Yerington Copper Project — 2023 Technical Report

Figure 17-1: Yerington MacArthur Summary Process Flowsheet

This technical report describes the proposed processing route for the Yerington Copper Project, comprising two sites that will produce LME Grade A copper cathode through heap leaching, solvent extraction, and electrowinning.

Report context

The Yerington Copper Project consists of two sites: the MacArthur Site and the Yerington Site. The MacArthur Site, located 5.1 miles northwest of the main Yerington Site, will have three pits providing ore to its heap leach pad and solvent extraction facility. The Yerington Site will have the Yerington Pit providing sulfide ore to its crushing and agglomeration circuit and the heap leach pad. The rich electrolyte from both sites will be combined to feed into the electrowinning circuit to produce LME Grade A copper cathode. This report is dated as a 2023 NI 43-101 technical report for the prefeasibility study.

Processing route

MacArthur Site – Heap Leaching

The MacArthur Site primarily processes oxide copper ore from three pits: MacArthur, North MacArthur, and Gallagher. Copper recovery is approximately 46 to 59% based on test work from each of the run-of-mine ores. The leach cycle is approximately 90 days with an irrigation rate of 0.0025 gpm/ft². The leach cycle distribution is 75% in the first year and 25% in the second year.

MacArthur Site – Solvent Extraction Facility

The solvent extraction facility will receive pregnant leach solution from the MacArthur PLS pond. The facility will consist of one train with a total of three solvent extraction mixer-settlers and one stripping mixer-settler. At nominal flow of 17,800 gpm, the extraction circuit will operate with two settlers in series and the third settler in parallel. All extraction mixer-settlers have been designed identically and will accommodate equal flowrates. Under high flow conditions, the second stage extraction mixer-settler will become the third parallel extraction mixer-settler. The organic handling equipment includes a crud treatment package.

After solvent extraction, the rich electrolyte is pumped through a 12-inch pipeline in a lined trench approximately five miles to the Yerington Site for electrowinning. After electrowinning, the lean electrolyte from the Yerington Site will be pumped back to the MacArthur Site for reuse in the solvent extraction stripping circuit. There will be a minor lean electrolyte bleed stream from the lean electrolyte to the raffinate stream.

Yerington Site – Crushing and Agglomeration

Sulfide ore from the Yerington Pit will be brought by haul truck to two dump hoppers. Feeders supply two dual shaft mineral sizers deployed as primary crushers, reducing feed size of F80 at 6 inches to P80 at 3.5 inches. The crushed coarse ore will be transported to the coarse ore stockpile by two conveyors.

Coarse sulfide ore will enter the secondary crushing circuit through reclaim feeders. The secondary crushing circuit comprises three parallel trains, each including a feed bin, screen feeder, vibrating sizing screen, and cone crusher. Each train is designed to process a nominal rate of 1,553 STPH or a design rate of 1,864 STPH. The secondary crusher feed bin has a residence time of 15 minutes with a total capacity of 750 ST.

The tertiary crushing circuit comprises five parallel trains, each including a feed bin, apron feeder, vibrating sizing screen, and cone crusher. Each cone crusher will have a nominal throughput capacity of 593 STPH. The tertiary crusher feed bin will have a residence time of 15 minutes with a total capacity of 740 ST. Final crushed product will be P80 of 0.5 inches and P50 of 0.28 inches.

The fine ore stockpile will be reclaimed through reclaim feeders, conveyors, and bins, followed by agglomeration feeders and feed conveyors. Three agglomerators operating in parallel will process the ore with moisture from between 3% and 5% and increase it to 7% with raffinate solution.

Yerington Site – Nuton Technology

Nuton Technology will be implemented to enhance copper extraction from the sulfide ore. Nuton Technology introduces proprietary bacteria and additives to the ore which, when coupled with heap leach operating parameters, facilitates the process of chalcopyrite oxidation and leaching. Pyrite and a process solution stream carrying bacteria inoculum from the Nuton Technology package and pyrite will be added to the agglomerators for sulfide ore. Catalytic additives have not been included in the current design. Their potential value will be reassessed once all Phase 2 test columns have been mass-balanced and for future sample testing and studies.

Pyrite is added to the ore to maintain elevated temperature inside the heap leach facility. Nuton has developed a portfolio of patents directed to biological oxidation of pyrite and heap leach technologies, and implementation of Nuton Technology will target pyrite addition to maintain active leaching areas between 50°C and 60°C to achieve the modeled 73% recovery.

Yerington Site – Sulfide and Oxide Heap Leaching

The copper recovery for Yerington Sulfide is 73%, Yerington Oxide is 68%, and Yerington VLT is 69%. The leach cycle for Yerington Oxide is approximately 90 days with an irrigation rate of 0.0025 gpm/ft². The leach cycle for Yerington sulfide is 180 days with an irrigation rate of 0.0025 gpm/ft². The oxide PLS will partially offset the raffinate solution to the Yerington West HLF when the Yerington East HLF is in operation.

