Kobada Gold Project — 2024 Technical Report
| Company | Kobada Gold Project |
| Date | 2024 |
| Region | Nigeria |
| Commodities | Gold |
| Mine Type | Open Pit |
| Throughput | 3 Mt/a |
| Mine Life | 16 years |
| Annual Production | 100,000 oz Au |
| Status | Development |
Executive Summary
The Kobada Gold Project Technical Report outlines the recovery methods for a processing plant designed to treat oxide ores initially, transitioning to sulphides as the mine life progresses. The plant utilizes a gravity/CIL technology with a throughput of 3 Mt/a. The process includes crushing, milling, gravity recovery of free gold, and Carbon-in-Leach (CIL) for the remaining gold. The design is phased, with the first phase treating oxides using a single-stage ball mill and primary crushing, and a second phase adding secondary crushing and milling for sulphides.
Processing Profile
- Crushing: Primary Jaw Crusher (Oxide), Secondary/Tertiary Cone (Sulphide)
- Milling: Ball Mill (Single stage Oxide, Two stage Sulphide)
- Gravity: Centrifugal Concentrator
- Leaching: Carbon-in-Leach (CIL), Intensive Cyanidation
Reports
Website: https://toubaniresources.com/project/
Report Date: 2024
Region: Nigeria
Project Status: Development
Commodity: Gold
Throughput: 3 Mt/a
Mine Life: 16 years
Mine Type: Open Pit
Ore type: