San Manuel’s Integrated Copper Recovery Complex: A Historical Record

The San Manuel Property in Arizona once hosted a fully integrated copper recovery complex, combining sulfide flotation, smelting, and refining with heap and in situ leaching served by a central SX-EW plant. This article reviews the process configuration, equipment, and historical performance of that operation.

Opening Paragraph

The San Manuel Property is a historical mine site located in Pinal County, Arizona, approximately 65 miles northeast of Tucson. Owned by Faraday Copper Corp., the property is not an operating mine and currently holds no current mineral resource or reserve estimates. Historical production of copper, along with by-product molybdenum, gold, and silver, occurred from 1956 to 1999 via underground block-cave mining, open-pit mining, and in situ recovery methods. The property was placed on care and maintenance in 1999, formally closed in 2003, and surface facilities were demolished by 2007. The project is in a closed and reclaimed state, and a recommended work program to generate a current mineral resource is anticipated to require confirmation drilling.

Critical Data

Parameter Value Unit Notes
Property Status Historical mine site Not applicable Closed and reclaimed; formally closed in 2003.
Commodity Copper Not applicable Molybdenum, gold, and silver were historical by-products.
Sulfide Concentrator Operating Period 1956 to 1999 Year Conventional crush-grind-flotation circuit.
Heap Leach / SX-EW Operating Period 1986 to 2002 Year Treated oxide and secondary-sulfide ore.
LoM Sulfide Ore Milled 703,686,000 st Average feed grade of 0.66% Cu and approximately 0.03% MoS₂.
LoM Refined Copper Production 4,651,600 st Produced from 1956 to 1999.
LoM Molybdenum in Concentrate 73,200 st Shipped off-site for processing.
Design Mill Capacity (Circa 1982) 66,000 stpd Capacity varied over life, from 30,000 stpd in 1955 to 62,500 stpd in 1991.
Historical Cu Plant-Circuit Recovery 89.5 % Reported for 1991; includes Cu recovered from smelter slag.
LoM Heap Leach ASCu Extraction 88.3 % Achieved at closure in 2002.
Historical ISL Zone 6 ASCu Extraction 41.7 % Reported at zone closure.
SX-EW Plant Design Capacity (1988) 100 Mlb/y Two tankhouses, each originally designed for 25,000 st/y.
SX-EW Peak Annual Production (1993) 124 Mlb Combined heap and ISL feed.

Overview

The historical processing complex at San Manuel comprised two distinct operational units. The first was a conventional crush-grind-flotation concentrator with downstream molybdenum recovery, smelting, and electrolytic refining that treated sulfide ore from 1956 to 1999. The second was a heap-leach and in situ-leach circuit with a central solvent extraction and electrowinning (SX-EW) plant that treated oxide and secondary-sulfide ore from 1986 to 2002. Both units operated in parallel from 1986 onward, sharing an on-site sulfuric acid supply generated from the smelter’s SO₂ off-gas. The mill, smelter, and electrolytic refinery were integrated facilities on the plant site itself, with concentrate and intermediate streams transferred between them by short on-site rail and conveyors.

The sulfide concentrator processed 703,686,000 st of ore over its 44-year life, producing 4,651,600 st of refined copper. The heap leach and SX-EW circuit contributed additional copper production, with a cumulative acid-soluble copper (ASCu) extraction of 88.3% from stacked ore by the end of leaching in 2002. In situ leaching (ISL) operated in two parallel modes for most of its life, with documented extraction rates that varied by zone.

Key Process Stages

Sulfide Concentrator

The concentrator had a two-stage crushing circuit. Primary crushing was performed at the surface by four Nordberg gyratory crushers, each rated at 1,100 mt/h, located adjacent to the production shafts. ROM crushed ore was then hauled by rail approximately 6.8 miles to the on-site concentrator. Secondary crushing was performed by 11 Nordberg Symons cone crushers.

Grinding consisted of 13 wet grinding sections. Each section comprised one rod mill in open circuit plus two ball mills in closed circuit with hydrocyclones. The smaller sections used 10.0 × 10.0-ft rod mills and 10.0 × 13.0-ft ball mills, while the three large sections used 12.5 × 14.0-ft rod mills and 12.5 × 16.0-ft ball mills. Hydrocyclones were 20.0-in Krebs D20B units in 1982, later upgraded to 26.0-in Krebs units in the late 1980s to early 1990s.

The flotation circuit employed conventional bulk sulfide flotation followed by selective copper-molybdenum separation. Hydrocyclone overflow fed bulk Cu-Mo rougher flotation, where rougher concentrate was reground to 75% to 80% passing 325-mesh and cleaned in conventional cells through 1985. By 1991 to 1992, the cleaner circuit had been reconfigured to use 16 Magma-designed column flotation cells, each 5.9-ft in diameter and 39.0-ft high. At that time, the circuit comprised eight independent flotation sections with rougher cells including ten Maxwell 2,000-ft³ and 143 Wemco 300-ft³ cells.

The bulk Cu-Mo cleaner concentrate, which served as feed to the on-site molybdenum recovery plant, contained approximately 30% Cu and 0.90% to 1.00% MoS₂. The final cleaner concentrate, shipped after Mo separation, contained approximately 30% Cu and 0.90% to 1.00% MoS₂. The rougher Cu concentrate contained 9% to 12% Cu and 0.4% to 0.5% MoS₂.

An on-site slag retreatment circuit treated approximately 2,200 mt/d of flash-furnace and converter slag at approximately 3% Cu feed, returning slag concentrate at approximately 30% Cu to the smelter.

Molybdenum Recovery Plant

The molybdenum recovery plant treated the bulk Cu-Mo concentrate in a selective separation circuit using reagents to depress copper sulfides, allowing molybdenite to be floated into a separate concentrate. The Mo flotation circuit used three successive copper-depressant chemistries over its operating life: NaOCl-ferrocyanide from January 1956 to January 1964, H₂O₂-ferrocyanide from January 1964 to January 1980, and NaHS + NaCN from January 1980 onward.

The process involved thickening the bulk Cu-Mo concentrate in a 125-ft Eimco thickener to 60% to 64% solids, holding it in a 25 × 36.1-ft tank with 7-hour retention, and conditioning it in a 10.0 × 10.0-ft Denver overflow conditioner with NaCN + NaHS dosed at 44% to 46% solids and 20-minute retention. The conditioned pulp then passed through an 8-stage countercurrent cleaning train, using Galigher #36 cells in early stages and Denver #18 Specials in stages 4 to 8. A 4.00-ft square × 32.0-ft column flotation cell was installed in 1981 for fine-MoS₂ scavenger duty and was later repositioned to replace cleaners 2 to 4.

The 8th-cleaner concentrate, containing approximately 87% to 88% MoS₂ and 1.2% to 1.3% Cu, was repulped to 50% solids and held with NaCN at 0.2% free CN for 36 hours before three-stage countercurrent recleaning with attrition scrubbing and sodium-silicate as an "insol" depressant. Final Mo concentrate contained approximately 91% to 92% MoS₂ and 0.75% Cu. The concentrate was filtered, dried in multi-hearth Skinner dryers to less than 10% moisture, and packaged in 55-gallon steel drums for off-site sale.

Smelting and Refining

The on-site smelter operated continuously from January 1956 to October 2003. The original configuration included one green-feed reverberatory furnace, three Pierce-Smith converters, two anode vessels, and one anode casting wheel. Through the late 1960s and early 1970s, it was expanded to three reverberatory furnaces, six converters, four anode vessels, and two casting wheels. A two-train Monsanto sulfuric acid plant was added in 1974.

In July 1988, under an EPA-Magma consent decree, the three reverberatory furnaces were replaced by a single 2,700 to 3,000 mtpd Outokumpu single-burner flash furnace, and the acid plant was modified from single-contact to double-absorption. The first flash-furnace campaign ran from July 1988 to May 1999, a world-record campaign for an Outokumpu copper flash furnace, processing approximately 10.9 Mt of new sulfide concentrate and yielding 3.1 Mt of new anode copper. The smelter drew roughly two-thirds of its feed from Magma's San Manuel, Pinto Valley, and Superior mines, with one-third from open-market toll smelting.

The refinery operated electro-refining at 27 A/ft² with a 12-day plating cycle and produced 350-lb cathodes. A 1995 bismuth quality issue in cathodes was managed by operational changes to starter-sheet production and electrolyte bleed.

Heap Leaching

A run-of-mine leach facility treated copper oxide ore and low-grade secondary sulfide material that was not amenable to flotation. The operation used dilute sulfuric acid solutions applied directly to ore. Six phases of leach pad construction occurred from April 1986 to August 1992, bringing the cumulative pad area to approximately 10,322,600 ft² of HDPE-lined leach surface. The original 1985 to 1986 build was the first plastic-lined heap leach in Arizona.

All ore sent to the heap leach was run-of-mine at 90% passing 4-inch. Crushing and agglomeration were not employed. Lift height was 15-ft from 1986 through early 1992, reduced to 10-ft thereafter, which drove an increase of approximately 5% in cumulative recovery. The final stack configuration in 1999 included 18 leach modules, each approximately 400 × 300 ft, with an ultimate stack height of about 300 ft and a 30° side slope.

Standard pre-cure practice involved two sulfuric acid applications at 250 g/L: a first application of 15 lb/ton of ore with a 4-day rest, then a second application of 10 lb/ton with a 3-day rest. Operating raffinate was pH 1.5 to 1.6, containing 0.06 to 0.20 g/L Cu, 1.13 to 1.8 g/L Fe, and 15 to 18 g/L free H₂SO₄, applied at 5.15 gal/(h·m²) at active loading and reduced to 1.9 to 2.6 gal/(h·m²) for residual leach. A 35-ppm cationic fluorochemical surfactant was added to the barren leach from June 1992 onward, following a test program that demonstrated cumulative ASCu extraction above 73% with the surfactant versus 63% without.

In Situ Leaching

In situ leaching operated in two modes. Surface-to-underground gravity-flow leaching, commissioned in June 1986 with 26 injection wells, was the sole mode through September 1989. This mode injected acidified raffinate from the surface into partially rubblized supergene rock above the abandoned block-cave levels, with PLS draining by gravity into adapted underground haulage drifts before being pumped approximately 2,380 ft to the surface SX-EW plant. Well-to-well leaching was added in September 1989, operating in modified seven-spot patterns on open-pit catch benches with 40.0-ft corner-to-corner spacing, later expanded to 49.87-ft for the 1998 west-side expansion.

Injection wells were reverse-circulation drilled with 1.5-inch Schedule 80 PVC casing. Production wells were mud-rotary drilled with 6-inch Schedule 80 PVC casing, 328 to 492-ft deep, fitted with submersible 304 SS / 316 SS centrifugal pumps at 7.4 to 11 kW. The active leach zone was 200 to 394 ft below the bench surface. By late 1998, the operation comprised approximately 1,200 wells across six leaching zones.

Solvent Extraction and Electrowinning

The SX-EW plant was commissioned in May 1986 with a rated cathode capacity of 25,000 st/y at 20 A/ft², expanded in 1988 to 50,000 st/y when ISL streams were added. The plant baseline included two tankhouses, each with two rectifiers and 94 EW cells. Each tankhouse was designed for 25,000 st/y but achieved 32,500 st/y in operation. Combined PLS feed of approximately 17,611 to 19,813 gpm was collected in a 1,341,600 ft³ plant feed pond before flowing to four parallel SX trains.

The solvent extraction circuit used an oxime-based organic extractant, specifically Henkel LIX 984, in Phillips 85X7 diluent. A semi-automatic montmorillonite-clay treatment system on a Sparkler vertical-plate stainless filter, retrofitted in 1991 to 1992, cleaned circuit organic, recovered entrained organic from the raffinate pond, and increased SX flow capacity from 16,000 to 19,500 gpm. The EW circuit deposited copper onto starter sheets to produce LME Grade A copper cathodes at 99.999% Cu. The San Manuel cathode was COMEX-certified in August 1991 and LME-listed as Grade A Copper in April 1992, the second SX-EW product ever LME-certified.

Gold Cyanidation Plant

A small on-site gold cyanidation plant processed Mo-plant final concentrate to recover Au, Ag, and 20% to 30% of the contained Cu. In June 1974, the plant processed 12.2 st/d of Mo concentrate at 0.462 oz Au/short ton, achieving 87% Au extraction by assay and 95% by independent gold balance.

Additional Interesting Data and Summary

Historical mill copper recovery was reported at 89.5% in 1991, a figure that captures copper recovered from smelter slag and returned to smelter feed. The ROM final flotation tailings grade reached a low of 0.076% Cu in 1990. Molybdenum recovery to the bulk Cu-Mo concentrate was 79.68% in 1984 and 81.91% in 1985 YTD, while recovery from bulk concentrate to final Mo concentrate was 82.75% in 1984 and 65.93% overall that year.

Heap leach cumulative ASCu extraction progressed from 73% around 1993 to 74.5% at the end of open-pit feed in January 1995, then to 86% at the end of 1998, and finally 88.3% at the end of leaching in 2002. For in situ leaching, a reconciliation for Zone 6, the longest-running ISL zone, showed cumulative ASCu extraction of 41.7% at zone closure against a BHP forecast of 52%. A controlled 551-day well-to-well test on a three-cell array produced 1 million kg of Cu, with ASCu extraction ranging from 45.5% in the footwall cell to 64.6% in the hanging-wall cell, demonstrating structural control of sweep efficiency.

The San Manuel operation represents a complete historical record of a large, integrated copper processing complex. All facilities are closed and demolished, but the technical documentation of equipment, flowsheets, and operating performance provides a detailed reference for the processing methods employed at this site.

Key Processes

  • Two-stage crushing (gyratory and cone crushers) followed by rod mill and ball mill grinding in closed circuit with hydrocyclones
  • Bulk Cu-Mo flotation with regrind and column flotation cells, followed by selective Cu-Mo separation
  • Molybdenum recovery via differential flotation with copper sulfide depression using NaHS and NaCN
  • Smelting in an Outokumpu flash furnace with double-absorption sulfuric acid plant
  • Electrolytic refining at 27 A/ft² producing 350-lb LME Grade A copper cathodes
  • Run-of-mine heap leaching with HDPE-lined pads, sprinkler irrigation, and surfactant addition
  • In situ leaching via surface-to-underground gravity flow and well-to-well injection patterns
  • Solvent extraction using oxime extractant with a clay treatment system for organic recovery
  • Electrowinning of high-purity copper cathode
  • Gold cyanidation of Mo-plant concentrate for by-product recovery

Source: Technical Report, San Manuel Property, July 29, 2026. Project website: San Manuel Property

Consolidated report summaries

The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

San Manuel’s Integrated Processing Complex: A Record of Copper Recovery in Arizona

A look at the historical recovery methods at the San Manuel Property, a closed copper mine in Arizona, covering its sulfide concentrator, heap leach, in situ leaching, and SX-EW operations.

The San Manuel Property is a historical mine site located in Pinal County, Arizona, approximately 65 miles northeast of Tucson and 75 miles east-southeast of Phoenix. The property, held by Faraday Copper Corp., is not an operating mine. It is a closed and reclaimed former copper producer that operated historically until approximately the late 1990s, with processing facilities on care and maintenance by June 1999, formally closed in October 2003, and demolished by 2007. The property encompasses patented and fee land, unpatented federal mining claims, Arizona State Land Department Mineral Exploration Permits, and split estate surface lands and mineral rights. Its target commodity is copper, with gold, molybdenum, and minor silver historically recovered as by-products. The San Manuel mine was mined via open pit, block cave, and in situ recovery methods over its operating life. A recommended work program to generate a current NI 43-101 compliant Mineral Resource is anticipated to require approximately 82,000 ft of confirmation drilling at an estimated cost of US$17,200,000.

Critical Data

Parameter Value Unit Notes
Property location Pinal County, Arizona Not applicable Approximately 65 miles northeast of Tucson
Property status Closed and reclaimed Not applicable Historical mine site
Issuer Faraday Copper Corp. Not applicable Not stated
Target commodity Copper Not applicable Gold, molybdenum, and minor silver historically recovered as by-products
Historical sulfide ore milled 703,686,000 st Over 44-year operating life
Average sulfide feed grade 0.66 % Cu Life of mine
Historical concentrator Cu recovery 89.5 % 1991 total concentrator copper recovery
Historical refined Cu production 4,651,600 st 1956 to 1999
Historical Mo production 73,200 st Mo in concentrate shipped for off-site processing
Heap leach LoM ASCu extraction 88.3 % At end of leaching in 2002
Heap leach LoM cathode production ~345,000 st Equivalent to 690 Mlb
ISL Zone 6 cumulative ASCu extraction 41.7 % At zone closure
SX-EW rated cathode capacity 50,000 st/y After 1988 expansion
Expected construction timing Not stated Not applicable No current development plan stated

Overview

The historical processing complex at San Manuel comprised two distinct operational units. A conventional crush-grind-flotation concentrator with downstream Mo recovery, smelting, and electrolytic refining treated sulfide ore from 1956 to 1999. A heap-leach, in situ-leach, and SX-EW circuit treated oxide and secondary-sulfide ore from 1986 to 2002. Both units operated in parallel from 1986 onward, sharing on-site sulfuric acid supply from the smelter SO₂ off-gas. The mill, smelter, and electrolytic refinery were integrated facilities on the San Manuel Plant Site itself, with concentrate and intermediate streams transferred between them by short on-site rail and conveyors.

The deposit is one of the largest Laramide porphyry copper systems in Arizona. Mid-Tertiary extension on the low-angle, southwest-dipping San Manuel fault offset the original porphyry column by approximately 3,609 to 4,265 ft of dip-slip, producing two spatially separated orebody segments. The San Manuel deposit extends approximately 7,710 ft down dip and 2,707 ft along strike from near surface at a 0.5% Cu cut-off, while the Kalamazoo deposit extends approximately 6,693 ft down dip and 3,002 ft along strike from a top-of-mineralization depth of approximately 1,600 ft.

Key Process Stages

The sulfide concentrator processed underground block cave feed through a two-stage crushing circuit. Primary crushing was performed at the surface by four Nordberg gyratory crushers each rated at 1,100 mt/h, located adjacent to the production shafts. ROM crushed ore was hauled by rail approximately 6.8 miles to the on-site concentrator. Secondary crushing at the concentrator was performed by 11 Nordberg Symons cone crushers. Grinding consisted of 13 wet grinding sections, each comprised of one rod mill in open circuit plus two ball mills in closed circuit with hydrocyclones.

The flotation circuit employed conventional bulk sulfide flotation followed by selective copper-molybdenum separation. Hydrocyclone overflow fed bulk Cu-Mo rougher flotation where rougher concentrate was reground to 75% to 80% passing 325-mesh and cleaned in conventional cells through 1985. By 1991 to 1992 the cleaner circuit had been reconfigured to use 16 Magma-designed column flotation cells, each 5.9-ft diameter by 39.0-ft high. Chadwick reported eight independent flotation sections with rougher cells comprising ten Maxwell 2,000-ft³ and 143 Wemco 300-ft³ in service.

A separate on-site slag retreatment circuit treated approximately 2,200 mt/d of flash-furnace and converter slag at approximately 3% Cu feed, returning slag concentrate at approximately 30% Cu to the smelter and slag tailings at 0.45% Cu against a target of 0.30%.

The Mo recovery plant treated bulk Cu-Mo concentrate in a selective separation circuit using reagents to depress copper sulfides. The Mo flotation circuit used three successive Cu-depressant chemistries over its operating life: NaOCl-ferrocyanide from January 1956 to January 1964, H₂O₂-ferrocyanide from January 1964 to January 1980, and NaHS plus NaCN from January 1980 onward. The 1985 plant had two parallel flowsheets of identical design. Bulk Cu-Mo concentrate was thickened in a 125-ft Eimco thickener to 60% to 64% solids, held in a holding tank with 7-h retention, conditioned with NaCN plus NaHS dosed at 44% to 46% solids and 20 min retention, then floated through an 8-stage countercurrent cleaning train. A column flotation cell was installed in 1981 for fine-MoS₂ scavenger duty and by March 1985 had been repositioned to replace cleaners 2 to 4.

The smelter and electrolytic refinery operated continuously from January 1956 commissioning to October 2003 final closure. The smelter began with one green-feed reverberatory furnace, three Pierce-Smith converters, two anode vessels, and one anode casting wheel. In July 1988, under an EPA-Magma consent decree, the three reverberatory furnaces were replaced by a single 2,700 to 3,000 mtpd Outokumpu single-burner flash furnace. The first flash-furnace campaign ran for 10 years 9 months 23 days, a world-record campaign for an Outokumpu copper flash furnace, processing approximately 10.9 Mt of new sulfide concentrate yielding 3.1 Mt of new anode copper. The refinery operated electro-refining at 27 A/ft² with a 12-day plating cycle and 350-lb cathodes.

The heap leach facility treated copper oxide ore and low-grade secondary sulfide material that was not amenable to, or uneconomic for, flotation treatment. Six phases of leach pad construction occurred from April 1986 to August 1992, bringing the cumulative pad area to approximately 10,322,600 ft² of HDPE-lined leach surface. The original 1985 to 1986 build was the first plastic-lined heap leach in Arizona. All ore sent to the heap leach was run-of-mine oxide ore at 90% passing 4-inch. Crushing and agglomeration were not employed at any stage of the heap-leach circuit.