Yerington Site – Solvent Extraction Facility

The solvent extraction facility will have the same layout as MacArthur’s facility, with equipment sized larger due to higher PLS flowrates. It will consist of two trains with a total of three solvent extraction mixer-settlers and one stripping mixer-settler for each train. At nominal flow of 24,100 gpm, the extraction mixer-settlers have been designed identically and will accommodate equal flowrates. Each train can operate with one or two stage extraction depending on the volume of flow. Under high flow conditions, the second stage extraction mixer-settler will become the third parallel extraction mixer-settler.

Electrowinning, Cathode Stripping and Handling

The copper rich electrolyte from MacArthur SX and Yerington SX will combine into one stream. It will pass through a set of parallel dual media filters and heat exchangers to remove any remaining organics and increase the electrolyte temperature. Guar and cobalt will be added to the copper rich electrolyte before the electrolyte enters the electrowinning circuit. The dosage rates are 0.4 lbs/ST Cu for guar and 3.5 lbs/ST Cu for cobalt sulfate heptahydrate.

The electrowinning circuit will consist of 128 cells with 85 lead anodes and 84 cathodes. One rectifier will be used for the electrowinning. The nominal design production rate is 75,000 tpy and maximum of 90,000 tpy.

Sulfuric Acid Plant and Cogeneration Plant

Two sulfuric acid plants with a capacity of 1,500 STPD will produce the sulfuric acid needed for both the Yerington and MacArthur Sites. Sulfur prill will be transported onto site via rail as raw material for sulfuric acid production. Two cogeneration plants will also be in operation in conjunction with the sulfuric acid plants, where a turbine will produce electricity from the excess steam generated by the plant. Some of the steam will be used for liquifying sulfur and heating Yerington’s PLS. Excess sulfuric acid generated by the acid plants will be sold and transported to the market by train.

Key reported parameters

Parameter Units Design / Testwork Basis
Copper Recovery (MacArthur)
Oxide MacArthur % 59 (testwork, ROM)
Oxide North MacArthur % 46 (testwork, ROM)
Oxide Gallagher % 46 (testwork, ROM)
Copper Recovery (Yerington)
Yerington Sulfide (Nuton) % 73
Yerington Oxide % 68
Yerington VLT % 69
Leach Cycles
MacArthur irrigation rate gpm/ft² 0.0025
MacArthur leach cycle days 90
Yerington oxide leach cycle days 90
Yerington sulfide leach cycle days 180
Leach Cycle Distribution
MacArthur Year 1 % 75
MacArthur Year 2 % 25
Yerington sulfide Year 1 % 65
Yerington sulfide Year 2 % 30
Yerington sulfide Year 3 % 5
Crushing
Primary crusher F80 inches 6
Primary crusher P80 inches 3.5
Final product P80 inches 0.5
Final product P50 inches 0.28
Secondary train nominal rate STPH 1,553
Secondary train design rate STPH 1,864
Tertiary crusher nominal throughput STPH 593
SX Facility – MacArthur
Nominal flow gpm 17,800
Extraction mixer-settlers number 3
Stripping mixer-settlers number 1
SX Facility – Yerington
Nominal flow gpm 24,100
Trains number 2
Extraction mixer-settlers per train number 3
Stripping mixer-settlers per train number 1
Electrowinning
Cells number 128
Anodes per cell number 85
Cathodes per cell number 84
Nominal production rate tpy 75,000
Maximum production rate tpy 90,000
Total Copper LOM Production
MacArthur ton 161,610
Yerington ton 559,742
Total ton 721,352
Sulfuric Acid Plants
Capacity per plant STPD 1,500
Reagent Consumption per Unit
MacArthur gross acid (MacArthur pit) lb/ton feed 24
MacArthur gross acid (North Ridge pit) lb/ton feed 44
MacArthur gross acid (Gallagher pit) lb/ton feed 46
Yerington sulfide gross acid lb/ton feed 30
Yerington oxide gross acid lb/ton feed 20
Yerington VLT gross acid lb/ton feed 15
Diluent (MacArthur SX) gal/ton Cu 7.5
Extractant (MacArthur SX) gal/ton Cu 1.9
SX acid (MacArthur) ton acid/ton Cu 0.5
Diluent (Yerington SX) gal/ton Cu 6.23
Extractant (Yerington SX) gal/ton Cu 1.56
SX acid (Yerington) ton acid/ton Cu 0.52
Guar addition lbs/ST Cu 0.4
Cobalt sulfate heptahydrate lbs/ST Cu 3.5

Project website: https://lioncg.com/

Project website: https://www.juniorminingnetwork.com/junior-miner-news/press-releases/989-cse/leo/93966-quaterra-enters-into-agreement-to-sell-certain-yerington-water-rights-for-us-2-91-million.html

Technical qualifications

This report is a prefeasibility study level (PFS) technical report under NI 43-101. The copper recoveries for MacArthur are based on test work from each of the run-of-mine ores. The Yerington sulfide recovery of 73% is modeled based on implementation of Nuton Technology, which introduces proprietary bacteria and additives. Catalytic additives have not been included in the current design, and their potential value will be reassessed once all Phase 2 test columns have been mass-balanced and for future sample testing and studies. The report does not provide final design details for the full processing circuit, and certain parameters remain subject to further testwork and engineering.

