Tuvatu 2024 Report Describes a 300 t/d Pilot Plant With Two-Stage Grinding, Two-Stage Gravity, Intensive Leaching and CIL, and Dry-Stacked Filtered Tailings

Lion One Metals' 2024 technical report for the Tuvatu gold project on Viti Levu, Fiji, describes the operating pilot plant. It has at times run above 500 t/d, with gold recovery from 65% to almost 93% depending on feed.

The NI 43-101 Technical Report and Mineral Resource Estimate, Tuvatu Gold Project, Viti Levu, Republic of Fiji, was prepared for Lion One Metals Limited, with an effective date of June 24, 2024. Shandong Xinhai Mining Technology & Equipment designed and installed the pilot plant, covering flowsheet, mass balance, equipment sizing and layout. Sepro Mineral Systems designed and supplied the gravity concentration and recovery systems. Metallurgical testwork since 1996 showed that the Tuvatu mineralization suits two-stage gravity concentration and concentrate pre-treatment followed by cyanidation. Given the deposit's complexity, the plant was built to allow different recovery methods to be tested and to allow later expansion. It is designed for 300 t/d.

Critical Data

Parameter Value Unit Notes
Report effective date June 24, 2024 Not applicable For Lion One Metals Limited
Design throughput 300 t/d Not applicable At times over 500 t/d
Gold recovery 65 to almost 93 % Depends on feed source and plant configuration
Availability 90.4 % Milling and leaching 24 h/d
Primary crusher Metso Nordberg C96 jaw, 90 kW Not applicable P80 about 70 mm
Secondary crushing Cone in closed circuit with double-deck screen Not applicable P80 about 10 mm at 50 dt/h
Grinding Open-circuit primary and closed-circuit secondary ball mill Not applicable P80 60 to 65 µm at 300 t/d
Grind at higher rates P80 85 to 105 µm Above 300 t/d
Gravity Two batch centrifugal concentrators and a continuous concentrator Not applicable Sepro systems
Intensive leach Sepro Leach Reactor (SLR) Not applicable Separate atmospheric electrowinning cell
Leach CIL at about 45% solids Not applicable Air agitation and aeration
Cyanide destruction SO2/air to below 1 ppm WAD Not applicable Ahead of tailings filtration
Tailings Filtered and trucked Not applicable Dry stacked at the TSF

Overview

Underground ore is crushed in two stages and ground in an open-circuit primary ball mill and a secondary ball mill closed with cyclones. Both mills discharge into a common pump box. A screen and two batch centrifugal concentrators recover free gold from the mill discharge. That concentrate is leached in the Sepro Leach Reactor, which replaced a Deister-style table used before the reactor was working. The circuit was designed for a continuous secondary concentrator on the cyclone overflow, with caustic pre-treatment of its concentrate. Cyclone overflow is thickened and leached in a carbon-in-leach (CIL) circuit. Loaded carbon is eluted, and gold is recovered in a heated, pressurized electrowinning circuit and smelted to doré in an electric furnace. Leach residue is detoxified, filtered and trucked to the tailings storage facility (TSF) for dry stacking.

Key Process Stages

Crushing. Run-of-mine ore is dumped directly or reclaimed by front-end loader into a hopper with a static grizzly and rock breaker. A vibrating grizzly feeder at 100 t/h feeds the jaw crusher. The secondary cone crusher runs in closed circuit with a double-deck screen. A metal detector and magnet protect it, and a second magnet was being added. Crushing runs on day shift, and on night shift as feed or sampling campaigns require.

Grinding. The primary mill runs in open circuit. The secondary mill takes the gravity screen oversize and cyclone underflow and grinds to P80 60 to 65 µm. A coarser grind at higher throughput gives better gravity recovery but lower CIL recovery.

Gravity and intensive leaching. The gravity screen underflow, about 100% of it, goes to the two batch concentrators. Their concentrate goes through a surge bin to the SLR, and its pregnant solution goes to a dedicated electrowinning cell. The continuous concentrator had mechanical, electrical and control problems and was bypassed, so cyclone overflow went straight to the leach feed thickener. Upgrades were under way to restore the design flowsheet.

Concentrate regrind. A vertical regrind mill with integrated cyclones was bought but not installed. Laboratory tests showed only 1 to 2% more gold recovery from regrinding to P80 about 20 µm, and periodic tests continue.

CIL and gold recovery. The thickened slurry is leached in mechanically agitated, air-sparged CIL tanks. Loaded carbon is eluted, and stripping and electrowinning run in closed circuit. One cycle takes about 24 hours to produce sludge for the doré furnace. Stripped carbon is acid washed and/or thermally regenerated, and new carbon is attrited and sized.

Cyanide destruction and tailings. The SO2/air process brings WAD cyanide below 1 ppm. The tailings are then filtered and trucked to the TSF for dry stacking.

Additional Interesting Data and Summary

The two-stage gravity circuit, with intensive cyanidation of the primary concentrate, is integrated with the secondary mill to capture coarse free gold.

In summary, the 2024 Tuvatu report covers a small, flexible gold pilot plant that combines two-stage gravity concentration and intensive leaching with CIL. Its recovery depends on feed source and grind, and its filtered, detoxified tailings are dry stacked.

Key Processes

  • Jaw and cone crushing to P80 10 mm
  • Two-stage ball milling to P80 60 to 65 µm
  • Batch and continuous centrifugal gravity concentration
  • Intensive cyanide leaching of gravity concentrate
  • Caustic pre-treatment of secondary gravity concentrate (as designed)
  • Leach thickening and carbon-in-leach
  • Elution, pressurized electrowinning and electric furnace smelting to doré
  • SO2/air cyanide destruction, tailings filtration and dry stacking

Source: NI 43-101 Technical Report and Mineral Resource Estimate, Tuvatu Gold Project, Viti Levu, Republic of Fiji, for Lion One Metals Limited, effective date June 24, 2024.

Earlier report summaries

Earlier versions of this profile, based on older technical reports, are retained below for source traceability. Dates and figures reflect each report’s own effective date and are superseded by the current information above.

Tuvatu Gold Project — 2015 Preliminary Economic Assessment

This report describes the proposed processing facility for the Tuvatu gold project, based on a flotation and carbon-in-leach flowsheet designed for 219,000 tonnes per annum.

Report context

The Tuvatu Gold Project Preliminary Economic Assessment technical report, dated June 2015, was prepared for Lion One Metals Limited. Section 17 of the report describes the proposed recovery methods and processing facility design for the project, with a nominal capacity of 219,000 tonnes per annum at a design rate of 600 tonnes per day, based on 91% overall availability and a life-of-mine average feed grade of 11.3 g/t Au. The plant is designed to operate 365 days per year, 24 hours per day.

Processing route

Crushing circuit

The proposed flowsheet commences with a secondary crushing system designed for 1,000 tonnes per day, operating 24 hours per day at 75% overall system mechanical availability. The crushing system is sized at this capacity to allow for potential day-shift-only operation, over-crushing prior to relines, or future expansion. The report notes that the crushing index is based on a single test and feed size is assumed. The circuit was simulated using PlantDesigner and Bruno simulation software, but the report cautions that due to hardness and equipment specifications, a tertiary crushing circuit may be required in practice to achieve necessary size reduction.

Mineralized material from underground mining feeds a vibrating grizzly and primary jaw crusher system in open circuit, producing a product size (P80) of 105 mm, with a top size of 600 mm assumed from the underground mine. The secondary screen is an inclined, dual-deck vibrating screen with 50 mm and 15 mm openings on upper and lower panels respectively. Oversize from both screen decks reports to a secondary cone crusher in closed circuit with the secondary screen. The cone crusher has a maximum motor power of 250 kW and a closed side setting range from 10 to 25 mm depending on mantle profile. Undersized material is conveyed to a covered stockpile with 600 tonnes live capacity, supporting 24 hours of process plant operations when the crushing plant is not operating.

Grinding circuit

The grinding circuit consists of an open circuit primary ball mill and a secondary ball mill with gravity circuit in closed circuit with hydrocyclones. The circuit operates at 91% mechanical availability with annual throughput of 219,000 tonnes. Mill sizing was calculated based on the 75th percentile of Bond Work test results. The report recommends additional work in the next engineering phase to confirm hardness indices and mill sizing parameters.

Both ball mills are identical, with a diameter of 3.0 m and effective grinding length of 4.6 m, each equipped with a 522 kW motor. The estimated power draw range for both mills is 425 to 450 kW. The ball mill hydrocyclone cluster classifies feed slurry, with coarse underflow feeding the secondary ball mill or a gravity separation circuit. Cyclones are designed with 300% recirculating load. Cyclone overflow at 80% passing 75 µm flows by gravity to the flotation circuit.

A single gravity concentrator treats approximately 25% of the cyclone underflow. Testwork indicates approximately 38% of gold will be recovered to a gravity concentrate, which reports to a concentrating table for further upgrading and direct smelting to doré.

Flotation circuit

The flotation circuit was sized based on testwork performed by METCON and AMMTEC. A scale-up factor of 2.5 was applied to the flotation time used for cell sizing, within the common range of 2 to 3 for sulphide rougher flotation. The circuit comprises a conditioning tank with 12 minutes conditioning time and a single bank of six 10 m³ self-aspirating flotation cells arranged in series.

The material floats at natural pH of approximately 7.6. Potassium amyl xanthate (PAX) is added as collecting agent, and a frother is added as needed. Flotation concentrate overflows to a trash screen and then to the flotation concentrate thickener. Flotation tailings report to the flotation tailings thickener.

Regrinding and carbon-in-leach circuits

Float concentrate thickened underflow proceeds to the regrind circuit. Testwork indicates regrinding to 20 µm P80 or less is necessary to extract precious metals from the sulphide concentrate. The flowsheet proposes a stirred mill circuit for regrinding. The target regrind size is 80% passing 20 microns, though the report notes mineralogy indicates the regrind size may need to be finer and additional studies are required.

After regrinding, slurry reports to the float concentrate CIL circuit. Both the float concentrate CIL and float tails CIL circuits use six tanks in a single train, providing 24 hours of leaching. Slaked lime slurry maintains pH at 11.0 to prevent hydrogen cyanide gas evolution. Oxygen is sparged in the float concentrate CIL tanks at approximately 0.05 Nm³/h/m³, while process air is added to the float tails CIL tanks. Float concentrate CIL tailings report to the float tails CIL circuit for additional precious metal recovery.

Cyanide detoxification

Combined leached flotation tailings report to cyanide destruction using the SO₂/Air process with copper sulphate addition, targeting less than 1 ppm CN WAD in the discharge solution. Un-optimized detoxification testwork indicates the process can reduce residual cyanide to less than 2 ppm CN WAD. The report recommends a trade-off study for a cyanide recovery thickener prior to detoxification in the next phase.

Adsorption, desorption, and refining

Loaded carbon from the CIL circuits is pumped to the ADR plant. Carbon is acid washed with hydrochloric acid to remove calcium deposits, iron particles, silica, magnesium, and sodium salts. Elution uses a solution of approximately 1% sodium hydroxide and 0.1 to 0.2% sodium cyanide at 138 to 140 °C and 450 kPa, circulated at approximately 2.0 bed volumes per hour.

Pregnant solution passes through heat exchangers to the gold room for electrowinning, producing gold sludge. Sludge is filtered, dried, mixed with fluxes, and smelted in a diesel-powered direct fire furnace to produce gold doré. Stripped carbon is thermally regenerated in a diesel-fired horizontal kiln.

Key reported parameters

Parameter Units Design Value Basis
Plant nominal capacity tpa 219,000 Design
Plant design rate tpd 600 Design
Overall plant availability % 91 Design
Life-of-mine average feed grade g/t Au 11.3 Design
ROM moisture % 5.0 Testwork
Bulk density t/m³ 1.6 Testwork
Bond Ball Mill Work Index (BWi, 75th) kWh/t 18.6 Testwork
Bond Rod Mill Work Index (RWi, 75th) kWh/t 19.8 Testwork
Crushing Work Index (CWi) kWh/t 12.5 Testwork
Crushing availability % 75 Design
Crushing throughput tpd 1,000 Design
Primary crusher product size (P80) mm 105 Design
Secondary crusher product size (P80) mm 30 Design
Primary grinding product size (P80) µm 1,000 Design
Secondary grinding product size (P80) µm 75 Design
Regrind product size (P80) µm 20 Design
Gravity recovery to concentrate % 38 Testwork
Flotation mass recovery % of feed 20.0 Design
CIL retention time (both circuits) h 24 Design
Carbon concentration in CIL g/L 20.0 Design
Gold recovery to bullion (LOM) % 86.3 Design estimate
Cyanide detoxification target CN WAD ppm 1 Design

Project website: https://liononemetals.com/

Technical qualifications

The report states that at the preliminary level of this study, testwork results, industry data, and assumptions have been used to make reasonable estimates for equipment sizing, which will be reviewed in the next engineering phase. Caution is advised regarding crushing plant sizing, as the crushing index is based on a single test and feed size is assumed; a tertiary crushing circuit may be required in practice. Mill sizing is based on the 75th percentile of Bond Work test results, and additional work is recommended to confirm hardness indices. Flotation testwork is preliminary, with a scale-up factor of 2.5 applied. Un-optimized detoxification testwork has been performed. The report recommends including metallurgical samples from the first three years of operation in future testwork programs to better define precious metal recoveries.

Source: *Tuvatu Gold Project , Preliminary Economic Assessment*, National Instrument 43-101 Technical Report, Lion One Metals Limited, June 2015, Sections 17.0 to 17.10, 26.0 and 27.0.

Mineral processing basics

Scroll to Top