Masbate’s Expanded SABC and Leach-Adsorption Plant Now Treats 8 Mt a Year, With a Third Ball Mill Added in 2019

B2Gold's Masbate Gold Project technical report, effective September 30, 2025, describes a Philippine gold plant expanded from 6.5 Mt a year in 2016 to 8 Mt a year, with a permitted maximum of 9.0 Mt a year.

The Masbate Gold Project, Philippines, NI 43-101 Technical Report was filed by B2Gold Corp. with an effective date of September 30, 2025. The plant uses a conventional SAG mill, ball mill and pebble crusher (SABC) grinding circuit, cyanide leaching with carbon adsorption, Anglo American Research Laboratory (AARL) elution, electrowinning and smelting, and cyanide detoxification of the tailings before they go to the tailings storage facility (TSF). Ore is ground to 80% passing 130 to 150 µm. The plant was expanded to 6.5 Mt a year in 2016, mainly with more leach capacity, and again in 2019 with crushing upgrades and a third ball mill. It now treats 8 Mt a year, against a permitted maximum of 9.0 Mt a year.

Critical Data

Parameter Value Unit Notes
Report effective date September 30, 2025 Not applicable B2Gold Corp.
Current throughput 8 Mt/a Permitted maximum 9.0 Mt/a
Primary crushing Metso C160 jaw (main), C125 jaw (supplementary) Not applicable Secondary GP200, tertiary HP4 cone
SAG mill 9.75 m x 3.62 m EGL, 8,500 kW installed Not applicable 1,000 dry t/h design new ore
Ball mills Two 5.30 m x 7.55 m and one 6.10 m x 9.50 m Not applicable Third mill added in 2019
Pebble crusher HP6, 450 kW Not applicable 250 dry t/h nominal
Grind P80 130 to 150 µm 20 duty and 2 standby cyclones
Leach and adsorption tanks 1 pre-aeration, 5 leach, 8 adsorption Not applicable Leach tanks 15.76 m x 18.30 m
Carbon advance 20.8 t/d 12 t batches; AARL elution
Cyanide destruction Caro's acid Not applicable Sulphuric acid and hydrogen peroxide
Power use 16,500 to 18,500 MWh/month Not applicable
Process water 94% from the TSF Not applicable 6% from a weir on the Guinobatan River

Overview

The design assumes an ore blend of 60% oxide and transition ore and 40% fresh ore. A main crushing plant and a supplementary crushing plant together feed the grinding circuit, and 13 conveyor belts carry ore from crushing to grinding and classification. Tailings run through a 2.1 km HDPE line to the TSF.

Key Process Stages

Crushing. The main plant receives run-of-mine ore through a static 800 mm grizzly and a mobile rock breaker. A 150 mm vibrating grizzly feeds a Metso C160 jaw crusher. The supplementary plant has its own grizzly and a Metso C125 jaw crusher, a 1.82 by 4.84 m primary screen, a GP200 secondary crusher at 62 mm closed side setting, two 2.38 by 6.10 m product screens and an HP4 tertiary cone crusher at 15 mm closed side setting. Crushed ore goes to a 125 t mill feed bin with reclaim feeders.

Grinding. The 9.75 m SAG mill, with a variable speed drive from 64% to 78% of critical speed, runs at a specific energy of about 6.0 kWh/t. An HP6 pebble crusher treats its oversize. Three ball mills, two at 5.30 by 7.55 m and the newer 6.10 by 9.50 m mill, are closed with 20 duty and 2 standby cyclones at 150 to 300% circulating load, targeting P80 150 µm.

Leaching and adsorption. Cyclone overflow passes a 3.6 by 7.30 m trash screen and a leach feed sampler. It then goes to a pre-aeration tank and five 3,500 m³ leach tanks, aerated to a dissolved oxygen target of 15 ppm and fed by an oxygen generator, followed by eight 2,900 m³ adsorption tanks at a 9 ppm oxygen target. Sodium cyanide, quicklime and lead nitrate are the leach reagents.

Elution and refining. About 20.8 t/d of carbon is advanced in 12 t batches, acid washed with hydrochloric acid and stripped in an AARL circuit with a 3,780 kW diesel-fired eluate heater. Three electrowinning cells with 18 cathodes each recover the gold, which is smelted. A regeneration kiln of 600 to 1,100 kg/h reactivates the carbon.

Cyanide destruction and tailings. CIL tailings, at about 1,946 m³/h nominal, are detoxified with Caro's acid, made from sulphuric acid and hydrogen peroxide, before being pumped to the TSF.

Additional Interesting Data and Summary

The section's text describes the adsorption stage as CIP with a 26-hour leach residence time, while the design table lists CIL tankage and a 24-hour nominal leach residence time. This article reports both as the report states them. Potable water comes from two groundwater wells, and seawater is an option if process water runs short. The site has a power station and a solar farm.

In summary, Masbate is a large SABC and leach-adsorption gold plant that has grown in stages, adding leach capacity, crushing and a third ball mill, to 8 Mt a year. It grinds relatively coarsely to 130 to 150 µm and uses Caro's acid for cyanide destruction.

Key Processes

  • Two jaw crushing plants with secondary and tertiary cone crushing
  • SAG milling with HP6 pebble crushing
  • Three ball mills with cyclone classification to P80 130 to 150 µm
  • Pre-aeration and oxygen-assisted cyanide leaching
  • Carbon adsorption in eight tanks
  • Acid wash, AARL elution, electrowinning and smelting
  • Kiln carbon regeneration
  • Caro's acid cyanide destruction and tailings storage

Source: Masbate Gold Project, Philippines, NI 43-101 Technical Report, B2Gold Corp., effective date September 30, 2025.

Earlier report summaries

Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.

Masbate Gold Project — 2011 Technical Report

A conventional carbon-in-leach processing plant on site treats ore from the Masbate Gold Project, with design and operating data reported through March 2012.

Report context

This technical report, dated October 31, 2011, describes the processing facilities for the Masbate Gold Project (MGP), operated by PGPRC. The processing plant was designed by Lycopodium Limited with a nameplate throughput of 4 Mtpa and constructed from September 2007 to April 2009. Ore treatment commenced on April 16, 2009, first gold was poured on May 12, 2009, and commercial production was declared on July 1, 2009. Successful ramp-up led to a revised throughput target of 6.5 Mtpa, with a supplementary crushing circuit commissioned in September 2011 to support this rate on harder feed blends.

Processing route

Crushing and grinding

Primary crushing is performed by a single-stage Nordberg C160 jaw crusher, reducing ore to a top size of 150 mm. Product from the primary crusher feeds directly to the SAG mill. A diverter gate on the conveyor system allows construction of a crushed ore stockpile and provides continuity of feed during jaw crusher maintenance.

A supplementary three-stage crushing circuit consists of a single Nordberg C125 jaw crusher feeding a secondary Nordberg GP200 cone crusher and two tertiary Nordberg HP4 cone crushers. This circuit reduces a portion of run-of-mine ore to a 12 mm product, which flows through the SAG mill to the ball mill section.

A single 6.0 MW Koppers SAG mill receives feed from the primary crusher. Underflow discharge of product less than 12 mm diameter is directed to the ball mills. Overflow product is recycled back to SAG feed after passing through a pebble crusher circuit.

Two parallel 3.6 MW ball mills produce a product with P80 at 106 micron.

Leaching and gold recovery

Gold leaching uses cyanide in a conventional eight-tank circuit, each tank of 3,000 m³ capacity. Gold is recovered from loaded carbon using a normal elution and single-pass electrowinning circuit, followed by smelting to produce gold bullion.

Historical plant performance

From July 2009 to March 2012, the plant processed 13.6 Mt of material at an average grade of 1.16 g/t, producing in excess of 432,000 oz Au. Process availability averaged 89.7% for this period, with the saw-tooth pattern in availability showing quarterly replacement of SAG mill liners. Process recovery averaged 84.9%. Overall recovery shows both mill feed composition (oxide, transitional, primary material types) and residence time within the CIL circuit. Design residence time at 4 Mtpa is 24 hours; at 6.5 Mtpa throughput, residence time is reduced to 19–20 hours.

Addition of lead nitrate enabled the process to maintain design recovery at 6.5 Mtpa throughput rates, and for transitional and primary ore types to improve on design recovery, by driving leach kinetics in the first 3 to 6 hours.

Reduced throughput and production from July 2011 to December 2011 were due to SAG mill repairs. Sharp dips in recovery during February 2010 and April 2010 show lack of lead nitrate reagent due to interruption to delivery to site.

Forward planning parameters

Forward planning targets a throughput rate of 6.5 Mtpa. Systematic improvements in mill liner design and materials have resulted in improved mill availability. Forward planning assumes a six-month cycle of five months at 94% mill availability followed by one month at 87% mill availability (average 92.8%).

Key reported parameters

Parameter Design / Target Historical Operating (July 2009–March 2012) Testwork / Notes
Plant nameplate throughput 4 Mtpa – Designed by Lycopodium
Revised throughput target 6.5 Mtpa – Achieved on oxide-dominant blends; supplementary crusher commissioned September 2011 for harder blends
Primary crusher top size 150 mm – Nordberg C160 jaw crusher
Supplementary crusher product size 12 mm – Three-stage circuit: C125 jaw, GP200 cone, two HP4 cones
SAG mill power 6.0 MW – Koppers mill
Ball mill power (each) 3.6 MW – Two parallel mills
Ball mill product P80 106 micron – –
CIL tank volume (each) 3,000 m³ – Eight tanks
CIL design residence time at 4 Mtpa 24 hours – –
CIL residence time at 6.5 Mtpa – 19–20 hours –
Total material processed – 13.6 Mt To end March 2012
Average feed grade – 1.16 g/t –
Gold production – >432,000 oz Au Since July 2009
Process availability – 89.7% average July 2009 to March 2012
Forward planning mill availability 92.8% average – 5 months at 94%, 1 month at 87%
Process recovery – 84.9% average July 2009 to March 2012
Power consumption (monthly range) – 14.5–16.5 kWh/t Forward planning: oxide 12.1, transition 14.8, primary 17.3 kWh/t
Cyanide consumption (monthly range) – 0.53–0.68 kg/t Forward planning: oxide 0.53, transition 0.58, primary 0.68 kg/t
Lime consumption (monthly range) – 2.20–2.70 kg/t Forward planning: oxide 2.70, transition 2.50, primary 2.20 kg/t
SAG grinding media (monthly range) – 0.13–0.15 kg/t Forward planning: oxide 0.13, transition 0.15, primary 0.15 kg/t
Ball mill grinding media (monthly range) – 0.42–0.45 kg/t Forward planning: oxide 0.42, transition 0.42, primary 0.45 kg/t
Lead nitrate consumption – 0.13 kg/t Same rate used in forward planning for all material types

Project website: https://www.b2gold.com/operations-projects/producing/masbate-mine-the-philippines/default.aspx

Technical qualifications

The report states that major reagent and power consumption rates are related to physical material type of ore processed. Table 17.2 (referenced as Table 17.1 in the source) details typical consumption rates for major consumables and includes values used in forward planning. The report notes that overall process recovery shows both the composition of the mill feed in terms of material type (oxide, transitional, primary) and residence time within the CIL circuit. The supplementary crushing circuit was commissioned to support mill throughput at 6.5 Mtpa on mill feed blends containing 65% primary material.

*Source: Masbate Gold Project , October 2011 Technical Report, Sections 17.1–17.4*