Mineral Processing Circuit of Pueblo Viejo

The Pueblo Viejo processing plant is designed to treat refractory ore at a rate of 24,000 tonnes per day (tpd). The plant employs a pressure oxidation (POX) circuit as the primary method for sulfide sulfur oxidation, followed by carbon-in-leach (CIL) cyanidation for gold and silver recovery.

Processing and Recovery Methods

1. Crushing & Grinding

– Primary Crushing: ROM ore is crushed to P80 of 130 mm using a gyratory crusher, then conveyed to a coarse ore stockpile.

– Grinding: A SAG mill (closed circuit with pebble crusher) and ball mill (closed circuit with hydrocyclones) reduce the ore to P80 of 80 µm.

– Expansion: A new single-stage SAG (SS-SAG) mill is being added to increase throughput.

2. Pressure Oxidation (POX) Circuit

– Autoclave Conditions: Operates at 225°C and 3,100 kPag (500 PSIG) with a 60-minute retention time.

– Oxygen Supply: The oxygen plant is a bottleneck, designed to oxidize 80 tph of sulfide sulfur (requiring 2.2 tonnes O₂ per tonne sulfide sulfur).

– Hot Cure: Oxidized slurry is held at >90°C for 12 hours to dissolve ferric sulfate, reducing neutralization costs.

3. Counter Current Decantation (CCD) Wash Circuit

– A three-stage CCD circuit removes dissolved metal sulfates and sulfuric acid.

– CCD overflow (containing >99% dissolved metals) is used for autoclave quench cooling, reducing emissions.

4. Lime Boil & Neutralization

– Lime Boil: Slurry is reheated to 95°C to break down jarosites and liberate silver.

– Neutralization: Uses limestone and lime in a high-density-sludge (HDS) circuit to precipitate metal sulfates.

5. Carbon-in-Leach (CIL) Cyanidation

– Gold/Silver Extraction: Cyanide and activated carbon recover gold/silver from cooled slurry (50°C).

– Carbon Regeneration: Loaded carbon is acid-washed, stripped via Zadra elution, and reactivated in kilns.

– Electrowinning (EW): Gold/silver are recovered from pregnant solution, then smelted into doré bars.

6. Tailings & Effluent Treatment

– Cyanide Destruction: Uses the INCO process (SO₂ + air + Cu catalyst) to detoxify tailings.

– Acid Rock Drainage (ARD) Treatment: Neutralized sludge is thickened and sent to the tailings facility.

Expansion Project (14 Mtpa Capacity)

– Flotation Circuit: Added to upgrade low-grade ore, with rougher-scavenger cells and a Float Tails CIL (FTCIL) circuit.

– Autoclave Optimization: A flash recycle thickening circuit increases residence time without new autoclaves.

– New Equipment:

– Second gyratory crusher (TSU 1100×1800, 1,645 tph).

– SS-SAG mill (23,000 kW).

– Flotation cells (2 trains of 5 cells).

– Expanded oxygen plant (additional 3,000 tpd capacity).

Key Technical Challenges & Solutions

– Oxygen Bottleneck: Expansion increases O₂ demand; new plant capacity addresses this.

– Sulfide Sulfur Handling: Controlled feed blending ensures stable autoclave performance.

– Mercury Management: Carbon kilns include mercury absorbers to capture off-gases.

Throughput & Recovery Metrics

– Current: 24,000 tpd (8.6 Mtpa).

– Expanded: 14 Mtpa (38,356 tpd).

– Recovery Rates: Not explicitly stated, but optimized via CCD, CIL, and flotation.

Innovations

– Flash recycle thickening enhances autoclave efficiency.

– Integrated HDS neutralization reduces acid consumption.

– On-site lime/limestone production minimizes costs.

The plant’s flowsheet integrates POX, CIL, and flotation to maximize recovery from refractory ore, with expansion focusing on lower-grade ore treatment and tailings capacity.