Executive Summary

This technical report details the processing methods and operational performance of the Palito Mining Complex in Pará State, Brazil, operated by Serabi. The facility processes ore from both the Palito and São Chico mines with a plant capacity of 500 tonnes per day. The flowsheet is designed to handle complex ore types, utilizing a combination of crushing, grinding, copper flotation, and carbon-in-pulp (CIP) cyanidation to recover gold and silver values.

Key operational highlights include the integration of an ore sorting circuit to upgrade low-grade Palito ore prior to grinding, enhancing overall recovery efficiency. The São Chico ore is processed through a separate grinding circuit featuring gravity concentration and intensive cyanide leaching. The combined tailings from these circuits undergo CIP cyanidation, with gold and silver adsorbed onto activated carbon before elution and electrowinning to produce a final doré product.

The report provides comprehensive data on equipment specifications, consumable requirements, and operating performance from 2017 to 2022. Gold recovery rates have remained consistent, averaging around 92% for milled ore, with the ore sorter demonstrating significant value in upgrading low-grade material. The facility employs robust cyanide detoxification processes to ensure environmental compliance before tailings disposal.

Processing Overview

  • Crushing: Jaw Crusher (Metso 6240E), Cone Crushers (Faço, Sandvik)
  • Ore Sorting: XRT/Optical (Comex CXR-1000)
  • Grinding: Ball Mills (Humboldt Wedag, Zanini), Hydrocyclones (Weir Cavex)
  • Flotation: Emprotec Dual Cells (Rougher, Scavenger, Cleaner)
  • Leaching: CIP (Carbon-in-Pulp), Intensive Leach (Gekko ILR150)
  • Elution: Zadra Process
  • Detoxification: INCO Air/SO2 Process

Reports

Website: https://www.serabigold.com/operations/palito-complex/

Report Date: 2025

Region: Pará State, Brazil

Project Status: Operating

Commodity: Gold, Silver, Copper

Throughput: 500 t/d

Mine Life: 

Mine Type: 

Ore type: 

Scroll to Top