Bibiani Plant Evolution: Sulphide Circuit Commissioned, Crusher Expansion on Schedule

Figure 17-6: Schematic Flowsheet of the Flotation Circuit and Concentrate Regrind

Asante Gold's Bibiani plant in Ghana has commissioned a new sulphide treatment circuit and is advancing a three-stage crusher expansion designed to lift throughput to 4.5 Mtpa.

The Bibiani Gold Project is an operating mine located in Ghana, West Africa, owned by Asante Gold Corporation. The processing facility, known as the Bibiani Plant, currently operates with a nominal design capacity of 2.4 Mtpa, employing a SAG/ball mill comminution circuit followed by a conventional carbon-in-leach (CIL) process for gold extraction. The operation was re-commissioned in June 2022 after a refurbishment period, and the most recent major modification was the commissioning of a sulphide treatment plant in Q4 2025, which was added to process gold from sulphide ores. Further modifications to the crushing, gravity, and leaching circuits are scheduled for 2026 to increase throughput capacity and improve recovery.

Critical Data

Parameter Value Unit Notes
Plant Design Throughput 2.4 Mtpa Original plant design; current operational capacity.
Future Plant Throughput 4.5 Mtpa Design capacity for the System 3 crusher plant.
Average Monthly Throughput (2023) 191 ktpm Plant performance data.
Average Monthly Throughput (2024) 195 ktpm Plant performance data.
Average Monthly Throughput (2025 YTD) 190 ktpm Plant performance data.
Design Plant Throughput 200 ktpm Design nameplate capacity for monthly throughput.
Crusher Plant Availability (Design) 91.3 % Lycopodium 1997 Process Design Criteria.
Milling Plant Availability (Design) 91.3 % Lycopodium 1997 Process Design Criteria.
Average Crusher Plant Effective Utilisation (2025) 29.13 % Plant performance data.
Average Milling Plant Effective Utilisation (2025) 79.56 % Plant performance data.
Cyclone Overflow Size, P80 75 µm Mill product size target.
Gold Head Grade (Design) 3.90 g/t Au Lycopodium 1997 Process Design Criteria.
Gravity Gold Recovery (Design) 31.0 % Lycopodium 1997 Process Design Criteria.
Leaching Gold Recovery (Design) 87.0 % Without gravity, Lycopodium 1997 Process Design Criteria.
Sulphide Treatment Plant Throughput 0.35 Mtpa Design capacity as concentrate feed.
Flotation Au Recovery (Design) 89.6 % Phase 1B Process Design Criteria.
Concentrate Leach Au Dissolution (Design) 88.4 % Phase 1B Process Design Criteria.
System 3 Crusher Plant Availability 91.3 % Design criterion for new crusher plant.

Overview

The Bibiani processing facility is a conventional gold plant that has been adapted to handle increasingly complex ore feed. The original design, established in 1997 by Lycopodium, featured a SAG mill and ball mill circuit with a standard CIL plant for gold recovery. Under Asante Gold's management, the plant was refurbished in Q3 2021, which included adding a gravity concentration circuit and re-conditioning the primary gyratory crusher. The plant was re-commissioned in June 2022.

Operational data from 2023 through 2025 shows the plant has consistently operated below its design throughput of 200 ktpm, with average monthly throughput of 191 ktpm, 195 ktpm, and 190 ktpm, respectively. The 2025 year-to-date figures extend through October 2025. Plant availability and utilisation are key constraints, with crusher and milling effective utilisations averaging 29.13% and 79.56% respectively in 2025, both below industry standards. Grid power supply interruptions are cited as the major cause of mill downtime, combined with primary gyratory crusher mechanical failures and the absence of surge capacity between the crusher and the mill.

The plant's response to these challenges has been a phased modification program. The first major change was the commissioning of the sulphide treatment plant in Q4 2025, followed by the construction of a new three-stage crusher plant (System 3) scheduled for 2026. Future upgrades to the gravity circuit and CIL plant are also planned.