Source: Yerington Copper Project , 2023 Technical Report, Recovery Methods section.

Consolidated report summaries

The following former standalone pages about this operation were consolidated here in October 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

MacArthur Project – Mineral Resource Update

MacArthur Project – Mineral Resource Update

Company Lion Copper and Gold Corp.
Date 2022
Region Lyon County, Nevada, USA
Commodities Copper

Executive Summary

This NI 43-101 Technical Report presents an updated mineral resource estimate for the MacArthur Project, located in Lyon County, Nevada. The project is owned by Lion Copper and Gold Corp. and is situated in the Yerington Mining District. The MacArthur Project represents a copper mineralization system that has been explored since the 1970s, with previous mining activity conducted by Arimetco in the late 1990s. The current mineral resource is pit-shell constrained and differs from previous unconstrained estimates. Planned processing includes a ROM heap leach facility with solvent extraction and electrowinning (SX/EW) to produce cathode copper. Additional metallurgical testwork is underway to improve understanding of copper recovery and acid consumption. Environmental baseline studies and permitting are ongoing, with no operating permits yet acquired. The project has potential for expansion through additional drilling and innovative recovery processes.

Key Highlights

  • Status: Exploration/Development
  • Mine Type: Open pit (planned)
  • Processing: ROM heap leach with SX/EW
  • Commodities: Copper (primary)
  • Permitting: None acquired; exploration permits complete

Reports

Website: https://lioncg.com/

Report Date: 2022

Region: Lyon County, Nevada, USA

Project Status:

Commodity: Copper

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

MacArthur Copper Project — 2014 Preliminary Economic Assessment

MacArthur Copper Project — 2014 Preliminary Economic Assessment

Company MacArthur Metals
Date 2014
Region Yerington, Nevada, USA
Commodities Copper
Mine Type Open Pit
Throughput Not specified
Mine Life Not specified
Annual Production Not specified
Status Development

Executive Summary

The MacArthur Copper Project Preliminary Economic Assessment outlines the planned recovery methods for the MacArthur Copper Project located near Yerington, Nevada. The proposed processing facilities include a ROM heap leach facility designed to recover copper from mineralized material using an acidified leach solution. This is followed by a solvent extraction and electrowinning (SX/EW) circuit to produce cathode quality copper for sale. The project also includes a sulfuric acid plant to generate the necessary acid for leaching and a power plant to generate electricity from waste heat produced during sulfur combustion.

The heap leach pad design adheres to Nevada Division of Environmental Protection requirements, featuring a compacted soil base, clay or geosynthetic liner, and HDPE liner with a perforated piping network. Mineralized material is mined from open benches and stacked on the pad, where it is irrigated with raffinate. The pregnant leach solution (PLS) flows by gravity to a collection pond and is pumped to the solvent extraction circuit at a rate of 10,400 gallons per minute.

The solvent extraction plant utilizes mixer-settlers to transfer copper from the aqueous phase to an organic phase, which is then stripped using an acidic electrolyte solution. The rich electrolyte is pumped to electrowinning cells where copper is plated onto stainless steel cathode blanks. The cathodes are harvested weekly, stripped, and bundled for shipment. Ancillary facilities include solution ponds, water and power distribution, and infrastructure to support the operations.

Reports

Website: https://www.juniorminingnetwork.com/junior-miner-news/press-releases/989-cse/leo/115411-lion-copper-and-gold-corp-releases-updated-geology-resource-presentation-on-the-macarthur-copper-project.html

Report Date: 2014

Region: Yerington, Nevada, USA

Project Status: Development

Commodity: Copper

Throughput: Not specified

Mine Life: Not specified

Mine Type: Open Pit

Ore type:

MacArthur Copper Project — 2012 Preliminary Economic Assessment

MacArthur Copper Project — 2012 Preliminary Economic Assessment

Company MacArthur Metals Ltd.
Date 23 May 2012
Region Nevada, USA
Commodities Copper
Mine Type Open Pit
Status Development

Executive Summary

The MacArthur Copper Project Preliminary Economic Assessment outlines a comprehensive recovery plan utilizing heap leach technology for copper extraction. The process involves mining ore from open benches and stacking it on a heap leach pad, where it is irrigated with an acidified leach solution to dissolve soluble copper. The resulting pregnant leach solution is collected and processed through a solvent extraction and electrowinning circuit to produce LME Grade A copper cathodes.

