Piskanja 2022 PEA Assumes Turkish-Style Colemanite and Ulexite Beneficiation Plus a 25 ktpa Boric Acid Plant, With 95% of Tailings Used as Backfill

The 2022 preliminary economic assessment for the Piskanja borate project in Serbia, prepared for Erin Ventures and Temas Resources, raises the target concentrate grades to 40 to 45% B2O3. The report states that the metallurgical parameters are largely assumptions pending testwork.

The Technical Report and Preliminary Economic Assessment for the Piskanja Borate Project, Serbia, was prepared for Erin Ventures Inc. and Temas Resources Corp., with an effective date of June 24, 2022 and a signature date of August 1, 2022. The report says more testing is needed to find the best way to upgrade the Piskanja mineralization to a minimum marketable concentrate grade. Borate beneficiation is, however, established and widely used in Turkish boron mines. The PEA assumes a flowsheet like that of the Emet colemanite plant in Turkey. Per Burat (2008), Emet treats 600,000 t a year of 27% B2O3 ore to make 300,000 t a year of concentrate at 43% B2O3. The Piskanja plan produces about 250 ktpa of colemanite and ulexite concentrates, and later 25 ktpa of boric acid.

Critical Data

Parameter Value Unit Notes
Report effective date June 24, 2022 Not applicable For Erin Ventures Inc. and Temas Resources Corp.
Average head grade (mine plan) 34.99 % B2O3 Range of head grades in the mine plan
Colemanite concentrate 40 % B2O3 Assumed
Ulexite concentrate 45 % B2O3 Assumed
Mixed colemanite/ulexite concentrate 40 % B2O3 Assumed
Tailings grade 7.5 % B2O3 From the magnetite fraction in SGS HIMS testwork
Concentrate production About 250 ktpa Colemanite and ulexite in total
Boric acid production 25 ktpa Later in the mine life; 80% B2O3 recovery assumed
Beneficiation tailings 18 to 200, average 47 ktpa Varies with ROM grade
Boric acid tailings 42 ktpa Expected
Tailings to backfill 95 % 5% to the TSF
TSF About 150,000 m³ over about 6 ha Not applicable Double 2 mm HDPE liner

Overview

The Emet reference flowsheet concentrates colemanite by disintegration, washing and size classification. Coarse sizes are upgraded by attrition tumbling and hand sorting, and fines below 6 mm by attrition scrubbing and size classification. For Piskanja, the PEA assumes a similar beneficiation route to colemanite, ulexite and mixed concentrates. A boric acid plant would follow later in the mine life. Mass yield and B2O3 recovery in beneficiation vary with run-of-mine grade, against fixed concentrate and tailings grades. About 95% of the beneficiation and boric acid tailings is used as underground backfill. The rest goes to a lined tailings storage facility (TSF) south of the plant.

Key Process Stages

Beneficiation (assumed). Disintegration, washing and classification are followed by attrition tumbling and sorting for coarse material and attrition scrubbing for fines. The process is modelled to give 40% B2O3 colemanite, 45% B2O3 ulexite, and 7.5% B2O3 tailings.

Boric acid. A 25 ktpa boric acid plant is assumed at a typical industry recovery of 80% of B2O3. The report recommends testing how feed grade affects sulphuric acid consumption.

Tailings storage. Of about 1.22 Mt of tailings produced over the project, about 61,000 t (55,000 m³ at a dry density of 1.1 t/m³) goes to the TSF. The site is a former Ibar Mine settling pond for coal washing, on already-degraded land. The conceptual dam is about 4.4 m high, with a 5 m crest, 1V:2.5H downstream and 1V:3H upstream slopes, and 1 m of freeboard. It uses downstream construction, as in the 2014 PEA. The design volume is about three times the need, to allow emergency spill catchment. Tailings are delivered as slurry by pipeline. A decant system returns water to the plant, and a leak detection system sits between and below the HDPE liners.

Additional Interesting Data and Summary

The report says only very limited metallurgical testwork supports the PEA. That work brought the iron content of the product close to target, but it did not upgrade the boron content to the assumed 40% B2O3. No specific process plant engineering was done, and plant costs are high-level estimates from generic databases and similar projects. Future testwork should cover the full range of grade and mineralogy, meaning the ratios of colemanite, ulexite and howlite. Dry stacking of tailings remains an option pending geophysical, rheological and geochemical testing.

In summary, the 2022 Piskanja PEA is a conceptual borate flowsheet modelled on Turkish colemanite practice. It assumes 40 to 45% B2O3 concentrates and a small boric acid plant, and its process basis remains unproven by testwork.

Key Processes

  • Ore disintegration, washing and size classification (assumed)
  • Attrition tumbling, hand sorting and attrition scrubbing (assumed)
  • Colemanite and ulexite concentrate production
  • Boric acid production with sulphuric acid
  • Tailings backfill and lined slurry tailings storage

Source: Technical Report and Preliminary Economic Assessment for the Piskanja Borate Project, Serbia, prepared for Erin Ventures Inc. and Temas Resources Corp., effective date June 24, 2022.

Earlier report summaries

Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.

Piskanja Project — 2014 PEA

The 2014 PEA for the Piskanja project assumes a conceptual processing route to produce colemanite concentrate and boric acid, based on limited testwork and no demonstrated technically feasible process route.

Report context

The preliminary economic assessment (PEA) for the Piskanja project was prepared by SRK Consulting in September 2014. The report acknowledges that no technically feasible process route has yet been demonstrated that can upgrade the Piskanja ore to what is considered a minimum marketable colemanite concentrate grade. The processing assumptions and conceptual flowsheet presented in the PEA are based on a limited amount of non-definitive metallurgical data.

Processing route

Processing assumptions

For the purpose of the PEA, SRK assumed that a process can be developed to upgrade the ore to satisfactory levels of B₂O₃ and iron. The assumed criteria are a concentrate grade of 35% B₂O₃ for the range of head grades in the proposed mine plan (24.3-32.9% B₂O₃) and a tailings grade of 7.5% B₂O₃, the figure achieved for the magnetite fraction in the SGS HIMS testwork.

Production plan

The production plan calls for the production of both colemanite concentrate and boric acid, the latter at a rate of 25 ktpa and the former at a rate of approximately 200 ktpa. SRK modelled this production scenario according to a conceptual process route shown in block form as Figure 17-1 in the report.

The mass yield and B₂O₃ recovery across the beneficiation stage are variable, a function of the variable run-of-mine grade and the fixed concentrate and tailings grades. For the boric acid plant, a fixed B₂O₃ recovery of 80% has been assumed as representing a typical industry value.

Tailings management

The quantity of beneficiation plant tailings is projected to range from 22 ktpa to 123 ktpa over the life of the project, averaging 88 ktpa. The quantity of tailings from the boric acid plant is expected to be 49 ktpa.

A desktop study was undertaken to determine the possible location for the tailings storage facility (TSF) to store 5% of 1.8 million tonnes of colemanite tailings and 5% of 1.0 million tonnes of boric acid tailings material. The amount of tailings material to be stored within the TSF totals 0.135 Mt (0.122 Mm³) at a dry density of 1.1 t/m³. The remaining 95% of boric acid and colemanite tailings will be utilised for backfill.

Site selection

The site selection study was not carried out as the client’s preferred location was the site immediately south of the proposed plant. The client stated that this site was previously used by the Ibar Mine to clarify water for the coal washing plant and was therefore considered a perfect location for the TSF.

TSF design

A conceptual TSF design has been developed by SRK to store about 150,000 m³ of tailings material that occupies an area of about 6 ha including the dam footprint area. SRK considered a downstream construction method for the proposed facility, which will require the construction of full height dam walls using suitable material for construction acquired from local borrow areas. The dam wall will have slopes of 1V:2.5H on the downstream side and 1V:3H on the upstream side and a crest width of 5 m. The maximum dam height at the lowest ground is about 4.4 m, and the crest elevation at 381 metres above sea level. A freeboard of 1 m was added to the dam height.

Tailings waste will be disposed as slurry which will be delivered via a pipeline into the facilities. SRK did not consider dry stacking at this stage as there are many unknowns regarding the final tailings product. The conceptual design includes a double 2 mm HDPE liner system with a leakage detection system between the liners and below the bottom liner.

Key reported parameters

Parameter Value Basis
Concentrate grade (B₂O₃) 35% Assumed design criterion
Head grade range (B₂O₃) 24.3-32.9% Proposed mine plan
Tailings grade (B₂O₃) 7.5% Based on SGS HIMS testwork (magnetite fraction)
Colemanite concentrate production ~200 ktpa Production plan
Boric acid production 25 ktpa Production plan
Boric acid plant B₂O₃ recovery 80% Assumed typical industry value
Beneficiation plant tailings (life-of-project range) 22-123 ktpa Projected, variable
Beneficiation plant tailings (average) 88 ktpa Projected
Boric acid plant tailings 49 ktpa Projected
TSF storage capacity 150,000 m³ Conceptual design
TSF storage mass 0.135 Mt At dry density 1.1 t/m³
TSF area ~6 ha Including dam footprint
Dam slopes (downstream:upstream) 1V:2.5H : 1V:3H Conceptual design
Dam crest width 5 m Conceptual design
Maximum dam height 4.4 m At lowest ground
Dam crest elevation 381 masl Conceptual design
Freeboard 1 m Conceptual design

Project website: https://www.theglobeandmail.com/investing/markets/markets-news/ACCESS%20Newswire/1076360/boron-one-holdings-inc-advances-with-potential-partner/

Project website: https://www.juniorminingnetwork.com/junior-miner-news/press-releases/1256-tsx-venture/bone/47167-erin-ventures-completes-current-boron-property-exploration-program.html

Technical qualifications

The report states that only a very limited amount of metallurgical testwork has been undertaken in support of the production of this PEA. This work consisted of some upgrading testwork which, while resulting in a reduction in the iron content of the product to close to the assumed target level, did not result in any significant upgrading of the boron content, at least not to the assumed minimum figure of 35% B₂O₃ for a saleable colemanite concentrate.

The metallurgical parameters developed for the PEA are therefore largely assumptions based on a limited amount of non-definitive data. Virtually no specific engineering was conducted with regard to the process plant design, and the process plant capital and operating costs subsequently generated are high level estimates based on generic databases and parallel project data.

No technically feasible process route has yet been demonstrated that can upgrade the Piskanja ore to what is considered to represent a minimum marketable colemanite concentrate grade.

Geophysical, rheological and geochemical testing on tailings material is recommended to evaluate the preferred tailings deposition method.

*Source: Piskanja Project , 2014 PEA, U5932 Piskanja 43-101 PEA_Final.docx, September 2014, sections 17.1, 17.2, 17.3*

Mineral processing basics

Scroll to Top