The in situ leaching operation ran in two parallel modes for most of its operating life. Surface-to-underground gravity-flow leaching, commissioned June 1986, injected acidified raffinate from the surface into partially rubblized supergene rock above the abandoned San Manuel block-cave underground levels and gravity-drained PLS into adapted underground haulage drifts. Well-to-well leaching, added September 1989, operated in modified seven-spot patterns on open-pit catch benches with 40.0 ft corner-to-corner spacing through 1989 to 1998.

The solvent extraction circuit processed PLS to selectively extract copper using an organic extractant, producing a high-purity copper-loaded electrolyte for the electrowinning circuit and a raffinate solution returned to the leach pads. The EW circuit deposited copper from the rich electrolyte onto copper starter sheets to produce LME Grade A copper cathodes. The SX-EW plant was commissioned in May 1986 with rated cathode capacity of 25,000 st/y at 20 A/ft² but was expanded in 1988 to 50,000 st/y when the ISL streams were added.

The gold cyanidation plant processed Mo-plant final concentrate to recover Au, Ag, and 20% to 30% of the contained Cu. In June 1974, the plant processed 12.2 st/d of Mo concentrate at 0.462 oz Au/short ton, achieving 87% Au extraction by assay and 95% by independent gold balance. Annualized Au production was approximately 1,950 oz/y.

Additional Interesting Data and Summary

Historical mill capacity evolved from 30,000 stpd in September 1955 to a peak rated capacity of 66,000 stpd in 1982. In 1991 and H1 1992 average operating throughput was approximately 55,685 stpd, running at approximately 89% of nameplate. Life-of-mine ore milled totaled 703,686,000 st of sulfide ore at an average feed of 0.66% Cu and approximately 0.03% MoS₂.

The concentrator processed two parallel feed streams: the ROM ore stream at approximately 52,000 mt/d at 0.63% Cu feed grade, and the slag retreatment circuit at 2,200 mt/d of smelter slag at approximately 3% Cu feed. The ROM final flotation tailings grade reached a low of 0.076% Cu in 1990. A ROM head-to-tails balance does not reconcile to the 89.5% recovery figure because that value also captures Cu recovered from smelter slag and returned to smelter feed.

For the heap leach, cumulative ASCu leach extraction from ore into PLS progressed from 73% around 1993 to 88.3% at the end of leaching in 2002. The 1995 to 2002 increase was achieved through residual leaching with controlled surface, side slope, and berm-walled sprinkler-cell irrigation described as rice-paddy irrigation. The LoM heap cathode production was approximately 345,000 st. A 35-ppm cationic fluorochemical surfactant was added to the barren leach during preconditioning from June 1992 onward as standard practice, following a test program that demonstrated cumulative ASCu extraction above 73% with the surfactant versus 63% without.

For in situ leaching, Sutton reconciled the BHP block-model ASCu against cathode-equivalent Cu produced for Zone 6, resulting in cumulative ASCu extraction at zone closure of 41.7%, against a BHP 1999 internal forecast of 52%. The difference was attributed to faulting, block-cave-induced ground subsidence, channeling, and gypsum precipitation in fractures. Sutton revised the estimate to 55% sweep times 90% leachability equals 50% ASCu extraction with continued operation. A Resource Recovery Test from 1992 to 1993, a controlled 551-day well-to-well test, produced 1 million kg of Cu where ASCu extraction was 45.5% in the footwall cell to 64.6% in the hanging-wall cell.

The SX-EW plant achieved COMEX certification in August 1991 and LME Grade A listing in April 1992, the second SX-EW product ever LME-certified. Peak annual production was 124 Mlb in 1993 from heap plus ISL feed. The theoretical maximum at full rectifier capacity and 93% current efficiency was 143 Mlb/y.

Key Processes

  • Sulfide ore processing: two-stage crushing, rod and ball mill grinding, bulk Cu-Mo flotation, Mo recovery, smelting, and electrolytic refining.
  • Oxide ore processing: run-of-mine heap leaching with dilute sulfuric acid, no crushing or agglomeration.
  • Secondary sulfide processing: in situ leaching through surface-to-underground gravity flow and well-to-well modes.
  • Solution processing: solvent extraction with oxime-based extractant followed by electrowinning to LME Grade A cathode.
  • By-product recovery: gold cyanidation plant processing Mo-plant final concentrate.
  • On-site sulfuric acid production from smelter SO₂ off-gas supplying both market sales and SX-EW raffinate make-up.

Source: Technical Report San Manuel Property Pinal County, Arizona, July 29, 2026. Project website: San Manuel Property

Mineral processing basics

Scroll to Top