| Company | STARCORE International Mines Ltd. |
| Date | 2024 |
| Commodities | Gold, Silver |
| Status | Operating |
Executive Summary
This section of the NI 43-101 Technical Report details the recovery methods employed at the San Martin Mill. The facility utilizes a conventional cyanidation process combined with the Merrill Crowe recovery method. The mill has a rated capacity of 1,100 tpd, though current operations average around 650 tpd based on data from April 2017 to April 2024. During this period, the mill achieved average recoveries of 86% for gold and 55% for silver.
Metallurgical research is ongoing to improve gold and silver recovery, reduce process time, and lower costs. The current treatment time has been optimized to 35 hours through the addition of oxygen in the grinding area, which has reduced cyanide consumption. Recent tests have achieved 93% gold extraction using a new reagent mixture, pending validation. Additionally, the smelting area has been optimized to produce doré bars with 99.3% purity, reducing flux and crucible consumption.
The ore presents challenges due to refractoriness caused by carbonaceous material in some areas, with current extractions at 82% in those zones. A tailings filtration plant installed in 2005 supports dry handling and stacking, and the tailings dam is being reinforced to higher standards.
Website: https://starcore.com/en/operations/producing/gold-and-silver-in-queretaro/
Report Date: 2024
Project Status: Operating
Commodity: Gold, Silver
Consolidated report summaries
The following former standalone pages about this operation were consolidated here on October 25, 2026. They are retained for source traceability; dates and figures reflect each report’s own effective date and may be superseded by the current information above.
San Martin Mill — 2018 Technical Report
San Martin Mill — 2018 Technical Report
| Company | Not Specified |
| Date | 2018 |
| Region | Not Specified |
| Commodities | Gold, Silver |
Executive Summary
The San Martin Mill operates as a conventional cyanidation facility utilizing the Merrill Crowe recovery process. The mill has a rated capacity of 1,100 tpd, though operational data from April 2017 to April 2018 indicates an average throughput of 755 tpd. During this period, gold recovery averaged 88% and silver recovery averaged 55%.
The processing circuit includes two-stage fine crushing, two-stage grinding involving ball mills and a tower mill, followed by total ore cyanide leaching in a CCD circuit. Gold and silver are recovered via zinc precipitation and refined on-site to doré. Tailings management includes a filtration plant for dry handling and stacking, installed in 2005, with ongoing dam reinforcement.
Website: https://www.firstmajestic.com/projects/exploration-development/san-martin/
Report Date: 2018
Region: Not Specified
Project Status:
Commodity: Gold, Silver
Throughput:
Mine Life:
Mine Type:
Ore type: