Taysan Copper-Gold Project — Revised PEA (2012)

This revised preliminary economic assessment describes a 15 Mtpa copper-gold concentrator design with associated magnetite by-product recovery, based on conventional processing units.

Report context

The Taysan Copper-Gold Project Revised PEA (2012) was prepared in February 2012 as an order-of-magnitude scoping study update, reducing plant throughput from 30 Mtpa to 15 Mtpa as requested by CZH. The study was intended to provide an indication of capital expenditure, operating expenditure, and potential internal rate of return improvements to guide the project toward prefeasibility and bankable feasibility studies.

Processing route

Primary crushing and ore storage

The concentrator design is based on a maximum copper head grade of 0.60% and a maximum gold head grade of 0.20 g/t, processing 15 Mtpa using a single processing line. The primary crushing circuit, designed for 75% availability and 90% utilisation (67.5% operating utilisation), comprises a 62-inch by 75-inch gyratory crusher delivering 2,537 t/h to meet mill throughput. Coarse ore is stored in a stockpile with 12 hours live capacity (22,500 tonnes) and dozable capacity of 100,000 tonnes, equivalent to two days operation. Reclaim uses three apron feeders, each capable of delivering up to 1,000 t/h to the milling circuit.

Grinding and classification

A SAG-ball (SAB) grinding circuit is designed with 91.3% overall availability, processing nominally 1,875 t/h. The circuit comprises a single 16 MW SAG mill (38 ft by 20 ft) and a single 16 MW ball mill (26 ft by 44 ft) operating in closed circuit. Allowance has been made for possible future installation of a pebble crusher circuit if required.

Flotation and copper concentrate handling

The flotation circuit consists of rougher flotation with two stages of cleaning. Rougher flotation uses six 300 cubic metre tank-type flotation cells. Rougher concentrate is cycloned prior to regrind in an M10000 ISAMill to achieve a 60 micrometre product. The cleaner flotation circuit comprises four 70 cubic metre cleaner cells, three 70 cubic metre cleaner scavenger tank-type flotation cells, and two 3-metre diameter re-cleaner columns.

Re-cleaner flotation concentrate is thickened in a 15-metre diameter Outotec thickener, with overflow recycled to the process circuit. Thickened concentrate is filtered on a vertical plate and frame filter, then stored in a bulk copper concentrate storage shed. A front-end loader loads concentrate trucks for transport to port.

Magnetite recovery

Magnetite is recovered as a by-product from copper flotation tailings streams. The recovery circuit comprises nine wet low-intensity magnetic separator drums (WLIMS) in the rougher circuit. Non-magnetic tails from rougher magnetic separation are pumped to the final tailings thickener. Rougher magnetite concentrate is ground in a closed-circuit 1.6 MW ball mill. The cleaner circuit uses two triple-drum WLIMS separators, with tails reporting to final process plant tailings. Cleaner magnetic separator concentrate is de-magnetised and thickened in a 20-metre diameter Outotec thickener, with overflow recycled and underflow dewatered on a vertical plate and frame filter. Filtered magnetite concentrate is stockpiled in a bulk magnetite concentrate storage shed.

Tailings and process control

Tailings from the rougher and cleaner scavenger flotation circuits are flocculated and thickened in a 55-metre diameter thickener. Underflow is discharged to the tailings storage facility, with overflow returned to the process plant. Make-up process water is collected from the tailings storage facility along with additional raw water.

The control philosophy uses a typical system for contemporary mineral processing operations, with field instrumentation providing inputs to the Process Control System via fibre optic data network. Control modules located in Motor Control Centres perform instrument monitoring, loop control, drive control, process interlocking, and proportional-integral-derivative control.

Key reported parameters

Parameter Basis Unit Quantity
Annual Capacity Design t/a 15,000,000
Concentrator Operating Time Design h/a 8,000
Concentrator Throughput Rate Design t/h 2,537
Ore Head Grade – Copper Design % 0.6
Ore Head Grade – Gold Design g/t 0.2
Ore Head Grade – Copper LOM % 0.3
Ore Head Grade – Gold LOM g/t 0.1
Copper Concentrate Production Design t/a 300,000
Contained Copper Metal Design t/a 81,000
Contained Gold Metal Design oz 48,226
Copper Concentrate Production LOM t/a 150,000
Contained Copper Metal LOM t/a 40,500
Contained Gold Metal LOM oz 24,113
Magnetite Production LOM t/a 364,000
Copper Recovery Design % 90
Gold Recovery Design % 60
Silver Recovery Design % 57
Magnetite Recovery Design % 52
Primary Crusher – type Design 62" x 75" gyratory
Primary Crusher Circuit Throughput Design t/h 2,537
SAG Mill – power Design MW 16
SAG Mill – dimensions Design ft 38 x 20
Ball Mill – power Design MW 16
Ball Mill – dimensions Design ft 26 x 44
Regrind Mill – type Design M10000 ISAMill
Regrind Product Size Design µm 60
Total Installed Load Design kW 78,846
Total Average Running Load Design kW 52,708
Annual Energy Consumption Estimate MWh 421,124
Power Cost Estimate US$/kWh 0.128

Project website: https://www.northernminer.com/news/hounded-by-shortsellers-chase-offers-legal-opinions-to-dispel/1000187477/

Project website: https://www.mining.com/web/crazy-horse-resources-inc-completion-of-pre-feasibility-study-on-taysan-copper-gold-project/

Technical qualifications

Specific data for the Taysan process design was sourced from Metcon and Ammtec laboratory test work, Chase Minerals Corporation Optimet Test Work Report 95034 (December 1995), the AMEC Minproc in-house database, and preliminary vendor and catalogue data. The scoping study update is described as an order-of-magnitude exercise. The SAG mill and ball mill power values are design parameters. The flotation circuit is designed on the basis of 1,875 t/h throughput and nominal feed grade comprising 0.30% Cu with 90% overall copper recovery to a 27% copper concentrate, representing a different basis than the maximum head grade used for overall concentrator design.

Source: Taysan Copper Gold Project – Revised PEA- 15Mtpa Mine (Increased Magnetite), February 2012. Sections 17 Recovery Methods, 17.1 Process Description, 17.2 Process and Equipment Selection.

Mineral processing basics

Scroll to Top