Gadde Bissik — 2016 Technical Report

Figure 25: Conceptual process plant flow sheet
Company Avenira Limited
Date 2016
Region Senegal
Status Development

Executive Summary

This section outlines the conceptual recovery methods for the Gadde Bissik mineralization. Avenira commissioned Consulmet Pty Limited to design a modular, semi-transportable plant based on metallurgical test results. The design allows for future capacity expansion and potential relocation as mining activities progress through the Gadde Bissik area.

The process involves crushing and screening feed material, followed by wet screening to separate final product from reject material. The final product is stockpiled, dried using a tractor, and transported by road to port facilities in Dakar for shipping. Clay and slime components are stored and reclaimed for backfilling mined-out areas.

Processing Overview

  • Crushing: Impact crusher, Primary Screen
  • Screening: Ultrafine vibrating screens
  • Transport: Road transport to Dakar port

Website: https://finance.yahoo.com/news/avenira-files-technical-report-gadde-131309737.html

Report Date: 2016

Region: Senegal

Project Status: Development

Commodity: 

Throughput: 

Mine Life: 

Mine Type: 

Ore type: 