Commonwealth Silver and Gold Project — 2014 Technical Report

Company Commonwealth Silver and Gold Mining Inc.
Date 2014-04-30
Region Unknown
Commodities Gold, Silver
Mine Type Open Pit
Throughput N/A
Mine Life 6 years
Annual Production N/A
Status Development

Executive Summary

This NI 43-101 Technical Report outlines the processing scheme for the Commonwealth Silver and Gold Project. Based on extensive metallurgical test work, the selected method is a crush, heap leach, and Merrill-Crowe recovery process. The project involves a three-stage crushing circuit designed to handle different mineralized materials with varying crush size sensitivities.

The crushing circuit utilizes a primary jaw crusher, a secondary cone crusher, and two tertiary cone crushers. Material is crushed to either 80% passing 1/2 inch or 1/8 inch depending on the rock type (Andesite/Bisbee vs. Rhyolite/Vein). Agglomeration is performed using lime and cement on conveyors downstream of the tertiary crusher.

Heap leaching is conducted using sodium cyanide solution, with pregnant leachate pumped to a Merrill-Crowe plant for gold and silver recovery. The final precipitate is shipped to a refiner for production. The leach pad is designed for an initial 1.5 years of production with expansions planned for the second and sixth years.

Processing Profile

Reports

Website: https://cambridgehouse.com/company/1602/commonwealth-silver-and-gold-mining-inc

Report Date: 2014-04-30

Region: Unknown

Project Status: Development

Commodity: Gold, Silver

Throughput: N/A

Mine Life: 6 years

Mine Type: Open Pit

Ore type: 