leaching circuit comprises one leach reactor of 5,000 m³ and six CIL leaching tanks, each of 5,000 m³. Treating oxide ore at 5 Mt/a will result in reduced residence time in the CIL circuit, from 37 hours to 25 hours. The process plant includes an elution circuit with 14-tonne capacity, electrowinning, and gold smelting to produce gold doré.

Cyanide recovery and tailings management

Plant tailings are thickened for cyanide recovery using a 32 m diameter high-rate thickener, detoxified, and again thickened using a 32 m diameter high-rate thickener as a water conservation measure prior to disposal to a lined tailings storage facility located downstream of the process plant. The cyanide recovery thickener may be delayed as it is expected that the cyanide detoxification circuit will not need to be regularly operated to meet CN WAD 50 ppm in the decant pond.

Ancillary systems

An oxygen plant of 10 t/d capacity is included, along with air supply services. Reagent mixing, storage and distribution systems are provided, together with process, raw and potable water distribution. Duty-standby pumps have been included, including cyclone feed and tailings pumps.

Gold lock-up and inventory

Kurmuk has a high gravity gold content in the ores, leading to increased lock-up in the milling plant. With the gravity recovery circuit in place, total gold inventory is reduced to the equivalent of between 6 days and 10 days of production, varying depending upon head grade and carbon management. Lycopodium provided an estimate of gold inventory of 3,700 oz for inclusion into the financial model, representing six days of delayed production at 250 koz/a. This inventory is removed from the first production period and recovered at the end of the mine life.

Gold plant security

The gold plant, located close to an international border, will have three levels of security with appropriate fencing. A perimeter fence with gate house regulates entry to the administration building and plant warehouse. A double fence separated by about 10 m surrounds high security areas including crushing, milling, and leach circuits with the elution plant and associated facilities, with a clean-dirty change house for all workers entering the process plant area. The high-risk gold room is separately secured with additional access control, clean-dirty change house, motion sensors, closed-circuit television with monitoring, and security personnel.

Analytical laboratory

A proposal from an internationally recognized contractor for equipping the laboratory includes fire assay, wet chem, metallurgical laboratory, sample preparation and storage with an AAS room and a bullion room plus ablutions, lunchroom and offices. Approximately 8,000 mining and grade control samples will be analyzed per month, with 421 solids, 518 solutions and 113 carbon samples from the plant and 104 environmental samples. The equipping cost of $1.4 million has been incorporated into the capital schedule, with the building cost making a total of $2.7 million. The operating cost is estimated at $1.64 million per annum, based upon a budgetary proposal, with contractor staffing of 22 persons. The cost per sample is $14.23 each, incorporating 66% fixed charges. The laboratory building is to be supplied free by Allied to the contractor, while the facility will be equipped and operated by the contractor.

Product quality

The doré to be produced at Kurmuk is likely to contain between 90% and 95% gold with silver plus minor quantities of base metals. It is assumed that the doré will be shipped to Rand Refinery in South Africa, but this decision may be reviewed during future studies or project execution.

Key reported parameters

Parameter Value Basis
Throughput
Oxide ore 5 Mt/a Design
Fresh ore 4 Mt/a Design
Head grade (overall project) 1.53 g/t Au Design
Gold recovery (overall project) 92.0% Design
Dish Mountain recovery 93.9% Design
Ashashire recovery 90.3% Design
Oxide/transition recovery (Ashashire) 95.0% Design
Grind size P80 75 µm Target
CIL residence time
Design 37 hours Design
At 5 Mt/a oxide 25 hours Calculated
Gold production (peak) ~250,000 oz/a Design
Gold production (average) 200,000 oz/a Design
Gold inventory (lock-up) 3,700 oz Estimate by Lycopodium
Power demand
Average 21.4 MW Design
Maximum 28.9 MW Design
Water demand
Fresh ore treatment 1.71 Mm³/a Design
Oxide ore treatment (peak) 2.87 Mm³/a Design
Dust suppression 40 m³/h Design
Leach reactor volume 1 x 5,000 m³ Design
CIL tank volume 6 x 5,000 m³ Design
Elution capacity 14 tonnes Design
Oxygen plant 10 t/d Design
Thickener diameter (cyanide recovery) 32 m Design
Thickener diameter (tailings) 32 m Design
Mill drives 7.5 MW each Design
Milling rate range 3.74–5.26 Mt/a Testwork by Orway Mineral Consultants
Cyanide detoxification target CN WAD 50 ppm Design criterion
Gold doré grade 90%–95% gold Expected

Project website: https://alliedgold.com/our-portfolio/kurmuk-project/default.aspx

Technical qualifications

The process plant design is based on a proposed flowsheet using metallurgical testwork, with adequately detailed process flow diagrams, process design criteria and operational philosophy documentation prepared in support of the design. The cyanide recovery thickener may be delayed as it is expected that the cyanide detoxification circuit will not need to be regularly operated to meet CN WAD 50 ppm in the decant pond. Treating oxide ore at 5 Mt/a will result in reduced residence time in the CIL circuit, from 37 hours to 25 hours. The gold inventory estimate of 3,700 oz was provided by Lycopodium for inclusion into the financial model, representing six days of delayed production at 250 koz/a. The analytical laboratory proposal and cost estimates are based on budgetary proposals from an internationally recognized contractor. The power demand is estimated at an average of 21.4 MW with a maximum of 28.9 MW. Water demand estimates range from 1.71 Mm³/a for fresh ore to 2.87 Mm³/a for oxide ore treatment. Consumable consumption rates are based on metallurgical testwork and presented by ore type.

Source: NI 43-101 Technical Report for the Kurmuk Gold Project, Ethiopia, 09 June 2023, Sections 17, 17.1, 17.2, 17.3, 17.4, 17.5, 17.6.