Supporting infrastructure includes a sulfuric acid plant to generate the necessary leaching acid and a power plant designed to generate electricity from waste heat produced during sulfur combustion. The facility is designed to conform to Nevada Division of Environmental Protection requirements, featuring a multi-layer liner system for the heap leach pad and solution ponds to manage water balance and prevent environmental contamination.

Processing Profile

  • Leaching: Heap Leach (ROM)
  • Solvent Extraction: Mixer-Settlers (3 stages extraction, 1 stage stripping)
  • Electrowinning: Stainless steel cathode blanks
  • Acid Plant: Sulfur burning with waste heat recovery

Reports

Website: https://www.globenewswire.com/news-release/2020/04/29/2024277/0/en/further-exploration-for-gold-and-copper-planned-for-macarthur-s-hillside-project.html

Report Date: 23 May 2012

Region: Nevada, USA

Project Status: Development

Commodity: Copper

Throughput: 

Mine Life: 

Mine Type: Open Pit

Ore type:

MacArthur Copper Project — Preliminary Economic Assessment

MacArthur Copper Project — Preliminary Economic Assessment

Project: MacArthur Copper Project
Report Type: Preliminary Economic Assessment (PEA) – Form 43-101F1
Date: 23 May 2012
Document Number: M3-PN110127
Revision: 0

Executive Summary

The MacArthur Copper Project is a copper development project located in Nevada, USA, near the Yerington site. The project utilizes a ROM (run-of-mine) heap leach facility to recover copper into a leach solution, followed by solvent extraction and electrowinning (SX/EW) to produce cathode-quality copper for sale. The process facilities also include a sulfur-burning sulfuric acid plant that generates electrical power from waste heat produced during sulfur combustion.

The heap leach operation will process copper ore mined from open benches. The ore will be transported directly to the heap leach pad and stacked, then irrigated with an acidified raffinate solution. The pregnant leach solution (PLS) will be pumped at 10,400 gallons per minute with approximately 1 gpl copper to the solvent extraction circuit. The SX plant consists of one train of mixer-settlers with three stages of extraction in a series-parallel configuration and one stage of stripping. The electrowinning circuit contains 54 cells that produce LME Grade A copper cathodes, harvested weekly and bundled into 2-3 ton packages for shipment.

Processing Overview

The MacArthur Copper Project employs a conventional heap leach-SX/EW flowsheet for copper recovery. Key facilities include the heap leach pad designed to NDEP requirements, solution ponds, a solvent extraction plant, electrowinning tankhouse, sulfuric acid plant, and power generation facilities. The sulfuric acid plant uses a double-contact double-absorption process that conforms to Best Available Demonstrated Control Technology (BADCT) for sulfur dioxide emissions. Waste heat from the sulfur combustion process drives a steam turbine generator to produce electrical power for the operation.

Processing Details

17.2 Heap Leach Pad

  • Ore Placement: Direct haul from open pit to leach pad
  • Irrigation: Drip emitters with raffinate solution
  • PLS Rate: 10,400 gpm at 1 gpl copper
  • Pad Design: Compacted soil base, clay/GCL liner, HDPE liner, perforated collection piping, 24 inches crushed over-liner

17.3 Solvent Extraction

  • Configuration: One train of mixer-settlers
  • Extraction Stages: Three stages (series-parallel)
  • Stripping Stage: One stage
  • Flow: Counter-current aqueous/organic flow

17.4 Electrowinning

  • Cells: 54 electrowinning cells
  • Product: LME Grade A copper cathodes
  • Harvesting: Weekly schedule
  • Packaging: 2-3 ton bundles

17.5 Sulfuric Acid Plant

  • Process: Double-contact double-absorption
  • Sulfur Source: Molten sulfur delivered by rail
  • Converter: Four-bed converter with vanadium pentoxide catalyst
  • Product: 98.5% H2SO4

17.6 Power Plant

  • Steam Source: Waste heat boiler from sulfur furnace
  • Turbine: Steam turbine generator
  • Cooling: Cooling towers with chemical water treatment
  • Water Treatment: Filtration, cation exchange softening, RO filtration

Ancillary Facilities

  • Fuel storage and distribution
  • Electrical substation
  • Guardhouse and truck scale
  • Refurbished buildings: administration, analytical lab, mine truck shop, warehouse, maintenance facilities

Website: https://lioncg.com/projects/yerington-project/

Report Date: 

Region: 

Project Status:

Commodity: 

Throughput: 

Mine Life: 

Mine Type: 

Ore type:

Mineral processing basics

Scroll to Top