Executive Summary
This technical report covers the Remedios Project located in the Municipality of Remedios, Antioquia, Colombia. Authored by James A. McCrea, P.Geo., the report was issued on July 9, 2014. It outlines the current status of the project’s mineral processing facilities, specifically focusing on the San Pablo Mill.
The San Pablo Mill is a 100 tonne per day mineral processing facility currently on care and maintenance for a number of years. During a site visit in December, an engineer reviewed the mill and reported it to be in good operational condition. However, as of the report date, no operational test of the mill has been completed.
The report references a mill flow sheet (Figure 17.1) from Minatura, 2011, which details the processing circuit. While the facility is in good condition, its operational status remains inactive pending further testing or commissioning.
Website: https://ca.finance.yahoo.com/news/wolverine-minerals-acquire-interest-colombia-223000626.html
Report Date: 2014-07-09
Region: Municipality of Remedios, Antioquia, Colombia
Project Status: Care and Maintenance
Commodity: Not Specified
Throughput: 100 tpd
Mine Life:
Mine Type: