Executive Summary
This technical report outlines the recovery methods for the Sandman Gold Property. Precious metal recovery is planned to utilize conventional heap leaching and adsorption, desorption, regeneration (ADR) technology for metal extraction from crushed product using industry standard equipment. Processing will involve mineralized material passing through a single stage of crushing, which will allow for haulage transport and end-dump stacking of the mineralized material onto a heap leach pad. The processing facilities accommodate a leachable tonnage of approximately 11Mt of product at a gold grade of 0.74g/t and a process rate of 6,000tpd or 2.2Mtpa.
The heap leach pad facilities have been located and designed with expandability for potential LOM production increases. Mineralized material will be delivered from the open pit to a stockpile adjacent to the crushing plant. The mineralized material will be fed to the crushing plant using a front-end loader and will be crushed and then transported to the heap leach pad via haul trucks.
The mineralized material will be stacked onto the heap using industry standard end-dumping and dozer pushing and then leached with a weak cyanide solution to extract the precious metal values. The gold will then be recovered from the pregnant solution in the carbon columns by adsorbing the dissolved gold onto activated carbon, which will be bagged and transported off-site to an external facility to extract gold from the loaded carbon. The doré will be sent to a contract refiner for final refining.
Website: https://borealismining.com/2025/03/borealis-announces-closing-of-gold-bull-resources-acquisition/
Report Date:
Region:
Project Status: Development (PEA)
Commodity: Gold
Throughput:
Mine Life:
Mine Type:
Ore type: