Arthur Gold Project — NI 43-101 Technical Report

Company: AngloGold Ashanti
Effective Date: 31 December 2025
Report Type: Pre-Feasibility Study
Location: Nevada, USA

Executive Summary

The Arthur Gold Project, centered on the Merlin deposit, is a gold-silver project located in Nevada, USA. The project employs a dual-processing strategy utilizing both conventional milling with carbon-in-leach (CIL) cyanidation and heap leaching with carbon-in-column (CIC) technology. The processing methods were selected based on ore characteristics, with higher-grade materials routed to the milling circuit and lower-grade materials processed via heap leach. The Merlin ore is strongly oxidised with gold recoveries increasing with decreasing feed size. Significant gravity-recoverable gold is present in higher-grade zones, with gravity circuit testwork indicating recovery of up to 50% of contained gold.

The mill process plant is designed for 7,000,000 t/a throughput, utilizing a three-stage crushing circuit (Gyratory-Cone-HPGR) followed by a single large ball mill (8.28 m diameter x 12.8 m EGL, 18,400 kW) operating in closed circuit with hydrocyclones. The grinding circuit produces a P80 of 106µm. The CIL circuit consists of 16 tanks across two parallel trains with carbon concentration maintained at 15g/L. Gold and silver are recovered through pressure Zadra elution, electrowinning, and smelting to produce doré bars. The heap leach operation processes 5,500,000 t/a through similar crushing, with ore agglomerated using cement before stacking on a lined pad. Pregnant solution is processed through vertical CIC units before transfer to the centralized ADR plant.

Processing Details

Mill Process Plant (7 Mt/a)

  • Crushing: Three-stage (Gyratory-Cone-HPGR)
  • Primary: 42×65 gyratory crusher (373 kW)
  • Secondary: MP1000 cone crusher (746 kW)
  • Tertiary: HRC2000e HPGR (4,040 kW)
  • Grinding: Single ball mill (8.28m x 12.8m EGL, 18,400 kW) with hydrocyclones
  • Gravity: Centrifugal concentrators with intensive leach reactor (ILR)
  • Leaching: 16-tank CIL circuit (2 parallel trains)
  • Elution: Pressure Zadra process
  • Gold Recovery: Electrowinning and smelting to doré

Heap Leach Operation (5.5 Mt/a)

  • Crushing: Three-stage (Gyratory-Cone-HPGR)
  • Agglomeration: Drum agglomerator with cement
  • Leaching: 65-day average leach cycle
  • Adsorption: Vertical CIC units
  • Solution Application: Drip emitters on lined heap pad

Key Parameters

  • Mill Throughput: 19,178 t/d (design)
  • Heap Leach Throughput: 15,068 t/d
  • Mine Life: LOM production of 4,526,000 oz Au and 1,466,000 oz Ag
  • Tailings: Filtered and dry-stacked (filtered TSF)

References

  • NI 43-101 Technical Report, Effective Date: 31 December 2025

Website: https://www.anglogoldashanti.com/portfolio/americas/united-states-projects/

Report Date: 2025

Region: Nevada

Consolidated report summaries

The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.

Gold Recovery Methods at Arthur Gold Project – Milling & Heap Leach

Gold Recovery Methods at Arthur Gold Project – Milling & Heap Leach

Source: Unnamed_Company_44 (2026)
Website: https://www.anglogoldashanti.com/portfolio/americas/united-states-projects/

Critical Data

Parameter Value Unit Notes
Throughput 1,065 t/h Mill design throughput (nominal 19,178 t/d)
Throughput 15,068 t/d Heap leach design throughput (5.5 Mt/a)
Mill Power 18,400 kW Installed ball mill motor power
Target Grind Size 106 μm P80 for hydrocyclone overflow (mill circuit)
Head Grade Not specified in Section 17
Recovery % Up to 50 % Gravity gold recovery; overall CIL recovery pending testwork
Processing Capacity 7,000,000 / 5,500,000 t/a Mill / Heap leach annual capacity
Energy Consumption kWh/t Not specified in Section 17
Water Consumption m³/t Not specified in Section 17
Operating Hours 24 hours/day Both mill and heap leach circuits designed for 24 h/d operation