Key Process Stages

The existing plant processes ore through a re-conditioned FLS 42 x 70 gyratory crusher for primary crushing. The crushed ore feeds a primary SAG mill and a secondary ball mill with classification hydrocyclones. A gravity concentration circuit using one Knelson XD48 concentrator and a Gekko ILR captures coarse gold, with the balance of the ore reporting to the conventional CIL circuit. The CIL section is followed by carbon elution and regeneration, a gold room with electrowinning, and reagent mixing.

The new sulphide treatment circuit, commissioned in October 2025, is designed to extract gold from sulphide ores. The circuit consists of scavenger flotation on the mill product stream, followed by ultra-fine regrinding of the concentrates in a vertical mill using ceramic media. Concentrate thickening is followed by intensive cyanidation in separate tank stages. The leached concentrate reports to carbon-in-pulp contactor tanks, with reagents mixed on site.

The future System 3 crusher plant is designed to replace the mobile crushers currently in use and to provide additional comminution capacity. The plant will feature a primary jaw crusher fed by a vibrating grizzly feeder, a secondary cone crusher, and tertiary crushers including two impactors and a cone crusher in closed circuit with screens. The system will produce a feed size of 100% passing 33 mm to the SAG mill, which is expected to support a throughput of 4.5 Mtpa. The current mill throughput from the mobile crushers is 400 tph, with simulations indicating that a feed size of 80% passing 25 mm would achieve the 4 Mtpa target.

Additional Interesting Data and Summary

Design criteria from the original Lycopodium 1997 work show a design head grade of 3.90 g/t Au and expected leach gold recovery of 87% without the gravity circuit. The existing plant design assumes a cyclone overflow P80 of 75 µm, a leach time of 24 hours, and a leach tails solution grade of 0.010 g/m³ Au. The design sodium cyanide addition is 0.75 kg/t material, and lime addition is 0.50 kg/t material.

The Phase 1B sulphide treatment design includes a flotation residence time of 15 minutes and a design mass pull of 8%. The intense leach circuit is designed for a pre-oxidation residence time of 1.5 hours at 20 ppm dissolved oxygen, followed by a cyanide leach residence time of 4.8 hours. The design concentrate gold dissolution is 88.4%, with carbon loadings of 1,000 g/t in the adsorption circuit.

Mill power consumption varies with the ore blend. Blends with a higher proportion of softer oxide ore consume less than 18 kWh/t. As the fresh ore proportion increases, power consumption rises to over 20 kWh/t, peaking at 24 kWh/t. This higher energy demand reduces milling throughput when targeting the P80 of 75 µm.

Operational data from February 2025 to October 2025 shows gold recovery fluctuated between approximately 75.8% and 78.9%. The head grade varied from 0.83 g/t to 1.41 g/t over the same period, with mill power ranging between 13.53 kWh/t and 23.75 kWh/t.

A notable operational constraint is the low crusher plant utilisation. The 2025 average was 29.13%, with several months recording zero utilisation. The report notes that mobile crushers have been used since October 2024 to maintain plant throughput above 150 ktpm.

The future modifications include a gravity circuit change in Q1 2026, with a new scalping screen on the cyclone underflow feed and a new additional Knelson concentrator. The CIL plant will also be modified in Q2 2026, converting the first CIL tank to a pre-leach tank and installing an Aachen shear reactor pumping system.

Key Processes

  • Comminution: Gyratory crusher for primary crushing, followed by SAG mill and ball mill with hydrocyclone classification.
  • Gravity Concentration: Knelson XD48 concentrator and Gekko ILR for gravity-recoverable gold.
  • Flotation: Scavenger flotation cells on the mill product stream for sulphide ore treatment.
  • Ultra-fine Regrinding: Vertical mill using ceramic media for scavenger concentrates.
  • Intensive Cyanidation: Shear reactor pre-oxidation and pre-leaching stages followed by carbon-in-pulp contactors.
  • Carbon-in-Leach: Conventional CIL circuit for gold leaching and adsorption.
  • Elution and Regeneration: Carbon stripping and regeneration for cyanide recovery.
  • Electrowinning: Gold recovery from concentrated solutions in the gold room.

Source: NI 43-101 Technical Report and Updated Mineral Resource Estimate, Asante Gold Bibiani Ltd., Ghana, West Africa, 31 December 2025. Project website: Bibiani Gold Project

Mineral processing basics

Scroll to Top