Kalana Mineral Resource Estimate and PEA

The Kalana project proposes a new 1.2 Mtpa gravity and carbon-in-leach processing plant to treat saprolite and fresh rock, supported by metallurgical testwork and historical operating data from the existing 60,000 tpa plant.

Report context

The Kalana Mineral Resource Estimate and Preliminary Economic Assessment (PEA), dated 31 March 2014, includes a processing route based on metallurgical test work completed by a range of reputable laboratories, the history of gold plant operations at Kalana, and benchmarking against similar gold operations and projects in West Africa. The existing gold plant at Kalana has a capacity of 60,000 tonnes per year and uses crushing, milling and gravity concentration to recover gold from high grade quartz ores mined from underground. The existing plant is located within the footprint of the proposed open pit.

Processing route

Overview

It is proposed to construct a new process plant with a capacity of 1.2 million tonnes per year of saprolite and fresh rock to recover gold by gravity and carbon in leach (CIL) technology. The gold mineralisation is present in the weathered saprolite to a depth of about 80 m and in fresh rock. It is also proposed that the leaching and gold elution sections of the new process plant will be constructed to enable processing of the tailings resource to be completed prior to the commissioning of the crushing and milling circuits.

Crushing and ore stockpiling

It is proposed that a scrubber will be used to remove clay and fine material from saprolite ore before crushing. The primary jaw crusher will produce a product size of 100% passing 240 mm. The crushed ore stockpile would have a capacity of about 5,000 tonnes.

Milling and classification

It is currently proposed that the milling circuit will include a SAG mill, ball mill and pebble crusher; however no detailed work has been completed to design the SAG mill. The circuit is expected to produce a particle feed size to the CIL of 80% passing 75 micron. Preliminary test has not identified potential viscosity issues but more detailed test work is required. It is proposed that the gravity gold will be recovered by Knelson concentrators, which is the same process used in the existing plant.

Carbon in leach

There is no presence of preg-robbing materials. Tests have shown addition of oxygen has some benefit and it is proposed to introduce oxygen to the tanks prior to cyanide leaching. Leach tests have shown that 30 hours residence time is appropriate. The plant will require a cyanide detoxification process. No test work has been completed to assess the optimum plant.

Flotation potential

There is potential to introduce flotation into the recovery process after recovery by gravity concentration. Test work on underground mineralisation indicates that 85% of the gold in the gravity tailings can be recovered in 10% of the mass, resulting in a potential reduction in the cost of reagents and a smaller plant footprint. Further test work is required to demonstrate the viability of including flotation in the process design. A flotation circuit has not been included in the capital estimates. Test work has shown potential benefits of a flotation circuit for fresh ore and possibly oxides.

Elution and gold recovery

It is assumed that a standard AARL method will be used for elution and a kiln used for carbon regeneration. Standard electro-winning cells will be used for recovering gold from pregnant eluate. An electric furnace will be used for smelting.

Consumables and services

The main consumables are cyanide and lime. Metallurgical tests have shown consumption to be acceptable within normal gold operations. Storage will be to internationally acceptable standards. It is assumed that an oxygen plant will be required to provide the required quantity of oxygen; however the actual quantity required has not been estimated. The capital estimate allows for two compressors, one operational and one standby. Water supply to the existing gold plant is supplied from underground water pumping and it is understood that excess water will be available from the same source, with pumping from boreholes. There will be an added benefit of dewatering the pit ahead of mining. Potable water is available on site but will require purification.

Key reported parameters

Parameter Value Basis
Existing plant capacity 60,000 tpa Historical operating data
Existing plant gravity recovery 80% to 90% since 2004 Historical operating data
Proposed new plant capacity 1.2 Mtpa saprolite and fresh rock Proposed design
Work index, saprolite 11 kWh/t Metallurgical test work and historic operations
Work index, fresh rock 17 kWh/t Metallurgical test work and historic operations
Gravity recoverable gold, saprolite and fresh rock 40% to 95% Metallurgical test work
Gravity recovery, underground mineralisation 80% to 92% Operating experience
Leach grind size, saprolite and fresh rock 80% passing 75 micron Cyanide leach test work
Leach grind size, tailings 80% passing 180 micron Cyanide leach test work
Tailings recovery 83% Assumed, no milling required
Gold recovery, oxide and fresh mineralisation 93% Assumed, based on 2013 results
Gravity and BLEG leach recovery on gravity tailings 94.2% SGS testwork, 2014
CIL residence time 30 hours Leach tests
Crushed ore product size 100% passing 240 mm Proposed design
Crushed ore stockpile capacity about 5,000 tonnes Proposed design
CIL feed size 80% passing 75 micron Expected circuit performance
Preg-robbing Not present Metallurgical tests
Flotation: gold recovered in gravity tailings 85% in 10% of mass Test work on underground mineralisation

Project website: https://www.endeavourmining.com/our-portfolio/projects/kalana/

Technical qualifications

The process description is based on metallurgical test work, historical operating data and benchmarking, with several elements remaining at a preliminary stage. Specific limitations identified in the report include:

  • No detailed work has been completed to design the SAG mill.
  • More detailed test work is required to confirm the absence of viscosity issues.
  • No test work has been completed to assess the optimum cyanide detoxification process.
  • Further test work is required to demonstrate the viability of including flotation in the process design.
  • A flotation circuit has not been included in the capital estimates.
  • The actual quantity of oxygen required has not been estimated.
  • The plant flow sheet and design is expected to be similar to many process plants world-wide, indicating a benchmarking approach rather than site-specific design.

Source: Avnel Gold Mining Limited, Kalana Mineral Resource Estimate and PEA, 31 March 2014, Section 17 Recovery methods.

Mineral processing basics

Scroll to Top