Overview

AngloGold Ashanti’s Arthur Gold Project in Nevada, USA, employs a dual processing strategy to maximize gold recovery from the Merlin and Silicon deposits. The pre-feasibility study, effective 31 December 2025, outlines two complementary recovery methods: a milling circuit with gravity concentration and carbon-in-leach (CIL) for higher-grade ore, and a heap leach operation for lower-grade material. This approach lowers the economic cut-off grade and enhances overall project profitability. The mill processes 7 million tonnes per year through three-stage crushing (gyratory, cone, HPGR) followed by a single large ball mill in closed circuit with hydrocyclones. Gravity recovery captures up to 50% of contained gold, with the balance recovered via CIL and pressure Zadra elution. The heap leach operation handles 5.5 million tonnes per year, employing similar crushing stages, agglomeration, and cyanide percolation through stacked ore, with gold recovered in vertical carbon-in-column (CIC) circuits. Both technologies are well-proven in the region and globally, with no novel processes required. The facility is designed for 24-hour operation with high availability, and tailings are filtered and dry-stacked to meet stringent environmental and safety standards.

Key Process Stages

  • Stage 1: Comminution – Three-stage crushing uses a 42×65 gyratory crusher (373 kW), an MP1000 cone crusher (746 kW), and an HRC2000e HPGR (4,040 kW) to reduce feed to a P80 of 3.1 mm for the mill circuit. Coarse and fine ore stockpiles decouple crushing from grinding.
  • Stage 2: Grinding and Classification – A single 8.28 m diameter × 12.8 m EGL ball mill (18,400 kW) operates in closed circuit with a 20-inch cyclone cluster (22 cyclones). The hydrocyclone overflow achieves a P80 of 106 µm and reports to the pre-leach thickener.
  • Stage 3: Gravity Concentration and Intensive Leach – Fresh feed diverted to centrifugal concentrators recovers gold in semi-continuous mode. Concentrate is transferred to an intensive leach reactor (ILR) for cyanidation; pregnant solution is sent to a dedicated electrowinning cell. Gravity tails return to the grinding circuit.
  • Stage 4: Carbon-in-Leach (CIL) Circuit – Thickened slurry (50% solids) feeds two parallel CIL trains (each with 8 tanks). Oxygen sparging maintains 20 ppm dissolved oxygen, milk of lime controls pH to 11, and sodium cyanide is added via a ring main. Carbon concentration is 15 g/L, and loaded carbon is advanced counter-currently.
  • Stage 5: Elution, Electrowinning, and Gold Room – Loaded carbon undergoes acid wash (3% HCl) followed by Pressure Zadra elution at ≥145°C and 400 kPag. Pregnant solution feeds four electrowinning cells; gold sludge is filtered, dried, fluxed, and smelted in an electric furnace to produce doré bars. Carbon is regenerated in a rotary kiln at 700–750°C.

Additional Interesting Data and Summary

The Arthur Gold Project’s recovery methods are supported by extensive metallurgical testwork confirming high gold recoveries for both milling and heap leaching. For the mill circuit, the 18.4 MW ball mill with a 300% recirculating load ensures efficient grinding. The gravity circuit captures up to 50% of gold, reducing downstream cyanide consumption. The CIL circuit (16 tanks total in two trains) operates at 50% solids with a carbon inventory of 15 g/L. The pressure Zadra elution system processes two 12t carbon columns per batch, with a strip solution of 1.5% NaOH and 0.2% NaCN at ≥145°C. Electrowinning uses four cells in two parallel trains plus a dedicated cell for ILR pregnant solution. Gold is smelted into doré bars at five smelts per week. Tailings are filtered to 85% solids and dry-stacked in a filtered TSF with a starter dam and toe buttress designed per GISTM standards. The heap leach operation agglomerates HPGR-crushed ore with cement and barren solution before stacking via grasshoppers and a radial stacker. Barren solution (cyanide) is applied via drip emitters; pregnant solution is collected and processed through vertical CICs for gold and silver adsorption. Loaded carbon from the heap leach is transported to the shared ADR plant for elution and electrowinning. Environmental controls include a mercury scrubber on the carbon regeneration kiln, acid-proof bunds, and a comprehensive water management system. The filtered TSF features engineered drainage, seepage collection ponds, and a geotechnical investigation confirming site suitability. The project’s dual-circuit approach reduces the cut-off grade, maximizes resource utilization, and aligns with sustainability goals through dry tailings and water recycling. The pre-feasibility study anticipates a 24-hour operation with 92% mill availability and 75–88% crushing availability, ensuring robust annual throughput. Future studies will refine design criteria and optimize reagent consumptions based on pilot-scale column leach results and comminution data.


Key Processes: Flotation, CIP/CIL, Heap Leaching, Cyanidation, Gravity Separation, SAG Mill, Ball Mill, Crushing

Target Commodities: Gold, Silver, Copper, Zinc, Lead

Mineral processing basics

Scroll to Top