Caylloma Mine — 2023 Technical Report

This report describes the processing facilities at the Caylloma mine, which uses differential flotation to produce lead–silver and zinc concentrates.

Report context

This technical report is dated December 31, 2023, and covers the Caylloma Mine operations in the Caylloma District, Peru. The Bateas processing plant resumed operations in October 2006 treating 600 tpd of polymetallic mineral. Capacity increased progressively, reaching 1,300 tpd with installation of a 1.8 m by 2.4 m ball mill in 2009, and 1,500 tpd at the end of March 2016 with installation of two Derrick Stack Sizer vibrating wet screens.

Processing route

Crushing and milling circuits

The crushing circuit is fed from a 10,000 t capacity stockpile used for ore storage and blending. Feed enters a coarse hopper with 450 t active capacity and 30 cm separation grates. Material passes through an apron feeder to a vibrating grizzly, then to a Kurimoto jaw crusher producing a product size between 76 mm and 90 mm. Material is transported to a two-deck vibrating 6 by 14-foot (1.82 x 4.27 m) screen. Undersize (100% passing ¾ inch) goes to the stockpile; oversize feeds a Sandvik CH-420 secondary crusher. Secondary crusher product goes to a two-deck vibrating 5 by 14 foot (1.52 x 4.27 m) screen, with undersize feeding the stockpile and oversize feeding a Sandvik CH-430 tertiary crusher whose discharge returns to the initial conveyor belt to close the circuit. The actual capacity of this circuit is 1,800 tpd.

A standby primary crushing circuit exists, starting at a 100 t capacity coarse hopper feeding a Kueken 24 by 36-inch (0.6 x 0.9 m) jaw crusher via a Ross chain feeder. Three permanent magnets and one electromagnet on the conveyors prevent entry of tramp iron.

The grinding circuit has two stages. The primary stage operates in open circuit with two ball mills (Comesa 2.4 m by 3.0 m and a Denver 2.1 m by 2.1 m). The secondary stage operates in closed circuit with three ball mills: a Magensa 1.8 m by 1.8 m, a Hardinge 2.4 m by 0.9 m, and a Liberty 1.8 m by 2.4 m.

The Comesa and Denver primary mills discharge to a flash cell (SK 240). Flash cell concentrate goes to the lead thickener; tailings feed a 6 by 6-inch (15 x 15 cm) horizontal pump feeding the Derrick Stack Sizer. Undersize goes to flotation; oversize feeds the three secondary ball mills. Discharge from the Hardinge and Magensa mills feeds a 6 by 4 inch (15 x 10 cm) horizontal pump feeding the D-15 cyclone. Fine product from the cyclone goes to flotation; coarse product returns to the secondary ball mills. Discharge from the Liberty mill also feeds the flash cell (SK240). The final product of the grinding circuit is 55% passing 130 µm.

Metallurgical treatment

Treatment is via differential flotation, first floating lead–silver followed by zinc.

Lead–silver flotation circuit: D-15 cyclone overflow and Derrick Stack Sizer undersize feed a 10 m³ conditioner before entering a TC-20 unit cell of 20 m³ capacity. Unit cell tailings feed three TC-20 rougher cells. Unit cell and rougher concentrates feed primary cleaner cells (four 3 m³ OK-3 cells). Primary cleaner concentrate feeds secondary cleaner cells (three 3 m³ OK-3 cells). Secondary cleaner concentrate feeds tertiary cleaner cells (two 3 m³ OK-3 cells). Tertiary cleaner concentrate forms the final lead–silver concentrate. Rougher tailings feed scavenger flotation (two TC-20 cells). Scavenger concentrate and primary cleaner tailings return to the Derrick Stack Sizers. Scavenger tailings feed the zinc flotation circuit.

Zinc flotation circuit: Lead–silver flotation tailings go to three conditioners (two 10 m³ and one 22 m³). Conditioned pulp feeds zinc rougher flotation (two RCS 20 cells of 20 m³ and six 8 m³ OK8U cells in series). Rougher concentrate feeds a four-stage cleaner circuit: one RCS 10 cell of 10 m³, then five, three, and two 2.8 m³ Sub-A30 cells for primary, secondary, and tertiary cleaners respectively, with a fourth cleaning stage. Rougher tailings feed scavenger flotation (two 8 m³ OK8U cells). Scavenger tailings are the final tailings of the whole process.

Concentrates thickening and filtration

Lead–silver concentrate is thickened in an Outotec 9.0 m diameter thickener; underflow pumps to a 1.8 m diameter disc filter (six discs). Filtered lead concentrate contains on average 7.5% moisture. Zinc concentrate is thickened in an Outotec 12.0 m diameter thickener; underflow pumps to a 1.8 m diameter disc filter (eight discs). Filtered zinc concentrate contains on average 9.0% moisture. Each filtered concentrate is discharged into covered temporary storage for truck transport.

Tailings disposal

Tailings are classified through cyclones. Underflow (approximately 40% of tailings) is used as hydraulic backfill in the mine. Overflow is pumped to the tailings storage facility. Water from the tailings impoundment is pumped back to the plant for reuse. Usage of tailings storage facility N°3 commenced in January 2013; capacity was increased to 921,000 m³ in January 2022, sufficient for four years at current production levels, with further expansion planned in 2025.

Requirements for energy, water, and process materials

Electric power is supplied through the Callalli substation from the national grid. The whole operation requires 7.8 MW including 3.2 MW for the processing plant. Two diesel generators provide backup power. Processing plant water consumption is 2.45 m³/t, with approximately 74% (1.82 m³/t) recovered from the tailings facility and 26% (0.63 m³/t) fresh water. Reagents and consumables include sodium cyanide (10 g/t), copper sulphate (239 g/t), zinc sulfate (954 g/t), xantato Z-11 (6 g/t), xantato Z-6 (16 g/t), calcium oxide (483 g/t), foaming agent MC 5 (94 g/t), and steel balls (720 g/t).

Key reported parameters

Parameter Value Basis
Crushing circuit actual capacity 1,800 tpd Operating data
Grinding circuit final product fineness 55% passing 130 µm Design specification
Silver recovery (2022) 81.34% Historical operating data
Gold recovery (2022) 31.78% Historical operating data
Lead recovery (2022) 87.83% Historical operating data
Zinc recovery (2022) 88.75% Historical operating data
Historical achievable lead recovery 90% Historical operating data
Historical achievable silver recovery (in lead concentrate) 81% Historical operating data
Historical achievable zinc recovery 88% Historical operating data
Lead concentrate moisture 7.5% average Operating data
Zinc concentrate moisture 9.0% average Operating data
Tailings used as backfill Approximately 40% Operating data
Total power requirement 7.8 MW Design/operating
Processing plant power requirement 3.2 MW Design/operating
Plant water consumption 2.45 m³/t Operating data
Water recovered from tailings facility 1.82 m³/t (74%) Operating data
Fresh water consumption 0.63 m³/t (26%) Operating data
Tailings facility N°3 capacity (January 2022) 921,000 m³ Design/operating
Tailings facility N°3 life 4 years at current production Design estimate

Project website: https://fortunamining.com/

Technical qualifications

The report notes that the qualified person considers process requirements to be well understood and consistent based on actual observed conditions in the operating plant. There is no indication that the characteristics of the material being mined will change, with the expectation of the high zinc oxide material that has been accounted for, and therefore the recovery assumptions applied for future mining are considered reasonable for the life of mine. The plant is of conventional design and uses conventional consumables. The report notes that metallurgical recoveries of lead and zinc are affected due to the increase in treatment of oxidized ore to 11% due to its higher gold head grade. From late 2009 to January 2011, a copper–silver concentrate was produced, but due to unfavorable commercial terms the production of copper concentrate was suspended and the copper circuit put on standby.

Mineral processing basics

Scroll to Top